TO: BOARD OF SUPERVISORS
FROM: MAURICE M. SHIU, PUBLIC WORKS DIRECTOR
DATE: March 6, 2001
SUBJECT: State Route 4 East / Railroad Avenue to Loveridge Road. Pittsburg area.
Project No.: 4660-6X4287 Task: ACQ Account: 3540
CDD — CP#: 00-85
SPECIFIC REQUEST(S)OR Rt-COMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
A. APPROVE Right of Way Contract and ACCEPT Grant Deed dated February 21, 2001 from
Roland S. Stewart.
B. AUTHORIZE Public Works Director to execute said Right of Way Contract on behalf of the
County.
C. APPROVE payment of $156,000 for said property rights and AUTHORIZE the Auditor-
Controller to issue a check in said amount payable to Placer Title Company, 1.981 North
Broadway, Suite 100, Walnut Creek, CA 94596, Escrow No. 6153857 to be forwarded to
the Real Property Division for delivery.
D. DIRECT the Real Property Division to have the above referenced Grant Deed recorded in
the Office of the County Recorder. (�
Continued on Attachment: X SIGNATURE:
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON March 6, 2001 APPROVED AS RECOMMENDED x_ OTHER_
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT )
AYES: NOES: I HEREBY CERTIFY THAT THIS IS A TRUE AND CORRECT COPY
ABSENT: ABSTAIN: OF AN ACTION TAKEN AND ENTERED ON THE MINUTES OF
THE BOARD OF SUPERVISORS ON THE DATE SHOWN.
LLO:eh ATTESTED March 6 2001
G:\GrpData\RealProp\2001-Files\BOs&RES\B021ove.doc ?
JOH SWEETEN CLERK OF THE BOARD AND
Orig. Div: Public Works (R/P) CO Y ADMI IOATOR
Contact: Dick Awenius (313-2227)
cc: County Administrator BY DEPUTY
Auditor-Controller(via R/P)
P. W.Accounting
Recorder(via R/P)
y
State Route 4 East / Railroad Avenue to Loveridge Road. Pittsburg area.
March 6, 2001
Page 2
11. Financial Impact:
The activity is funded by Contra Costa Transportation Authority (100%)
III. Reasons for Recommendations and Background:
These property rights are required to provide for advance right-of-way acquisition of properties
with willing sellers for the possible construction of an expanded freeway along the southern
portion of State Route 4 in the City of Pittsburg.
IV. Consequences of Negative Action:
Delay in approving the project will result in a delay of design and construction and may jeopardize