HomeMy WebLinkAboutMINUTES - 06251996 - C85 TO: BOARD OF SUPERVISORS `'; Contra
Costa
FROM: HARVEY E. BRAGDON
County
DIRECTOR OF COMMUNITY DEVELOPMENT �N� %� .�`,/
.... --•K.Ct
DATE: June 25, 1996
SUBJECT: Ratification of the Zoning Administrator's Decision Regarding Shell Oil
Company's Compliance with Conditions of Approval (LUP 2009-92)
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
Ratify the Zoning Administrator' s decision that Shell Oil Company
has complied with Condition of Approval #35B for the Cooling Water
Tower, the Lube Hydrotreater No. 2, the Pentane Spheres, the
Cracked Gasoline Depentanizer, the Nitrogen Supply System, the
Flare Gas Recovery Unit and the Isomerization Unit.
FISCAL IMPACT
None.
BACKGROUND/REASONS FOR RECOMMENDATIONS
When the Board of Supervisors approved the Land Use Permit for
Shell Oil Company' s Clean Fuels Project (County LUP #2009-92) , the
Board specified that the Zoning Administrator' s decision regarding
several conditions of approval be placed on the Board' s consent
calendar for ratification. As directed by the Board at the October
4, 1994 meeting, the County Zoning Administrator decisions
discussed herein have been placed on the Zoning Administrator' s
agenda for June 24, 1996. Any comments received at the meeting will
be forwarded to the Board.
CONTINUED ON ATTACHMENT: XX YES SIGNATUREZ,..�Gv. &76-( 767
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE (S)
ACTION OF BOARD ON June 25, 1996 APPROVED AS RECOMMENDED x OTHER
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A
X UNANIMOUS (ABSENT TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVISORS ON THE DATE SHOWN.
Contact: Catherine Kutsuris (510/335-1237) ATTESTED June 25, 1996
cc: Community Development Department (CDD) PHIL BATCHELOR, CLERK OF
Shell Oil (via CDD) THE BOARD OF SUPERVISORS
AND COUNTY ADMINISTRATOR
BY DEPUTY
cox\aw 10
ck(2)\sh16-25.bo
Board Order
June 25, 1996
Page 2
Condition of Approval #35B - Compliance with Noise Standards :
Permit Condition #35A requires the submittal of detailed noise
level calculations to demonstrate that the unit to be constructed
will comply with the noise performance standard (77 dBA when
measured five feet above the ground and 100 feet from the
equipment) . Permit condition #35B requires that once a unit is
operational, additional noise monitoring be completed to verify
that noise from the operating unit meets the standard. Shell Oil
has submitted the results of their noise monitoring which
demonstrated that the seven units identified in Recommendation #1
meet the noise standards .
COK\aw