Loading...
HomeMy WebLinkAboutMINUTES - 05071996 - C2 0. 2 TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: May 7, 1996 SUBJECT: Approval of Contract Change Order No. 24 for the Appian Way Triangle project, Project No. 0662-6R4056-88, EI Sobrante area. Specific Request(s)or Recommendation(s)&Bac group &Justification I. Recommended Action: APPROVE Contract Change Order No. 24 in the approximate amount of $5,000.00 and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, Joe Carone, Inc. for changes in contract and extra work quantities. II. Financial Impact: The project contingency funds are sufficient to cover the change order costs. The source of funds is State and Federal funds (60%), EI Sobrante A.O.B. (30%) and West County Wastewater District (10%). III. Reasons for Recommendations and Background: The cumulative total of Contract Change Orders Nos. 1 through 24 exceeds $25,000.00, requiring Board approval. Change Order 24 balanced all contract bid items and extra work. IV. Consequences of Negative Action: The lack of approval would preclude payment for work that was performed in good faith. Continued on attachment: _yes �/�`Y ✓�-�-� SIGNATURE: RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON: MaT7��gg� APPROVED AS RECOMMENDED / X OTHER VOTE OF SUPERVISORS X UNANIMOUS (ABSENT AYES: NOES: ABSENT: ABSTAIN: Contact: Joseph P. Murphy, (510) 313-2321 Orig. Div.: PW(Constr) cc: County Administrator Auditor-Controller Public Works Ihereby ccrtifythat thtsIsatrue and eorrectCopy of - Accounting, R. Gilchrist an action taken and entered on the minutes of the - Construction, R. Bruno Board of supervisors on the date shown. n ATTESTED' Z-, 1 Desi a— —. 9 PHIL BATA.Clerk of the Board Contractor of supervisors and county Administrator RB:tt By Deputy g:\CONST\BO\AWT-7.t5