HomeMy WebLinkAboutMINUTES - 03261996 - C30 TO: BOARD OF SUPERVISORS
Contra
FROM: HARVEY E. BRAGDON Costa
DIRECTOR OF COMMUNITY DEVELOPMENT
County
DATE: MARCH 26, 1995
SUBJECT: CONTRACT FOR ENVIRONMENTAL IMPACT REPORT FOR THE PROPOSED COWELL
RANCH PROJECT - PHASE II (CONTRACT NUMBER 45673-00)
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
Authorize the Director of Community Development to execute a second contract
with the firm of Wagstaff & Associates in the amount of $231, 696. 00 for work on
Phase II of the Cowell Ranch General Plan Amendment EIR Project.
FISCAL IMPACT
None. All costs are covered by applicant fees.
BACKGROUND/REASONS FOR RECOMMENDATIONS
On August 10, 1993, the Board approved a contract with the firm of Wagstaff &
Associates for the preparation of an EIR on the Cowell Ranch Project. That
contract has now been closed. This second contract for the additional work
required is referred to as Phase II, and is necessary to successfully complete
this project.
CONTINUED ON ATTACHMENT: YES SI
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDAT F COMMITTEE
APPROVE OTHER
SIGNATURE(S) :
ACTION OF BOARD ON March 26, 1996 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A
X UNANIMOUS (ABSENT I TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVISORS ON THE DATE SHOWN.
Contact: Jim Cutler (510/335-1236) ATTESTED March 26, 1996
cc: Community Development Department (CDD) PHIL BATCHELOR, CLERK OF
Judy Coons, Auditor-Controller THE BOARD OF SUPERVISORS
County Administrator AND COUNTY ADMINISTRATOR
David Joslin, CDD
Wagstaff & Associates,
Consultant (via CDD)
BY , DEPUTY
DWJ: \
board\96\Cowe113.EIR