HomeMy WebLinkAboutMINUTES - 07112000 - SD2 TO: BOARD OF SU PERVISORSIREDEVELOPMENT AGENCY
a. Contra
FROM: DENNIS M. BARRY, AICP h Costa
COMMUNITY DEVELOPMENT DIRECTOR County
r <
DATE: JULY 11, 2000
SUBJECT: DRAINAGE AREA 48B IMPROVEMENTS
SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
AUTHORIZE the Deputy Director — Redevelopment, on behalf of the Contra Costa County
Redevelopment Agency, to execute a contract between the County Redevelopment Agency
and the Contra Costa County Flood Control District for the design of Drainage Area 48B
Improvements in the Bay Point Redevelopment Project Area.
AUTHORIZE the Deputy Director r Redevelopment, on behalf of the Contra Costa County
Redevelopment Agency, to enter into a standard developer reimbursement agreement with the
Contra Costa County Flood Control District for funding of Drainage Area 48B Improvements in
the Bay Point Redevelopment Project Area.
CONTINUED ON ATTACHMENT: X YES SIGNATURE4--F
_RECOMMENDATION OF COUNTY ADMINISTRATORIEXECUTIVE DI COMMENDATION OF BOARD/AGENCY COMMITTEE APPROVE O
SIGNATURES :
ACTION OF BOARD/REDEVEOPMENT AGENCY ON """ PPROVED AS
RECOMMENDED e"MER
VOTE OF SUPERVISORSICOMMISSIONERS I HEREBY CERTIFY THAT THIS IS A TRUE AP
UNANIMOUS(ABSENT,� iy`.;� CORRECT COPY OF AN ACTION TAKEN At
AYES: NOES: ENTERED ON THE MINUTES OF THE BOARD t
ABSENT:_ABSTAIN: SUPERVISORS/REDEVELOPMENT AGENCY ON TI
DATE SHOWN. ,
Source: Maureen Toms 335-1250 ATTESTED
cc: Community Development Department PHIL BATCMWOR, AEkK OF THE BOARD
Redevelopment Agency SUPERVISORBTAGENCY SECRETARY
County Administrator
Flood Control District
Public Works Department BY � � EPUTy
County Counsel
Auditor-Controller '
BOARD OF SUPERVISORS/REDEVELOPMENT AGENCY
JULY 11, 2000
DRAINAGE AREA 48B IMPROVEMENTS
AUTHORIZE the Chief Engineer of the Flood Control District, on behalf of the Contra Costa
County Flood Control District, to execute a contract between the Flood Control District and the
County Redevelopment Agency for the design of Drainage Area 48B Improvements in the Bay
Point Redevelopment Project Area.
AUTHORIZE the Chief Engineer of the Flood Control District, on behalf of the Contra Costa
County Flood Control District, to enter into a standard developer reimbursement agreement
with the County Redevelopment Agency for funding of Drainage Area 48B Improvements in
the Bay Point Redevelopment Project Area.
FISCAL IMPACT
The estimated cost of the project is $200,000. No General Funds would be utilized.
Redevelopment Funds will be used for the improvements. Drainage Area 48B funds will be
used to reimburse the Redevelopment Agency when the funds become available.
BACKGROUND/REASONS FOR RECOMMENDATIONS
A major activity in Bay Point is to improve and upgrade the existing infrastructure. Flow is
constricted at the 60-inch culvert under Port Chicago Highway, resulting in flooding
upstream. Property owners in the Shore Acres area, upstream of the culvert have
experienced flooding problems. Replacement of the 60-inch culvert with an 84-inch culvert
would alleviate the flooding problems upstream of the culvert.
Currently, Drainage Area 48B does not have the funds available to pay for the proposed
improvements. These funds will become available when drainage area fees are collected
for development on the south side of State Route 4. The Bay Point Project Area
Committee has recommended that the Redevelopment Agency pay for the improvements
and enter into a reimbursement agreement with the Flood Control District.