TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: JUNE 17, 1997
SUBJECT: DA57 DETENTION BASIN PRIMARY SPILLWAY -MARTINEZ AREA
Project No.: 7538-6D8463 Task: ACQ Account: 3540
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
1. Recommended Action:
A. APPROVE Relocation Agreement and ACCEPT Right of Entry and Release of Claim of
Indemnity from the Burlington Northern & Santa Fe Railway Company.
B. AUTHORIZE Public Works Director to execute said Relocation Agreement & Release of
Claim of Indemnity on behalf of the County.
C. APPROVE payment of $250.00 for said property rights and AUTHORIZE the Auditor-
Controller to issue a check in said amount payable to the Burlington Northern'& Santa Fe
Railway Company, to be forwarded to the Real Property Division for delivery.
D. DIRECT the Real Property Division to have the above-referenced Relocation Agreement
recorded in the office of the County Recorder.
Continued on Attachment: X SIGNATURE: t -��w
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON �wY.J- I? 1197 APPROVED AS RECOMMENDED OTHER
VOlE OF SUPERVISORS —
_,� UNANIMOUS(ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: €
KAL:gpp I
g:\realprop197-61BO217-6.wpd ( i hereby certify that this is a true and correct copy of
Orig. Div: Public Works(R/P) i an action taken and entered on the minutes of the
Contact: Karen A.Laws(313-2228) ` Board of Supervisors on the date shown.
1-7 cc: County Administrator ATTESTED: 19 *�*
Auditor-Controller(via R/P) PHILB CHELOA,Clerk of the Board
P.W.Accounting of Supervisors and County Administrator
Recorder(via RIP) '
gy, J 11 0 1 CQ .6 ,Deputy
i
S
June 17, 1997
DA57 Detention Basin
Page Two
II. Financial Impact:
Payment of$250.00 from DA57 funds.
III. Reasons for Recommendations and Background:
These property rights are required for the DA57 Detention Basin Primary Spillway project in
accordance with the approved plans and specifications.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow construction in accordance with the
approved plans and specifications.