HomeMy WebLinkAboutMINUTES - 07141998 - C5-C7 TO:x BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July 14, 1998
SUBJECT: Determine the Meed to Continue the Emergency Action Regarding the Repair of the
Alhambra Valley Road Bank Erosion at Pinole Creek, Pinole Area
Project No: 0672-6R6356.98
1. Recommended Action:
DETERMINE that there is a need to continue the emergency action taken by the Board of
Supervisors on April 14, 1998 pursuant to Public Contract Code Sections 22035 and 22051, to
repair the Alhambra Valley Road Bank Erosion at Pinole Creek, Pinole',Area.
If. Financial impact:
There is no impact to the general fund. Plans, specifications and engineer's estimate are
complete. The preliminary cost estimate for the project indicates a construction cost of$110,000.
Project construction should begin in late July.
Continued on Attachment:X SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
—APPROVE —OTHER
SIGNATURE(S):
ACTION OF BOARD ZSR u y T4, 1918 APPRO ED A3 RECOMMENDED
VOTE OF SUPERVISORS
X UNANIMOUS(ABSENT Nona, }
AYES: NOES: i hereby certify that this is a true and correct
ABSENT: ABSTAIN: copy of an action taken and entered on the
minutes of the Board of Supervisors on the
MM:IIg date shown.
g:tdesignibotAlValPinole7-14.doc ATTESTED:
PHIL BATC ELL , Clerk of the Board
cnDiv:
Iant13-otcWorks
32225) of 8 Oervisors and Cot nty Administrator
cc: Auditor/Controller
County Counsel By ,,?,���,: Deputy
Construction Div,A.Bruno
Maintenance Div.
Transp.Engineering
Determine the Need to Continue the Emergency Action Regarding the Repair of the Alhambra Valley Road Bank
Erasion at Pinole Creek, Pinole Area
July 94, 1998
Page Two
III. Reasons For Recommendations And Background:
The excessive rains of February 2, 1998 and debris in an unmaintained creek, caused storm
waters from Pinole Creek to flow over Alhambra Valley Road, washingout the embankment on
the far side of the crossing.
Alhambra Valley Road, in this area, accommodates more than 4,200 vehicles per day. If the Aide
is allowed to progress and a road closure becomes necessary, east/west traffic between Central
and West County along this corridor would no longer be possible. Immediate repair of this
washout is necessary to assure the road's stability.
Since Alhambra Valley Road is included in the federal highway system and with the federal
designation of Contra Costa County as a disaster area, it qualifies for Federal Highway
Administration funds to make the repairs. To receive 100%funding for this repair, the work must
be completed within 180 days of the February 2, 1998 emergency declaration. After that time,
only 88.5% financing is available and the County will have to pay the 11.5% matching funds.
If we were to follow our normal construction contract advertisement and approval process, the
slide repair could not begin until early September. Pursuant to provisions of Sections 22035 and
22050 of the Public Contract Code, when the appropriate findings of an emergency are made by
the Board of Supervisors, the normal bidding procedures are waived and repairs can begin
immediately.
We are, therefore, recommending that the Board continue the emergency action and direct the
Public Works Director to proceed with the project and enter into any necessary contracts to
ensure completion of the repair in the most expeditious manner.
IV. Conseguences of Negative Action:
Nonconcurrence of the above recommendation will significantly delay repair of the slide which
would result in potential road failure and road closure, and resulting in a loss of 100% funding for
the repair from the federal government.
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July 14, 1998
SUBJECT: DETERMINE the Need to Continue the Emergency action Regarding the Repair of the
Alhambra Valley Slide, 2.7 miles east of Bear Creek Road, Pinole area.
Project No.: 0672-6R6355.98
Specific Request(s) or Recommendation(a) & Background & Justification
L RECOMMENDED ACTION:
DETERMINE that there is a need to continue the emergency action taken by the Board of
Supervisors on April 14, 1998, pursuant to Public Contract Code Sections 22035 and 22050, to
repair the Alhambra Valley Road Slide, 2.7 miles east of Bear Creek Road, Pinole area.
II. FINANCIAL IMPACT:
There is no impact to the general fund. Plans, specifications and engineer's estimate are 95%
complete. The preliminary cost estimate for the project indicates a construction cost of$9071•+"}00.
Project construction should begin in late July. ,I ?f
Continued on Attachment:_x SIGNATURE: . "
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
—APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON duly 14, 1998 APPROVED AS RECOMMENDED�40=4_..
VOTE OF SUPERVISORS
X UNANIMOUS(ABSENT None l
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct
BF:drg copy of an action taken and entered on the
g:\dssignV301alhvly&bear cmak7-#4..98.doc minutes of the Board of Supervisors on the
date shown.
Ong.Div: Public Works(Design Division) x
Contact: M.Morton(313-2225) ATTESTED: � 5}
cc: CountyArr. E.KevorAdministrator PEAL BATCH LGI Cierk Ci'ins Board
Attu: E.Kuavor
Auditor-Controller of Supervisors and County Administrator
PW Accounting
Construction A t
Community Development By ,i.L 1. 'I rK+� $ Deputy
Maintenance
County Counsel
DETERMINE the Need to Continue the Emergency action Regarding the;Repair of the
Alhambra Valley Slide, 2.3 miles east of Bear Creek Road, Pinole area
Page 2
July 14, 1998
111. Reasons for Recommendations and Background:
The storms of February 2, 1998 and associated high floods in Vaca Creek caused a slide under
cutting a section of Alhambra Valley Road at a point approximately2.7 miles east of the
intersection with Bear Creek Road.
Alhambra Valley Road in this area accommodates more then 4,200 vehicles per day. If the
slide is allowed to progress and a road closure becomes necessary, eatlwest traffic between
Central and West County along this corridor would no longer be possible.
Since Alhambra Valley Road is included in the federal highway system and with the federal
designation of Contra Costa County as a disaster area, it qualifies for Federal Highway
Administration funds to make the repairs. To receive 100% funding for this repair, the work
must be completed within 180 days of the February 2, 1998 emergency declaration. After that
time, only 88.5% financing is available and the County will have to pay the 11.5% matching
funds.
If we were to follow our normal construction contract advertisement and approval process, the
slide repair could not begin until early September. Pursuant to provisions of Sections 22035
and 22050 of the Public Contract Code, when the appropriate findings of an emergency are
made by the Board of Supervisors, the normal bidding procedures are waived and repairs can
begin immediately.
We are, therefore, recommending that the Board continue the emergency action and direct the
Public Works Director to proceed with the project and enter into any nece*sary contracts to
ensure completion of the repair in the most expeditious manner.
IV. Consequences of Negative Action.
Non-concurrence of the above recommendation will significantly delay repair of the slide which
would result in potential road failure and road closure, and resulting in a loss of 100% funding
for the repair from the federal government.
TO: BOARD OF SUPERVISORS tf
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July 14, 1998
SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of the Fish
Ranch Road Nide, Orinda area.
Project No: 0672-6R6346
1. Recommended Action:
DETERMINE that there is a need to continue the emergency action taken by the Board of
Supervisors on March 24, 1998, pursuant to Public Contract Code Sections 22035 and 22050,
to repair the Fish Ranch Road Slide, Orinda area.
II. Financial lmpact:
There is no impact to the general fund. Plans, specifications and engineer's estimate are
complete. The project is currently under construction. The expected contract cost based on the
low bid is $684,651.
Continued on Attachment:X SIGNATURE;
k
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURES :
ACTION OF BOARD ON Judy 14, 1998 APPROVED A9 RROMMENSE5
VOTE OF SUPERVISORS
_ UNANIMOUS{ABSENT
AYES: NOES. I hereby certify that this is a true and correct
ABSENT: ABSTAIN: copy of an action taken and entered on the
minutes of the Board of Supervisors on the
date shown.
MM:IRATTESTED:PDATA1oESIGMPHIL_BABOtFISHRANCH7-14,DOC BTCH C)
G::iCV� k
R, lark of the Board
Orig.Div: Public works(Design) of Supervisors and County Administrator
Contact: Melissa Morton(313-2225)
cc: Auditor/Controller By r Deputy
County Counsel
Construction civ.-R.Bruno
Maintenances Div.
Transp.Engineering
Determine the Need to continue the Emergency Action Regarding the Repair of the Fish Ranch Road Slide, Orinda
Area
.lune 23, 1998
Page Two
Ill. Reasons For Recommendations And Background:
Fish Ranch Road has been damaged by a landslide which affected the uphill, north bound lane and
approximately three feet of the downhill, south bound lane. The Aide scarp has dropped
approximately one foot below road surface, creating a dangerous condition which necessitated
closing the road February 21, 1998. The Public Works Department was able to make temporary
repairs to the slide damaged roadway which facilitated opening the south bound lane on March 9.
Slide movement has slowed, but further movement and increased pavement damage is expected
over the next few weeks as groundwater continues to accumulate at the slide site. A small Aide
along the edge of the north bound lane approximately half a mile from the larger site will also be
repaired as part of this project. Fish Ranch Road carries 8,000 vehicles per day and this traffic has
been severely hampered by the closure of the road from February 21 to March 9, and the
subsequent closure of the north bound lane to date.
Since Fish Ranch Road is included in the federal highway system and with the federal designation
of Contra Costa County as a disaster area, it qualifies for Federal Highway Administration funds to
make the repairs. To receive 100% funding for this repair, the work must be completed within'180
days of the February 2, 1998 emergency declaration. After that time, only 88.5% financing is
available and the County will have to pay the 11.5% matching funds.
If we were to follow our normal construction contract advertisement and approval process, the Aide
repair would not have begun until early September. Can March 24, 1998, pursuant to provisions of
Sections 22035 and 22050 of the Public Contract Code, the Board of Supervisors declared an
emergency for the slide repair, allowing the normal bidding procedures to be waived and repairs
to begin immediately.
We recommend that the Board continue the emergency action to ensure'completion of the repair
in the most expeditious manner.
IV. Conseauence.s of Negative Action:
Non-concurrence of the above recommendation will significantly delay' repair of the roadway,
prolonging impacts to traffic flow, and resulting in a loss of 100% funding for the repair from the
federal government.