HomeMy WebLinkAboutMINUTES - 03111997 - C53 .,Z C �3 TO: BOARD OF SUPERVISORS FROM: , J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: MARCH 11, 1997 SUBJECT: Determine the Need to Continue the Emergency Action Regarding the Repair of"Hill 310" Land Creep, Bay Point Project No.: 4500-6G5094 SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION I. Recommended Action: DETERMINE that there is a need to continue the emergency action taken by the Board of Supervisors on June 4, 1996 pursuant to Public Contract Code Sections 22035 and 22050, to repair the "Hill 310" Land Creep, Bay Point. II. Financial Impact: Total cost of repairs cannot be fully determined at this time, but staff is developing an estimate for completion of the repair. III. Reasons for Recommendations and Background: A. On February 26, 1996, Public Works and Building Inspection were notified that cracks were occurring in Beaulieu Court. The County hired a geotechnical firm to identify the cause of the slide, and recommend and direct remedial actions to mitigate land movement. B. On March 19, 1996 the Board of Supervisors concurred in the County Administrator's proclamation of a local emergency. C. On June 4, 1996 the Board of Supervisors declared an emergency and authorized the Public Works Director to proceed in the most expeditious manner to repair the area subject to creep. Continued on Attachment: X SIGNATURE: 1 Yl _RECOMMENDATION OF COUNTY ADMINISTRATOR _RECOMMENDATION OF BOARD COMMITTEE —APPROVE —OTHER SIGNATURE(S): / ACTION OF BOARD ON //, /9 77 APPROVED AS RECOMMENDED_OTHER VO�OF SUPERVISORS ��// UNANIMOUS (ABSENT ) AYES: NOES: ABSENT: ABSTAIN: JPM:tt g\const\B O\H 310-11.t3 Orig.Div: Public Works(Construction) Contact: Joseph P.Murphy(313-2320) 1 twit caf*that this Is a true and correct f70py of �n action taken and entered on the mtnutaa TI198 cc: CAO board of Supemso on the d>t�:shown. Auditor/Controller p County Counsel at 8 BATCHELOR d6ZIy odmIn GMEDA Design Div. Construction Div.-R.Bruno (Original to file) �, o xa ppm Maintenance Div. Contractor Determine the Need to Continue the Emergency Action Regarding the Repair of"Hill 310"Land Creep March 11, 1997 Page Two III. Reasons for Recommendations and Background (cont'd): D. Repair status: The prime contractor, Judd Drilling, Inc. has retained the Walter C. Smith Company to complete the critical directional boring. The estimated completion date of this project continues to be mid- March. IV. Consequences of Negative Action: This project is part of a series of sequential construction projects that will stabilize the landslide and restore the streets and sidewalks of the affected neighborhood. A negative action would stop this process.