Loading...
HomeMy WebLinkAboutMINUTES - 06131995 - 1.5 (2) T0: BOARD OF SUPERVISORS 5. .L.. _ Contra FROM: Costa PHIL BATCHELOR, COUNTY ADMINISTRATOR ;< County , June 20 1995 DATE: SUBJECT: APPROVING AND AUTHORIZING EXECUTION OF CHANGE ORDER NO. 28 TO CONTRACT FOR BID PACKAGE NO. 2 - SITE PREPARATION AT MERRITHEW MEMORIAL HOSPITAL REPLACEMENT, 2500 ALHAMBRA AVENUE, MARTINEZ SPECIFIC REQUEST MENDATION(S)&BACKGROUND AND JUSTIFICATION I . RECOMMENDATION A. APPROVE Change Order No . 28 to the Contract dated October 5, 1993, for Site Preparation - Demolition, Relocation and Modifications of Existing Structures and Features, and the Widening of Street No . 4 at Merrithew Memorial Hospital, 2500 Alhambra Avenue, Martinez, and AUTHORIZE the County Administrator or his designee to execute the Change Order, which provides for revisions as a result of design changes in the water system which were caused by hidden conditions and site conflicts . II. FINANCIAL IMPACT Funds in the capital account established for the project are sufficient to cover the amount encumbered by this contract, from bond proceeds , specified to the project . Bond financing for the total project cost was secured in May, 1992 in accordance with the Board of Supervisors direction. t CONTINUED ON ATTACHMENT: YES SIGNATURE: RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON ) j_9 9_S APPROVED AS RECOMMENDED I- OTHER VOTE OF SUPERVISORS I HEREBY CERTIFY THAT THIS IS A TRUE UNANIMOUS(ABSENT ) AND CORRECT COPY OF AN ACTION TAKEN AYES: NOES: AND ENTERED ON THE MINUTES OF THE BOARD ABSENT: ABSTAIN: OF SUPERVISORS ON THE DATE SHOWN. D. Bell, CAO ATTESTED 1 Contact: PHIL B CHELOR,CLERK OF THE BOARD OF CC: Auditor-Controller SUPERVISORS AND COUNTY ADMINISTRATOR GSD (Accounting) O'Brien-Kreitzberg (Via CAO) Contractor (Via CAO) BY DEPUTY Page 1 of 2 Board Order to Approve June 06, 1995 Change Order No. 27 for Bid Package No. 2 III . REASONS FOR RECOMMENDATIONS On October 5, 1993, the County awarded the contract to the lowest responsive and responsible bidder, Joe Carone, Inc. The new guaranteed maximum cost will exceed the total estimated cost stated in the construction contract agreement approved by the Board on October 5, 1993 . The new guaranteed maximum cost will be $2, 002, 626 . 94, an increase of $79, 000 . 00 . CO28BO.BP2 jC Page 2 of 2 1 HOSPITAL REPLACEMENT PROJECT , 651 PINE STREET, 8TH FLOOR MARTINEZ, CALIFORNIA 94553 (510) 646-1040 f•+ Initiation Date: May 24, 199�� CH&K= ORDER NO, 28 Contract for Construction of: DEMOLITION, RELOCATION AND MODIFICATIONS OF EXISTING STRUCTURES AND FEATURES, AND THE WIDENING OF STREET NO. 4 AT KWLRITHEW MEMORIAL HOSPITAL, 2500 ALHAMBRA AVENUE, MARTINEZ, CA Effective Date of Contract: October 5, 1993 Authorization No. : 0928-WH580B TO: JOE CAROM, INC. 2294 Vista Del Rio Crockett, CA 94525 You are directed to make the following change(s) in this Contract: DESCRIPTION OF CHAXGZt Item No. 1 Reference: PCO #103 Field Instruction # - RFI # - Add: $46,000.00 Cost increase due to revisions to B Street water system Item No- 2 Reference: PCO #._B2 Field Instruction # - RFI # - Add: $33,000.00 Changes in design adding to the water system within the upper campus REASON FOR CHANGE: ( ) Design Deficiencies (X) Criteria Change by End-Users (X Differing Site Conditions ATTACHMENTS: The Original Contract Price was . . . . . . . . . . . . . $1,124,644.00 Net Change by previously approved Change Orders . . . . . . . . . $ 798, 982.94 The Contract Price before this Change Order was . . . . . . . $1,923, 626.94 The Contract Price will be increased by this Change Order . . . . $ 79, 000.00 The new Contract Price, including this Change Order will be $2,002,626.94 The CoMletion Time will not change. RECOMMENDED BY: Project Manager Not valid until signed by both the Public Agency and the Contractor. By signature below, Contractor indicates acceptance of price stated herein as full compensation for all direct and indirect costs ' for all work described above, and as full compensation for any effects this change may have on the project in its entirety and/or on the time required to complete the project. PUBLIC AGENCY: CONTRA.CTOR- B B y - yJl� DeRoyce Bell, Director Date ( Aute ized O icer Date 4 Hospital Replacement Project ' 1 }