HomeMy WebLinkAboutMINUTES - 06201995 - D6 D.6
The Board of Supervisors of Contra Costa County, California
Adopted this Order on_June 20, 1995, by the following vote:
AYES: Supervisors Rogers, Smith, DeSaulnier,Torlakson, Bishop
NOES: None
ABSENT: None
ABSTAIN: None
SUBJECT: Decision Continued on Discovery Bay West Project, 2963-RZ
The Board on June 20, 1995, deferred to this day to consider certification of the Final Environmental
Impact Report(EIR), adopt findings and the mitigation monitoring program,and adopt Ordinance No. 95-28
giving effect to rezoning 2963-RZ, and approve preliminary Development Plan with conditions for
approximately 21'000 residential units, marina, lakes, park areas, a school area,a fire station,open space
areas, a commercial recreational area and other landscaped areas for the Discovery Bay West Project,
Hofmann Construction Company(applicant)and Hofmann Construction Company and Edna M. Fallman
(owners), Discovery Bay area.
Additional review time being required, IT IS BY THE BOARD,ORDERED that decision on this matter is
CONTINUED to June 27, 1995, at 9:45 a.m.
I hereby certify that this is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: June 20, 1995
PHIL BATCHELOR,Clerk of the Board of
Supervisors and County Administrator
By Deputy Clerk
CC: Director,CDD
Director,GMEDA
County Counsel
•• - Contra
-.+ TO: BOARD OF SUPERVISORS _ Costa
FROM: HARVEY E. BRAGDON ,. z County
DIRECTOR OF COMMUNITY DEVELOPMENT 04
DATE: June 6, 1995
SUBJECT: BEARING ON THE HOFMANN DISCOVERY BAY NEST PROJECT, REZONING 2963-RZ,
TO REZONE APPROXIMATELY 756.19 ACRES OF LAND TO THE PLANNED UNIT
DISTRICT FOR 21000 RESIDENTIAL UNITS, A 10 ACRE SCHOOL SITE,A 6.5 ACRE
PARR SITE, A COMMERCIAL RECREATIONAL CENTER, A SENIOR HOUSING VILLAGE,
A MARINA, LAKES, FIRE STATION, OPEN SPACE AREAS, TRAILS AND OTHER
LANDSCAPED AREAS.
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) i BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
1. Accept as adequate and in compliance with CEQA the previously
certified Final Environmental Impact Report and Addendum.
2. Approve Rezoning 12963-RZ along with the preliminary
development plan, subject to conditions as recommended by the
East County Regional Planning Commission and as amended
(Attachment A) .
J. Adopt the Final EIR and Addendum and CEQA Findings (Attachment
B) and approve the related Mitigation Monitoring Program
(Attachment C) .
4. Adopt the East County Regional Planning Commission's Findings
as set forth in Resolution 014-1995 as basis for the Board's
determination for this action.
5. Adopt the ordinance giving effect to the aforesaid rezoning.
6. Direct Staff to post the Notice of Determination with the
County Clerk and the Office of Planning and Research for the
above actions.
FISCAL IMPACT
Covered by developer fees.
CONTINUED ON ATTACHMENT: _ CIS YES SIGNATURE
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITT E
APPROVE OTHER
SIGNATURE(S) :
ACTION OF BOARD ON APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A
UNANIMOUS (ABSENT TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVISORS ON THE DATE SHOWN.
Coatact:Art Beresford 646-2031 -ATTESTED
cc: Community Development Department PHIL BATCHELOR, CLERK OF
Judy Coons, Auditor-Controller THE BOARD OF SUPERVISORS
CAO AND COUNTY ADMINISTRATOR
David Joslin, CDD
SEE PAGE TWO FOR ADDITIONAL CC'S BY , DEPUTY
AB:df
PAGE TWO
BACKGROUND/REASONS FOR RECOMMENDATIONS
On May 23, 1995, the Board closed the hearing on 2963-RZ (Discovery
Bay West) and directed staff to prepare final documentation for the
rezoning project.
The Developer and the interested school districts were to provide
documentation that suitable school mitigation agreements had been
reached. The Board is to then approve the project with revised
conditions (Attachment A) and adopt the Final CEQA Findings and the
EIR Addendum (Attachment B) and the Mitigation Monitoring Program
.(Attachment C) .
cc: Hofmann Company
County Counsel
Sheriff-Coroner
Public Works Department
Discovery Bay MAC
Byron MAC
Knightsen Town Council
East Bay Municipal Utility District
Health Services Department
Hazardous Materials Division
East County Regional Planning Commission
East Contra Costa Irrigation District
Byron-Bethany Irrigation District
East Bay Regional Park District
A-ENDA DATE - (S ITEM N0. v '
BACKGROUND NOT AVAILABLE AT
THE TIME AGENDA PACKET COMPILED
INFORMATION FOR THIS ITEM PREVIOUSLY
FURNISHED
ORAL REPORT TO BE GIVEN AT BOARD MEETING
ERROR IN NUMBERING AGENDA ITEM
DELETED
DOCUMENTS ON FILE WITH
CLERK
i