HomeMy WebLinkAboutMINUTES - 06102003 - C.83 TO: BOARD OF SUPERVISORS 0- Contra
FROM: GEORGE ROEMER . Costa
Senior Deputy County Administrator
County
DATE: June 10, 2003
SUBJECT: JUVENILE HALL EXPANSION PROJECT C.•
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
RECOMMENDATION( :
ACKNOWLEDGE receipt of Report from the County Construction Administrator regarding
construction status at the Juvenile Hall Expansion project.
BACKGROUNDIREASON(S) FOR RECOMMENDATION(S):
At its September 19, 2002 meeting, the California State Board of Corrections chanted Contra Costa
County a nine-month time extension for completion of the Juvenile Hall Expansion. The current
Grant completion deadline is March 31, 2004. This extension was conditioned on Contra Costa
County submitting written progress reports to the State Board on a quarterly basis and attending
each subsequent State Board meeting until construction completion.
The attached report provides the information requested by the State Board's staff. Additionally, this
report responds to the Contra Costa County Grand Jury Report#0104 wherein the Grand Jury
recommends that the County Construction Administrator provide written quarterly progress reports to
the Board of Supervisors and the Probation Department.
CONTI EO ON ATTACHMENT: YES SIGNATURE: w r
k. ECOMMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATIO OF B ITTEE
DROVE OTHER
SIGNATURE(S): '��-�
ACTION BOA N s ,`RECOMMENDED OTHER
VOTE OF SUPERVISORS I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
X UNANIMOUS{ABSENT ? AND ENTERED ON THE MINUTES OF THE
BOARD OF SUPERVISORS ON THE DATE
AYES: NOES: SHOWN,
ABSENT:__ ABSTAIN:_
**District III Seat VACANI** June 101, W03
ATTESTED
CONTACT: JOHN SWEETEN,CLERK OF THE BOARD OF SUPERVISORS
AND COUNTY ADMINISTRATOR
CC:
BY � '
Contra Costa County
Juvenile Hall Expansion
Progress Report for the
State Board of Corrections
May 2003
Prepared by
URS Construction Managers
Project Status
The project is divided into three phases. Phase one includes the relocation of the police
and public entrances to the existing hall along with all site work required to construct the
new parking areas for the facility. Phase two includes the construction of the
Administration, Intake, Sallyport, Kitchen/Laundry, (A, B, C, & S) and Housing units (D,
E, F, & G) (see attached Juvenile Hall Expansion area diagram). Phase three includes
finalizing work to the existing facility to meet building code requirements for occupancy.
The contractor substantially completed phase one and continues to work on phase two.
Phase Two Progress
Administration, Intake,Kitchen/Laundry, and Sally»ort Areas (A, B, C, and Sl
As of May 30, 2003, construction of the Juvenile Hall Expansion is approximately 65%
complete. The wall and floor file along with the ceiling grids and telecommunication
infrastructure are installed on the first floor. The gypsum board walls along with the
security wall surrounding central control on the second floor are installed and painted.
Several exhaust fans are installed on the roof that vents the kitchen on the first floor.
Also, all of the major kitchen appliances are on site with several installed.
Housing nits (D,&Y, and G)
The steel for the roof structure is erected above housing units D & E, and the formwork
for the concrete slabs above the tiers is in place. Also, the installation of the mechanical
ductwork, sprinkler pipes and plumbing for each individual cell in the housing units D &
E are nearly complete. The second floor slab is installed in housing units F & G and the
CMU is erected to the tier levels. Window frames are installed along"S" line along with
the frames at the existing building(Sierra) tie-in.
The Construction Manager continues to monitor the Contractor's Storm Water Pollution
Prevention Plan (SWPPP).
Contra Costa County Juvenile Hall 2 of 9
Schedule
Activity Actual/Estimated Date
Grant Award May 20, 1999
Notice to Proceed May 8, 2001
Building Completion January 2004
Grant Deadline March 2004
After absorbing a four to six month delay during the first year of construction, the
contractor continues to construct the improvements in accordance with the updated
master schedule. This schedule indicates a substantial completion before the grant
deadline of March 2004.
The attached site photographs demonstrate progress as of May 2003.
Grant and .Match Cash Flaw
Period Estimated Actual
2/28/03 to 5/30/03 $3,140,360 $3,746,534
Billings for the quarter are slightly above estimated values. This is attributed to large
equipment procurement and installation.
Attached: Juvenile Hall Expansion Area Diagram
Site Photos
Contra Costa County Juvenile Hall 3 of 9
�lIr 'Pt")lam)f441r) '
} A'
t--
4-.t k- y-,it .dt-,A' -R r ,Z x _ A'.e A•A1 .i-',i t`,q-,if+l
,. I
{
CL
I W
{
_ t�
t
x
Ry
g
Contra Costa County Juvenile Hall 4 of 9
Juvenile Hall Expansion Photos 5/30/03
now
Structural reel roof framing at housing units " a E'
. . \ . ,. . . . f .
? \
» }
CMUnstruicon at tiers in 60 in«units "F + G'
Conti Costa County Juvenile Hall 5 of 9
. �C. � � . ..�
Window frames along line
Exterior decorative CMS at honing units " a E"
Contra Costa County Juv nib/Q! 6 o{9
Sally port and mechanical building
Entry and sally port
Contra Costa County Juvenile Hall 7 of 9
z,�d
II 3 7
V F,
Housing units "F & G"
i
i�
t�
� .3
r '
rl"�
gi=n
b
+qty;
Outdoor recreation space in housing unit"D"
Contra Costa County Juvenile Hall
8 of 9