HomeMy WebLinkAboutMINUTES - 06201995 - 1.7 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: JUNE 20, 1995
SUBJECT: STATE HIGHWAY 4/13AILEY ROAD INTERCHANGE - BAY POINT AREA
Project No.: 4660-6X4158 Task: ACID Account: 3540
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
A. APPROVE Full & Final Settlement Agreement and Release dated June 20, 1995, from
Sierra Pacific Properties, Inc.
B. AUTHORIZE Public Works Director to execute said Settlement Agreement on behalf of the
County.
C. APPROVE payment of$24,912.85 for said property rights and AUTHORIZE the Auditor-
Controller to issue a check in said amount payable to Sierra Pacific Properties, Inc.,
forwarded to the Real Property Division for delivery.
Continued on Attachment: X SIGNATURE:
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON yO 1 X19 APPROVED AS RECOMMENDED OTHER_
V7OF SUPERVISORS
UNANIMOUS(ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
KAM:glo
g:\realprop\temp\B0220.t6
Orig. Div: Public Works(R/P) I hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
Contact: Karen McNamer(313-2228) Board of Supe; shows.A "
on the date
cc: County Administrator
Auditor-Controller(via R/P) To-
P.W.Accounting PHIL ELOR,Clerk of the Board
of Supervisors and County Administrator
By C)e�uty
II. Financial Impact:
Payment of $24,912.95 from State Highway 4/13ailey Road Interchange funds which are 100%
reimbursable from Contra Costa Transit Authority.
III. Reasons for Recommendations and Background:
This Agreement is required for the State Highway 4/13ailey Road Interchange project in
accordance with the approved plans and specifications.
IV. Consequences of Negative Action:
The County will fail to complete its financial and contractual obligations as outlined in said
agreement.