HomeMy WebLinkAboutMINUTES - 05112004 - C2 TO: BOARD OF SUPERVISORS FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR DATE: May 11, 2004 SUBJECT: Approve Project Contingency Fund Increase for the Olympic Boulevard Pedestrian Path Project, Project No. 0662-6R4208-03, Walnut Creek area. District II Specific Request(s)or Recommendation(s)&Background&Justification 1. Recommended Action: APPROVE project contingency fund increase of$6,000 for a new total of$50,933 effective May 11, 2004 in order to compensate the contractor, W.R. Forde Associates, for extra work due to unforeseen conditions. it. Financial Impact: The project contingency funds are currently insufficient to cover the increased cost.The increase in contingency funds will be funded by 58% Transportation Development Agency Grant, 29% Measure C and 13% Drainage Area 15A Funds. Continued on attachment: X yes SIGNATURE: RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON: My _I 4 APPROVED AS RECOMMENDED xx OTHER_ VOTE OF SUPERVISORS xx UNANIMOUS (ABSENT NONE) AYES: NOES: I hereby certify that this is a true and correct copy of an ABSENT: ABSTAIN: action taken and entered on the minutes of the Board of Supervisors on the date shown. Contact: Mike Carlson,(925)313-2320 Orig.Div.: PW(Construction) ATTESTED: MAY 11i 2004 cc: County Administrator Auditor-Controller JOHN SWEETEN, Clerk of the Board of Supervisors and Public Works County Administrator - Construction,P.Edwards - Design - Transportation Engineering Contractor By Deputy PE:tb G:IGRPDATA\CONST,BOQ0041APPROVECONTINGENCYO LYMP 4CBLVD.DOC SUBJECT: APPROVE PROJECT CONTINGENCY FUND INCREASE FOR THE OLYMPIC BOULEVARD PEDESTRIAN PATH PROJECT, PROJECT NO, 0662-6R4208-03, WALNUT CREEK AREA. DISTRICT II DATE: MAY 11, 2004 PAGE 2 OF 2 Ill. Reasons for Recommendations and Background: Additional funding is needed to pay the contractor for extra work that was not part of the original contract. The extra work consisted of transporting and placing fill material that was necessary in order to provide an adequate base for the path. The additional work costs exceed the project contingency fund. Approval of the project contingency fund increase is required to compensate the contractor for the additional work. IV. Consequences of Negative Action: The lack of approval would prevent successful completion of this contract and preclude payment to the contractor for required work.