TO: BOARD OF SUPERVISORS
_
FP,(jM: BARYON J. GILBERT, DIRECTOR OF GENERAL SERVICES �'���� —��•:� Contra
Costa
DATE: Tune 26, 2001 ���..-� � r
c�rr�'c6tiw`�d
County
SUBJECT: APPROVING AND AUTHORIZING EXECUTION OF CHANGE ORDER NO. 3 TO
CONTRACT FOR NEW OFFICE BUILDING AT DELTA FAIR BOULEVARD,
ANTIOCH, FOR EMPLOYMENT AND HUMAN SERVICES DEPARTMENT (WH420F)
SPECIFIC REQUESTS OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. RECOMMENDATION
APPROVE Change Order No. 3 to the Contract dated September 12, 2000 for construction of New
Office Building at Delta Fair Boulevard, Antioch, with Roek Construction, Stockton, California, and
AUTHORIZE the Director of General Services to execute the Change Order, which provides for new
raised crosswalks and revises the layout of the new concrete sidewalk to match that installed for the
adjacent East County Transitional Housing project, and increases the Contract Price by $32,774.34 for a
total Contract Price of$6,269,139.19.
II. FINANCIAL IMPACT
There are sufficient funds in the plant acquisition account to cover Change Order No. 3.
III. REASONS FOR RECOMMENDATIONSBACKGROUND
A. After construction began, the Employment and Human Services Department requested that raised
crosswalks be installed so as to encourage vehicular traffic on the existing access drive to maintain a
safe speed at critical intersections. Change Order No. 3 revises the contract documents to include
those raised crosswalks.
B. After construction began, the County received information from the adjacent East County
Transitional Housing project regarding the location of their sidewalk. Change Order No. 3 revises
the location of this project's sidewalk so that it aligns with the adjacent East County Transitional
Housing project's sidewalk.
CONTINUED ON ATTACHMENT: ✓ YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF 7N LTD I APPROVED AS RECOMMENDED^ OTHER
VOTE OF SUPERVISORS
UNANIMOUS(ABSENT,/'
AYES: NOES:
ABSENTS: ABSTAIN:
MEDIA CONTACT: BARTON J.GILBERT(313-7100)
CC: General Services Department I HEREBY CERTIFY THAT THIS IS A TRUE
Architectural Division AND CORRECT COPY OF AN ACTION TAKEN
AND ENTERED ON THE MINUTES OF THE BOARD
Accounting OF SUPERVISORON THE DATE SHOWN.
File:305-9805/A.5 nn
County Administrator's Office ATTESTED ( t/YLP (9('0 , a b-0)County Counsel JOHN SWEETEN,CLERK F THE BOARD OF
Auditor-Controller SUgRVISORS AND COUNTY DMINISTRATOR
Contractor(Via A/D)
Consultant(Via A/D) BY / DEPUTY
SJ:tb
H:\1998\3059805\8B005121b.doc Page 1 of 1 M382(10/88)
CONTRA COSTA COUNTY
GENERAL SERVICES DEPARTMENT
ARCHITECTURAL DIVISION
1220 MORELLO AVENUE, SUITE 100
MARTINEZ, CALIFORNIA 94553-4711
(925) 313-7200 FAX (925) 313-7299
Effective Date: June 26, 2001
File: 305-9805/C.5.2
CIIANGE ORDER NO. 3
Contract for Construction of. NEW OFFICE BUILDING AT DELTA FAIR BOULEVARD, ANTIOCH FOR
EMPLOYMENT AND HUMAN SERVICES DEPARTMENT
Effective Date of Contract: September 12, 2000
Authorization No.: WH420F
TO: Roek Construction
2580 Teepee Drive
Stockton, CA 95205
You are directed to make the following changes in this Contract:
Item 3-1: Raised Crosswalks (000091):
Furnish and install all labor and materials required to provide two raised crosswalks and to revise
concrete walks in accordance with the attachment. These raised crosswalks are required to provide
continuous ADA-compliant walk access between Delta Fair Boulevard and the adjacent transitional
housing project, and also to encourage driving at safe speeds on the existing access drive.
ADD: $32,774.34
REASON FOR CHANGE:
( ) Design Deficiencies
(x) Criteria Change by End-Users
( ) Differing Site Conditions
ATTACHMENTS:
.item 3-1: Drawing: ASK-416-1 through ASK-4164, "Concrete Bridge/Speed Bump", four sheets, 8%2x11
inches, dated revised April 20, 2001.
The Original Contract Price was...................................................................................................$ 6,097,130.00
Net Change by previously approved Change Orders....................................................................$ 139,234.85
The Contract Price before this Change Order was........................................................................$ 6,236,364.85
The Contract Price will be increased by this Change Order..................................................$ 32,774.34
The new Contract Price, including this Change Order will be.....................................................$ 6,269,139.19
The Completion Time will remain unchanged. The Contract Completion Date as of the date of this Change
Order therefore is October 7, 2001.
RECOMMENDED BY:
Consulting Architect Project Manager Architectural Services Manager
Not valid until signed by both the Public Agency and the Contractor. By signature below, Contractor indicates
acceptance of price stated herein as full compensation for all direct and indirect costs for all work described
above, and as full compensation for any effects this change may have on the project in its entirety and/or on the
time required to complete the project.
PUBLIC AGENCY: CONTRACTOR:
By By
Contra Costa County Date Authorized Officer Date
Director of General Services