HomeMy WebLinkAboutMINUTES - 04052005 - 2005 RES 185 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY,CALIFORNIA
Adopted this Resolution on April 5, 2005 by the following vote:
t
AYES: SUPERVISORS GIOIA, PIEPHO, DESAULNIER, AND UILKENA
NOES: NONE
ABSENT: SUPERVISOR FEDERAL GLOVER
ABSTAIN: NONE
RESOLUTION NO.2005/ 185
SUBJECT: Ratifying the prior decision of the Public Works Director to fully close all of South
Wedgewood Road and Dougherty Road between the Bollinger Canyon Road loop
from the original term of May 5,2004 through November 15, 2404 to an additional
term from November lb, 2044 through March 15, 2445 for 24 hours a day,for the
purpose of the necessary grading for gale Ranch Phase III,construction of Stoneleaf
Road (Road Improvement Agreement RA 1152) and Dougherty Road Bridge
replacement(RA 1157), San Ramon(Dougherty Valley) area. (District III)
RC-04-4
The conditions of approval for Subdivision 8306 require Shapell Industries to maintain the
existing Dougherty Road between the Bollinger Canyon Road loop, until the ultimate six-lane
Dougherty Road is constructed through Gale Ranch Phase 4. Grading operations include the
construction of the new StoneleafRoad(RA 1152)from Wedgewood Road to future Ivyleaf Springs
Road at existing Dougherty Road, which will be the interim Dougherty Road. Concurrently, the
existing Dougherty Road Bridge will be replaced with a new 2-lane bridge. To accommodate the
required construction,Daugherty Road needs to be closed for additional four months. Traffic will
use Bollinger Canyon Road, as an alternate route, for the north-south connection.
IT IS BY THE BOARD RESOLVED that permission is granted to Shapell Industries of
Northern California to extend the temporary closure of South Wedgewood Road and Dougherty
Road between the Ballinger Canyon Road loop,from November 16,2004 through March 15,2005
for 24 hours a day, subject to the following conditions:
I hereby certify that this is a true and correct copy of an action
taken and entered on the minutes of the Board of Supervisors on
sG:rrn the date shown.
G:\GrpDera�EngSvc\BO\2005\04.05\Road Closure Extension RC 04-4130.doc
Originator: Public Works(APC) APRIL (}� 2005
Contact: Bob Hendry(335-1375) ATTESTED:
JOAN SWEETEN,Clerk of the Board of Supervisors and County
cc: CHP Administrator
Joe Yee,Maintenance
Sheriff-Patrol Div.Commander
Jennifer White,City of San Ramon
5000 Crow Canyon Road By ,Deputy
San Ramon,CA 94583
RESOLUTION NO.2005/ 185
SUBJECT: Ratifying the prior decision of the Public Works Director to fully close all of South
Wedgewood Road and Dougherty Road between the Bollinger Canyon Road loop
from the original term of May 5,2004 through November 15,2004 to an additional
term from November 16, 2004 through March 15, 2005 for 24 hours a day, for the
purpose of the necessary grading for Gale Ranch Phase M construction of Stoneleaf
Road (Road Improvement Agreement RA 1152) and Dougherty Road Bridge
replacement(RA 1157), San Ramon (Dougherty Valley)area. (District 111)
DATE. .April 5,2005
PAGE: 2
1. Shapell Industries shall maintain a road closure permit for the Dougherty Road Closure and
shall maintain an encroachment permit for all work within the existing public right of way.
2. All work shall comply with road improvement plans: RA 1152 (Stoneleaf Road), and RA
1157(Dougherty Road Bridge Replacement).
3. Traffic will be detoured via Bollinger Canyon Road.
4. All signing to be in accordance with the State of California Manual of Traffic Controls.
5. Shapell Industries of Northern California shall comply with the requirements of the
Ordinance Cade of Contra Costa County.
6. Have on file with the County Public Works Department at the Application and Permit Center
a Certificate of Insurance in the amount of$1,000,400 for Comprehensive general Public
Liability, which names the County as an additional insured.
7. Maintain approval for the closure from the Sheriffs Department, the California Highway
Patrol and the Fire District.
8. Progress reports and construction schedules shall be submitted by the applicant to the Public
Works Department every two weeks during road closure.
RESOLUTION N0. 2005/185