HomeMy WebLinkAboutMINUTES - 02061996 - C2 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: February 6, 1996
SUBJECT: Approval of Contract Change Order No. 4 for the San Pablo Dam Road Slide Repair at
Station 252+00, Project No. 0672-6R6523-93, EI Sobrante area.
Specific Request(s)orRecommendation(s)&Background&Justification
I. Recommended Action:
APPROVE Contract Change Order No. 4 in the approximate amount of $8,000.00 and
AUTHORIZE the Public Works Director to execute it in order to compensate the contractor,
Kulchin-Condon and Associates, for changes in contract bid quantities.
If. Financial lmpact:
The project contingency funds are sufficient to cover the change order costs. The source of funds
is Federal and Storm Damage Repair Funds (65.8%) and County Road Funds (34.2%).
III. Reasons for Recommendations and Background:
The cumulative total of Contract Change Orders Nos. 1 through 4 exceeds $25,000.00, requiring
Board approval. Contract''Change Order No. 4 balanced estimated contract quantities.
IV. Consequences of Negative Action:
The lack of approval would preclude payment for work that was performed in good faith.
Continued on attachment: _yes •�
SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: APPROVED AS RECOMMENDED OTHER
VOTF.OF SUPERVISORS
UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
Contact: Joseph P. Murphy, (510) 313-2321
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works
- Accounting, R. Gilchrist
- Construction, R. Bruno
- Design
Contractor i hereby Cern
ORIGINAL- Project File en an entered on the corrM minutes opy�
1 an action taken and entered on the minutes of the
Board of Supe isors on the date shown.
DG:tt ATTESTED:
g:\CONST\BO\SPDR-6A.t2 P IL of 5�, ry�g��E�dRC�I k of th Board
Administrator
By
Oeputy