Loading...
HomeMy WebLinkAboutMINUTES - 05091995 - H.4 �.Rr �E. 8 E... •.'' --...- _ -.��'• Contra TOI BOARD OF SUPERVISORS �; Costa 0. County FROM: HARVEY E. BRAGDON ° " ~ DIRECTOR OF COMMUNITY DEVELOPMENT DATE: May 9, 1995 OUN SUBJECT: APPEAL BY THE APPLICANT-NEA GOLF ENTERPRISES (APPLICANT) - WEST/FLANIGAN/SILVA (OWNERS) , COUNTY FILE #2017-92, OF THE DENIAL DECISION BY THE SAN RAMON VALLEY REGIONAL PLANNING COMMISSION BOARD OF APPEALS TO ESTABLISH A GOLF COURSE, IN THE DANVILLE AREA. SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND JUSTIFICATION RECOMMENDATIONS Option #1 Uphold the Planning Commission's decision and deny the appeal. Option #2 1. Refer the matter back to the San Ramon Valley Regional Planning Commission for public hearings and direct Staff to renotice for new public hearings in seven months; and 2. Allow the applicant four months to complete the reclaimed water routing study under the direction of the Dublin San Ramon Service District (as indicated by the applicant's January 9, 1995 letter) and resolve the potable water issues; and 3 . Direct Staff to complete the appropriate environmental documentation upon receipt and acceptance of all the information requested of the applicant; and 4 . Direct staff to prepare a staff report with recommendation on the applicant's proposal following completion and posting of the appropriate environmental documentation; and 5. Require the applicant to provide monthly reports to staff on the progress being made on completion of the reclaimed water routing study and the provision of potable water. If t e CONTINUED ON ATTACHMENT: X YES SIGNATURE RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITT E APPROVE OTHER SIGNATURE(S) ACTION OF BOARD ON May 9, 1995 APPROVED AS RECOMMENDED x OTHER x _ See Addendum for Board Action VOTE OF SUPERVISORS I HEREBY CERTIFY THAT THIS IS A x UNANIMOUS (ABSENT TRUE AND CORRECT COPY OF AN AYES: NOES: ACTION TAKEN AND ENTERED ON THE ABSENT: ABSTAIN: MINUTES OF THE BOARD OF SUPERVISORS ON THE DATE SHOWN. Contact:Debbie Chamberlain ATTESTED May 9, 1995 cc: Community Development Department PHIL BATCHELOR, CLERK OF New Golf Enterprises THE BOARD OF SUPERVISORS Public Works-Attn: Mitch Avalon COUN DMINISTRATOR r4 BY 7 a , DEPUTY DC:df Page Two applicant fails' to provide a monthly or no progress is made within the four month period, direct Staff to renotice and schedule this item with a recommendation for denial with prejudice before the Board of Supervisors; and 6. If the requested information is provided to the satisfaction of the Community Development Department, direct the applicant to deposit the sum of $7, 000. 00 prior to beginning work on the environmental documentation to cover staff time for processing the appeal and to complete the processing of the application. FISCAL IMPACT None, if the appropriate fees are collected to process the application, as indicated in Option #2 (6) . BACKGROUND/REASONS FOR RECOMMENDATIONS The application to establish a 27 hole golf course was filed in March of 1992 . The application was subsequently deemed incomplete in November of 1992. The application was then suspended from processing until July 28, 1993 at the request of the applicant, to resolve related zoning issues. The applicant was notified on September 28, 1992 of the information required to complete the environmental documentation. As of this date, all the information requested of the applicant in September 1993, has not been provided. A chronology of events is provided in the Staff Report to the San Ramon Valley Regional Planning Commission dated March 15, 1995. In summary, the applicant failed to provide the information which staff had requested numerous times, in order to complete the environmental review for the project. Information which was' received by the applicant, was not complete or adequate to complete the environmental review. The application was scheduled for denial before the County Zoning Administrator on August 8, 1994. The item was subsequently continued to September 12, 1994 and to October 10, 1994 and finally to January 9, 1995 to allow the •applicant the opportunity to' provide information on a timely basis, preventing staff from providing a complete and accurate assessment of the project. The applicant appealed the Zoning Administrator's decision to the San Ramon Valley Regional Planning Commission. The Commission considered the applicants appeal on March 15, 1995. The discussion among the Commissioner's focused on the inappropriateness to approve a project that is outside the Urban Limit Line and the boundaries on an ultimate service provider. Concerns about open, space surrounding the project would be developed and approving a project without a verifiable source of water. After taking testimony and considering all the evidence before them, the Commission voted 6-1 to deny the appeal of the applicant and uphold the Zoning Administrator's decision. The applicant's appeal to the Board of Supervisor's does not raise any new issues that were not addressed in the March 15, 1995 Staff Report to the San Ramon Valley Regional Planning Commission. ADDENDUM TO ITEM H.4 MAY 9, 1995 This is the time noticed by the Clerk of the Board of Supervisors for hearing on the appeal of New Golf Enterprises (appellant) from the decision of the San Ramon Valley Regional Planning Commission acting as the Board of Appeals on the application of New Golf Enterprises (applicant) and West/Flanaga/Silva (owners) to establish a 27-hole golf course and related facilities (LUP 2017-92) in the Danville area. Dennis Barry, Community Development Department, presented the staff report, commenting on the lack of information presented by the applicant to make an environmental determination. The following persons presented testimony: John L. Baker, 6 Lois Lane, Lafayette, representing New Golf Enterprises; Bert Michalczyk, 7051 Dublin Boulevard, Dublin, representing the Dublin/San Ramon Services District; Ken Stromgren, 7450 Johnston Road, Pleasanton; Marcia Muething, 6800 Johnston Road, Pleasanton; Dennis Hurlburt, 7191 Johnston Road, Pleasanton; Cindy Kohler, 5795 Bruce Drive, Pleasanton; Jim Perry, 6667 Johnston Road, Pleasanton; Steve Williams, 260 Joseph Lane, Danville; Mike Johnston, 6975 Johnston Road, Pleasanton; Hugh Afshar, 671 Ironbark Circle, Orinda; Burke M. Critchfield, 5510 Sunol Boulevard, Pleasanton, representing CoWest, property owner; Kris Kalstrom, 7191 Johnston Road, Pleasanton; Rich Penarelli, 6850 Johnston Road, Danville; Nora McClelland, 5775 Johnston Road, Pleasanton. The Chair read comments from Jackie Martin, 555 Bruce Drive in Pleasanton expressing her concerns on issues including water. Mr. Baker spoke in rebuttal . The Board discussed the issues . Supervisor Bishop moved approval of staff recommendation #1 and Supervisor Torlakson seconded the motion. Supervisor DeSaulnier moved approval of staff recommendation #2 with the addition of a recommendation 47 requiring the applicant to provide ten to fifteen thousand dollars for staff to get a financial feasibility study with an estimate of what the return would be to the County in taxes . After further discussion, the Board took the following action: APPROVED Option #2, recommendations 1 through 6, relative to LUP #2017-92 , referring the matter back to the San Ramon Valley Planning Commission and other related actions; ADDED recommendation 7, directing that the applicant provide the financial resources to the Community Development Department to do a financial feasibility study, with the inclusion of an estimate in terms of what the return in taxes to the County would be from this proposed project . APPEAL NEW GOLF ENTERPRISES (APPLICANT) WEST/FLANIGAN/SILVA (OWNERS) COUNTY FILE #2017-92 A request to establish a Golf Course in the Danville area. BOARD OF SUPERVISORS CONTRA COSTA COUNTY MAY 9, 1995 - 2 : 00 P.M. Contra Costa TO: BOARD OF SUPERVISORS County FROM: HARVEY E. BRAGDON •, DIRECTOR OF COMMUNITY DEVELOPMENT Sra coU DATE: May 9, 1995 SUBJECT: APPEAL BY THE APPLICANT-NEA GOLF ENTERPRISES (APPLICANT)- WEST/FLANIGAN/SILVA (OWNERS), COUNTY FILE 02017-92, OF THE DENIAL DECISION BY THE SAN RAMON VALLEY REGIONAL PLANNING COMMISSION BOARD OF APPEALS TO ESTABLISH A GOLF COURSE, IN THE DANVILLE AREA. SPECIFIC REQUEST(S) OR RECOMMENDATIONS) 4 BACKGROUND AND JUSTIFICATION RECOMMENDATIONS Option #1 Uphold the Planning Commission's decision and deny the appeal. option #2 1. Refer the matter back to the San Ramon Valley Regional Planning Commission for public hearings and direct Staff to renotice for new public hearings in seven months; and 2. Allow the applicant four months to complete the reclaimed water routing study under the direction of the Dublin San Ramon Service District (as indicated by the applicant's January 9, 1995 letter) and resolve the potable water issues; and 3. Direct Staff to complete the appropriate environmental documentation upon receipt and acceptance of all the information requested of the applicant; and 4. Direct staff to prepare a staff report with recommendation on the applicant's proposal following completion. and posting of the appropriate environmental documentation; and 5. Require the applicant to provide monthly reports to staff on the progress being made on completion of the reclaimed water routing study and the provision of potable water. If t e CONTINUED ON ATTACHMENT: X YES SIGNATUREl_"_ RECOMMENDATION OF COUNTY ADMINISTRATOR _ RECOMMENDATION OF BOARD COMMITT E _ APPROVE OTHER SIGNATURE(S) : ACTION OF BOARD ON APPROVED AS RECOMMENDED OTHER VOTE OF SUPERVISORS I HEREBY CERTIFY THAT THIS IS A UNANIMOUS (ABSENT TRUE AND CORRECT COPY OF AN AYES: NOES: ACTION TAKEN AND ENTERED ON THE ABSENT: ABSTAIN: MINUTES OF THE BOARD OF SUPERVISORS ON THE DATE SHOWN. Contact:Debbie Chamberlain ATTESTED cc: Community Development Department PHIL BATCHELOR, CLERK OF New Golf Enterprises THE BOARD OF SUPERVISORS Public Works-Attn: Mitch Avalon AND COUNTY ADMINISTRATOR BY , DEPUTY DC:df j f Page'Two ' applicant fails to provide a monthly or no progress is made within the four month period, direct Staff to renotice and schedule this item with a recommendation for denial with prejudice before the Board of Supervisors; and 6. If the requested information is provided to the satisfaction of the Community Development Department, direct the applicant to deposit the sum of $7,000.00 prior to beginning work on the environmental documentation to cover staff time for processing the appeal and to complete the processing of the application. FISCAL IMPACT None, if the appropriate fees are collected to process the application, as indicated in Option 12(6) . BACKGROUND/REASONS FOR RECOMMENDATIONS The application to establish a 27 hole golf course was filed in March of 1992. The application was subsequently deemed incomplete ' in November of 1992. The application was then suspended from processing until July 28, 1993 at the request of the applicant, to resolve related zoning issues. The applicant was notified on September 28, 1992 of the information required to complete the environmental documentation. As of this date, all the information requested of the applicant in September 1993, has not been provided. A chronology of events is provided in the Staff Report to the San Ramon Valley Regional Planning Commission dated March 15, 1995. In summary, the applicant failed to provide the information which staff had requested numerous times, in order to complete the environmental review for the project. Information which was received by the applicant, was not complete or adequate to complete the environmental review. The application .was scheduled for denial before the County Zoning Administrator on August 8, 1994. The item was subsequently continued to September 12, 1994 and to October 10, 1994 and finally to January 9., 1995 to allow the .applicant the opportunity to provide information on a timely basis, preventing staff from providing a: complete and accurate assessment of the project. The applicant appealed the Zoning Administrator's decision to the San Ramon Valley Regional Planning Commission. The Commission considered the applicant's appeal on March 15, 1995. The discussion among the Commissioner's focused on the inappropriateness to approve a project that is outside the Urban Limit Line and the boundaries on an ultimate service provider. Concerns about open space surrounding the project would be developed and approving a project without a verifiable source of water. After taking testimony and considering all the evidence before them, the Commission voted 6-1 to deny the appeal of the applicant and uphold the Zoning Administrator's decision. The applicant's appeal to the Board of Supervisor's does not raise any new issues that were not addressed in the March 15, 1995 Staff Report to the San Ramon Valley Regional Planning Commission. 7 � 1 RESOLUTION NO. 12-1995 BEFORE THE BOARD OF APPEAL CONTRA COSTA COUNTY STATE OF CALIFORNIA APPEAL - New .Golf Enterprises, Applicants West Flanigan/Silva, Owners . Land Use Permit #2017-92 - Danville area WHEREAS, on August 12 , 1992, New Golf Enterprises (Applicant) and West/Flanigan/Silva (Owners) , filed an application to establish a 27 hole golf course and related facilities, in the Danville area; and WHEREAS, the application was subsequently deemed incomplete for environmental purposes after requesting and only receiving a portion of the information required to continue with the Environmental Process; and WHEREAS, a decision was made to schedule a public hearing and recommend denial without prejudice; and WHEREAS, after notice thereof having been lawfully given, a public hearing was held by the County Zoning Administrator on August 8, 1994 and was continued until September 12 , 1994 and continued again to October 10, 1994 and once again to January 9, 1995 for the remainder of the requested information; and WHEREAS, on January 9, 1995, the County Zoning Administrator considered and Denied without prejudice the request; and WHEREAS, following the decision, a letter was received by the Community Development Department on January 19, 1995 from the applicant appealing the Zoning Administrator's decision to the San Ramon Valley Regional Planning Commission Board of Appeals; and i WHEREAS, at a lawfully noticed scheduled public hearing on March 15, 1995, the San Ramon Valley Regional Planning Commission Board of Appeals upheld the Denial decision of the Zoning Administrator and denied the appeal; and Page Two RESOLUTION # 12-1995 NOW, THEREFORE, BE IT RESOLVED that the San Ramon Valley Regional Planning Commission Board of Appeals denied the appeal and upheld the Zoning Administrators's decision of denial without prejudice; and BE IT FURTHER RESOLVED that the foregoing was given by vote of the San Ramon Valley Regional Planning Commission Board of Appeals in a regular meeting Wednesday, March 15, 1995 as follows: AYES: Commissioners - Gibson, Naidorf, Harvey, Lucia, Pancoast, Matsunaga NOES: Commissioners - Kaplan ABSENT: Commissioners - None ABSTAIN: Commissioners - None BE IT FURTHER RESOLVED that the decision of the San Ramon Valley Regional Planning Commission Board of Appeals was appealed by the applicant on March 24, 1995. ATTEST: Secretary of the San Ramon Valley Regional P anning Commission, County of Contra Costa, State of Calif. nia DC/df 2017-92.res John L. 'Baker West/Flanagan Jim Blickenstaff New Golf Enterprises 5500 Bruce Drive 2410 Talavera Drive P.O. Box 381 San Ramon, CA 94566 San Ramon, CA 94583 Lafayette, CA 94549-0381 Mr. & Mrs. Denny Kahler Debbie Compilli Dorothy Burt 5795 Bruce Drive 7220 Johnston Rd. P.O. Box 2286 Pleasanton, CA 94588 Plesanton, CA 94566 Danville, CA 94526 Jim Perry Beverly Matta Reza Manafi 6667 Johnston Road 1613 Sunnyvale Avenue 274 Sequoia Terrace Pleasanton, CA 94588 Walnut Creek, CA 94596 Danville, CA 94506 Transcredit Afshar Hugh Afshar Emma Hites 1200 Mt. Diablo Blvd. 671 Ironbark Circle 259 Joseph Lane Walnut Creek, CA 94596 Orinda, CA 94563 Pleasanton, CA 94588 Jeorge Hites Stephen Williams Paul Speroni 259 Joseph Lane 260 Joseph Lane 245 Joseph Lane Pleasanton, CA 94588 Danville, CA 94588 Pleasanton, CA 94566 Marcia Muething Kay Stromgren Del Thonpson 6800 Johnston Road 7450 Johnston Road 6821 Johnston Road Pleasanton, CA 94566 Plesanton, CA 94566 Plesanton, CA 94566 Carl Caban John Ochoa Anthony & Ra c; 6621 Johnston Road 7171 Johnston Road Montemayor _ Plesanton, CA 94566 Plesanton, CA 94566 6550 Johnston Road Plesanton, CA 94566 Dennis Hurlburt Gary Wolfe Mike Johnston 7191 Johnston Road 6911 Johnston Road 6975 Johnston Road Plesanton, CA 94566 Plesanton, CA 94566 Plesanton, CA 94566 Donald Black Bert Michalczyic Wilbert Perry 6971 Johnston Road DublinSanRamon Servs. 6575 Johnston Road Plesanton, CA 94566 7051 Dublin Blvd. Plesanton, CA 94566 Dublin, CA 94568 Jim Perry Gary Wolfe Tony Teixeira 6667 Johnston Road 6911 Johnston Road 6615 Johnston Road Plesanton, CA 94566 Plesanton, CA 94566 Plesanton, CA 94566 Steve Williams B. Critchfield Jeff Ryan 260 Joseph Lane 5980 Stoneridge Drive 5870 Bruce Drive Pleasanton, CA 94588 Pleasanton, CA 94588 Pleasanton, CA 94588. Michael & Nora McClelland 5775 Johnston Road Plesanton, CA 94566 r John & Suzanne Kenton PO Box 31.91 Danville, CA 94526 MAG Mike & Lois Johnston 6975 Johnston Road Pleasanton, CA 94588 Robt & Diamond Hunter 5445 Bruce Drive Pleasanton, CA 94588 i John & Regina Holloman 6915 Johnston Road Pleasanton, CA 94588 Elaine M- Halpin 370 N. Civic Dr, #312 -.-,_..r rrprk. CA 94596 L Phil & Nancy Fay 7225 Johnston Road Pleasanton, CA 94588 Rick & Troy Deherrera 196 Cambridge Ave San Leandro, CA 94577 Sandra J. Dare 6900 Johnston Road Pleasanton, CA 94588 Frank F. Coelho 25633 Clover Road Hayward, CA 94542 Paul & Janet Brock 5785 Johnston Road Pleasanton, CA 94588 Frank & Clara Bonde 5707 Highland Road Pleasanton, CA 94588 t Donald & Frances Black 6971 Johnston Road Pleasanton, CA 94588 James & Lee Ann Bowers 7210 Johnston Road Pleasanton, CA 94588 Emil & Cate Carre 7400 Johnston Road Pleasanton, CA 94588 i J• Danny & Kathleen Corneil 5600 Bruce Drive .Pleasanton, CA 94588 . I;For L'i-•. arJv 1 Annette C. Darnes 5351 Johnston Road Pleasanton, CA 94588 Donald & Kim Fastabend 5730 Old School Road Pleasanton, CA 94588 UNA _ Peter & Mira Goetsch 5910 Bruce Drive Pleasanton, CA 94588 George & Emo Hites 259 Joseph Lane Pleasanton, CA 94588 Kenneth & Renae Howland PO Box 1133 Dlaacant-nn, CA 94566 h� I VSA Cy W. Bugh & Mary Hustead PO Box 2002 Danville, CA 94526 Dennis & Cynthia Kahler 5795 Bruce Drive Pleasanton, CA 94588 Scott Bishop & Dorothy Burt PO Box 2286 Danville, CA 94526 Henry F. Borghi 5574 Old School Road Pleasanton, CA 94588 Michael & Teri Brown 5655 Bruce Drive Pleasanton, CA 94588 ii use G _ Bobby & Shalini Chaudhuri 5500 Bruce Drive Pleasanton, CA 94588 Charles & Patricia Daggett 5311 Bruce Drive Pleasanton, CA 94588 Robert D. Elworthy Po Box 628 Danville, GA 94526 Lawrence & Dorothy Ferry 7754 Country Lane Pleasanton, CA 94588 tF.us. «� Bradley & Marilyn Haupt 7300 Johnston Road Pleasanton, CA 94588 • . . !� USA G ,�Fvl:i.ddrtvo oN. Charles & Vivienne Holman 5400 Johnston Road Pleasanton, CA 94588 James & Lorraine Hudack 5400 Penny Lane Pleasanton, CA 94588 Arnold Jacobs& Sue Kamins 5660 Old School Road Pleasanton, CA 94588 Weideman Properties 2301 Norris Canyon Rd San Ramon, CA 94583 Frank & Carmen Taylor 5530 Johnston Road CA 94588 Pleasanton, usAG Edward & Diem Zobrist 5601 Highland Road Pleasanton, CA 94588 Cory Soltau 240 Joseph Lane Pleasanton, CA 94588 M. David Silva 6000 Johnston Road Pleasanton, CA 94588 Jeff & Geraldine- Ryan 7225 Johnston Road Pleasanton, CA 94588 r Chas & Monica Pottier 6700 Johnston Road Pleasanton, CA 94588 USA G i - :.Fw lLi dbouoµ Ken & Tracy Spencer 5401 Johnston Road Pleasanton, CA 94588 Delbert & Joan Thompson 6821 Johnston Road Pleasanton, CA 94588 z William T. Tauscher 5611 Highland Road Pleasanton, CA 94588 Amy Stiles 5451 Johnston Road Pleasanton, CA 94588 Lyle & Kathleen Setter 5310 Bruce Dirve Pleasanton, CA 94588 Louise Rutledge 5390 Johnston Road Pleasanton, CA 94588 Wilbert & Helen Perry 6575 Johnston Road Pleasanton, CA 94588 John & Linda Ochda 7171 Johnston Road Pleasanton, CA 94588 r Dieter & Jennifer Norpchen . 254 Joseph Lane Pleasanton, CA 94588 i Ronald Nunes 5885 Bruce Drive _, rn QAgRR Dan &Deborah McHugh 5300 Penny Lane Pleasanton, CA 94558 Erika R. Marshall 5920 Old School Road Pleasanton, CA 94588 Anthony & Mrs Montemayor 6550 Johnston Road Pleasanton, CA 94588 Paul & Wendla McCann 7111 Johnston Road Pleasanton, CA 94588 Gary & Kathleen Loda 6921 Johnston Road Pleasanton, CA 94588 Us,,G I;hx LS+ddrtum aNc • James & Shelley Kerr 6650 Johnston Road Pleasanton, CA 94588 Howard & Jacqueline Martin 5555 Bruce Drive Pleasanton, CA 94588 Louis & Kristi Miramontes 6611 Johnston Road Pleasanton, CA 94588 Gerald & Marcia Muething J: 6800 Johnston Road Pleasanton, CA 94588 _ MAV Ernest & Margret Pearson 5621 Highland Road Pleasanton, CA 94588 Charles & Donna Rund 255 Joseph Lane Pleasanton, CA 94588 w,+V Kenneth & Marlene Santos 5750 Old School Road Pleasanton, CA 94588 Paul & Michelle Speroni 245 Joseph Lane Pleasanton, CA 94588 Leroy & Marilyn Stevens 5848 Old School Road Pleasanton, CA 94588 � us.,G lF«us.ee,vow. i Kenneth & Kathryn Stromgrei 7450 Johnston Road USA G Anthony & Bonnie Texeira 6615 Johnston Road Pleasanton, CA 94588 James Soule 7470 Johnston Road Pleasanton, CA 94588 Dennis Hurlburt PO Box 2257 Pleasanton, CA 94588 q . �;wus..em—«JY Pedro D. Zamora 22 Dartmouth Place Danville, CA 94526. uan V ' - i!For L'S.dd,mo mh Constance E. West 6351 Johnston Road Pleasanton, CA 94588 usn G Carol Roen 1530 Finley Road Pleasanton, CA 94588 Bruce & Debbie Compilli 7220 Johnston Road Pleasanton, CA 94588 The Pringle Group 90 El Camino Real Burlingame, CA 94010 P 4' Stephen R. Williams 260 Joseph Lane Pleasanton, CA 94588 Norbert & Jo Ann Walz 5400 Bruce Drive ({ uSA G Tim Caban 6621 Johnston Road Pleasanton, CA 94588 Norah Tuttle & Michael McClelland 5775 Johnston Road Pleasanton, CA 94588 Margaret. G. Wiley Trust 6901 Johnston Road Pleasanton, CA 94588 Ronald L Ferry 5656 Johnston 89 Pad leasanton, CA 94588 Gary & Levi Wolfe 6911 Johnston Road Pleasanton, CA 94588 New Golf.Enterprises 1 PO Box 381 Lafayette, CA 94549- NEW (5I0) 284-7100 FAX 284-7112 GOLF (Z) ENTERPRISES March 24, 1995 Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Appeal ICO Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club, in the vicinity of Tassajara) 1. This letter appeals the March 15, 1995 decision of the San Ramon Valley Regional Planning Commission to deny referenced application. 2 . The reasons for denial stated by the Commission: a. The decision concerning bringing reclaimed water back into the county for a project like this is most appropriately considered by the County Board of Supervisors . 3 . The reasons for appeal stated in my letter of appeal dated January 19 , 1995, which will be included in your staff report, are still germane. This is a win-win project which provides jobs and recreation for county citizens . It also provides several kinds of taxes for the county' s coffers . It does so at no environmental or growth impact and helps positively recharge the aquifer i the Tassajara/Finley Road/ Johnston Road area. John . C � CO vi my .. -� O Agenda Item #� Community Development Contra Costa County SAN RAMON VALLEY REGIONAL PLANNING COMMISSION WEDNESDAY, MARCH 15, 1995 - 7:30 P.M. BOARD OF APPEALS I. INTRODUCTION NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SILVA (Owners), County File #2017-92. This is an appeal by the applicant of the Zoning Administrator's denial decision to establish a 27 hole golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800 feet on the north side of Johnson Road approximately 1 ,350 feet east of Camino Tassajara, in the Danville Area. (A-80, A-40, A-2) (ZA: U-20, V-20, V-21 ) (CT 35.51 -03) (APN's 203-050-021 , 204-100-012, 204-160-001 , 206-200-003, 204-080-007, 204-110-003, 204-180- 005). II. RECOMMENDATION A. Staff recommends the Commission uphold the Zoning Administrator's decision, deny the appeal. B. Alternatively, if the Commission finds merit in the applicant's request for continuance, Staff recommends the following course of action: 1 . Continue the matter for seven months; and 2. Allow the applicant four months to complete the reclaimed water routing study under the direction of Dublin San Ramon Service District (as indicated in the applicant's January 9, 1995 letter) and resolve the potable water issues; and 3. Direct staff to complete the appropriate environmental documentation upon receipt and acceptance of all the information requested of the applicant; and 4. Direct Staff to prepare a staff report with recommendation on the applicant's proposal following completion and posting of the appropriate environmental documentation; and 5. Require the applicant to provide monthly reports to Staff on the progress being made on completion of the reclaimed water routing study and the provision of potable water. If the applicant fails to provide a monthly report or no progress is made within the four month period, direct staff to re-notice and schedule this item with a recommendation for denial with prejudice before the Commission. . 2 6. If the requested. information is provided to the satisfaction of the Community Development Department, direct the applicant to deposit the sum $7000.00 prior to beginning work on the environmental documen- tation to cover staff time for processing the appeal and to complete the processing of the applications. 111. BACKGROUND A. Summary: The application to establish a 27 hole golf course was filed in March of 1992. The application was subsequently deemed complete in November of 1992. The application was then suspended from processing until July 28, 1993 at the request of the applicant, to resolve related zoning issues. The applicant was notified on September 28, 1993 of the information required to complete the environmental documentation. As of this date, all the information requested of the applicant in September 1993, has not been provided. B. Chronology: 1 . March 12,1992: An application to establish a golf course and related facilities was filed with the Community Development Department. 2. April 10, 1992: The applicant was notified _that the application was incomplete and additional information was needed to process the request. (See Exhibit 1 Correspondence) 3. October 14, 1992: Submittals were received from the applicant and the _application was deemed complete by default on November 13, 1992. (See Exhibit 2 Correspondence) 4. February 24, 1993: The applicant agrees to suspending the application from processing until July 28, 1993 until determination if the properties currently under Williamson Act Contract could be included as part of the application submittals. (See Exhibits 3, 3A - Correspondence, 3B Correspondence) 5. August 27, 1993: The applicant was provided with a tentative schedule for processing the application, including a County initiated revision to the Zoning Ordinance to include golf courses as a permitted use with the issuance of a land use. permit in the A-4 (Agricultural Preserve). (See Exhibit 4 Correspondence) 6. September 28,1993: The applicant was notified of the information necessary to complete the environmental assessment of the project, because the information requested is related to the environmental issues of the project, said information could not be requested at the time the application was deemed incomplete. (See Exhibit 5 Correspondence) 3 7. January 4, 1994; The text amendment pertaining to the application of the A-2 and A-20 ordinance 'was heard by the County Planning Commission at which time the Commission recommended approval to the Board'of Supervisors. Following the Planning Commission meeting, staff later determined that it would be necessary to include watershed uses as a part of the ordinance code text amendment. This item has not been rescheduled before the Commission. (See Exhibits 6A - Staff Report and 6B - Transcript of Hearing) 8. April 6, 1994: A portion of the requested information was received by the applicant. The applicant's cover letter indicated the remaining items would be forwarded within the week. No further information was received.(See Exhibit 7 Applicant's Submittal) 9. May 1994: The applicant informed staff by telephone that additional information would be submitted within the week. No further information was received. 10. August 8, 1994: Zoning Administrator meeting. Staff recommended the item be denied for delays by the applicant in processing the application. The applicant submitted additional information at the Zoning Administra- tor Hearing. The Zoning Administrator continued the matter to Septem- ber 12, 1994 to allow staff the opportunity to review the submitted information. (See Exhibits 8A - Staff Report; 8B - Applicant's Submittal) 1 1 . August 25, 1994: The applicant was notified the information requested' in Staff's September 28, 1993 was not provided at the August 8, 1994 Zoning Administrator Hearing. (See Exhibit 9 Correspondence) 12. September 12, 1994: Zoning Administrator meeting. Staff continues to recommend denial of the application for delays by the applicant in processing the application. The applicant provided additional information at the Hearing. The Zoning Administrator continued the matter to October 10, 1994 to allow staff the opportunity to review the submitted information. (See Exhibits 10A - Staff Report; 10B Applicant's Submit- tal) 13. October 10, 1994: Zoning Administrator meeting. The applicant at the September 12, 1994 meeting provided the information requested in Staff's September 28, 1993 letter. The information was not adequate to demonstrate that a verifiable source of reclaimed water or potable has been secured for the project. Staff recommended an indefinite continu- ance to allow the applicant the opportunity to meet with DSRSD and initiate the Planning Study necessary to demonstrate if reclaimed water is viable for the subject property. A verifiable water source for irrigation of the golf course is necessary to demonstrate that an adequate water supply exist prior to staff completing the environmental documentation for the project. 4 The applicant requested a three-month continuance to January 9, 1995 to provide the information. (See Exhibits 11 A - Staff Report; 1 1 B - Transcript of. Hearing) 14. October 27, 1994: Staff met with the applicant and DSRSD to discuss providing reclaimed water to the project site. DSRSD preliminary suggested that if all the appropriate studies are completed and infra- structure and planning cost are covered, they are not opposed to servicing the site. County Staff and DSRSD further indicated to the applicant, that preliminary engineering studies would b.e required before completing the environmental documentation for the project. Addition- ally, Staff and DSRSD suggested that the applicant begin meetings with County Health Services Department and if necessary, the State Department of Health Services,to discuss the proposed water treatment facility. Staff requested notification of any meetings with the County Health Services Department. Additionally, at the October 27, 1994 meeting Staff requested the applicant submit the preliminary engineering studies or a status report two weeks prior to the next Zoning Administrator meeting on January 9, 1995. 15. January 9, 1995: Zoning Administrator Hearing. The applicant did not provide staff with the preliminary engineering studies or a project status report prior to the writing of the staff report. Therefore, staff recom- mended denial of the application with prejudice for continued delays by the applicant. The applicant, provided a project status and indicated that he retained an engineering firm to complete the study and was currently awaiting funding. After receipt of funding, the study would take approximately four months to complete and the applicant requested continuance of the same length. The Zoning Administrator after hearing the applicant's testimony and that of neighbors opposed to the project about the numerous continu- ances and delays, denied the application with prejudice. (See Exhibits 12A - Staff Report; 12B - Applicant's Submittal; 12C - Transcript of hearing) 16. The applicant appealed the Zoning Administrator decision on January 19, 1995 at 5:00 pm. (See Exhibit 13 - Appeal Letter) IV. ZONING ADMINISTRATOR'S DECISION The Zoning Administrator on January 9, 1995, denied the applicant's request with prejudice for the following reasons: 5 A The applicant realized early on that in order to establish the project would have .to be major provision for the extension of water and the applicant is now, after two and one-half years beginning to engage a potential water district about providing water. The items should be identified early in the process, prior to the application being filed with the County. B. Cost of $2,000,000.00 to extend an eight inch water line to the project site may not be realistic given today's planning considerations in terms of annexations and decisions that would have to involve other properties and may raise a number of planning issues beyond the scope of this project. C. Lack of response on the part of the applicant. No response is received from the applicant until the day of the hearing on information which has been previously requested, information which is required to proceed with the project. D. The neighbors have continued to attend the public hearings and it would not be fair to keep continuing the item, if the applicant is unwilling to provide information in a timely manner. V. ISSUES OF APPEAL Staff has provided a summary of the applicant's four issues of appeal and a staff response to those issue. The appeal letter is attached as Exhibit 13 to this staff report. Issue #1 : The applicant was not informed of the continuance date from October 10, 1994 to January 9, 1995. Staff Response: The applicant was present at the October 10, 1994 meeting at which time he requested a three month continuance. The Zoning Administrator did not have a 1995 Public Hearing Calendar, but requested staff to the call the planning secretary for the date, so as not to unduly burden the neighbors. The date of continuance to January 9, 1995 was announced at the hearing. Additionally, staff informed the applicant at the October 27, 1994 meeting of the continuance date and additionally requested the applicant provide a project status two weeks prior to the January 9, 1995 meeting. Furthermore, neighbors opposed to the project appeared and spoke at the January meeting. In staff's opinion, the applicant and interested parties were adequately notified of the January 9, 1995 meeting. Issue #2: A process for continuance had been worked out between the applicant and staff. However, because of the applicant's non-communication, staff had presumed the applicant was not proceeding with the project. Staff Response: Staff concurs that a process for the applicant to proceed with completion of the required studies had been agreed to. However, staff requested the applicant to provide a project status two weeks before the next Zoning Administrator hearing. The burden of proof is placed on the applicant to supply staff with complete and accurate information in a timely manner. The applicant following the October 27, 1994 meeting had not communicated with staff until receipt of the staff reports in 6 early January 1995 recommending denial. As in the past, the applicant provided information at the public hearing, not allowing staff an opportunity to provide a staff report reflecting the applicant's submittals. Issue #3: The project has been delayed considerably. Staff Response: Please see chronology of the project in the Section lll, "Background" of this staff report. In staff's opinion, processing of the application was delayed because of the applicant's failure to submit the requested items in a timely manner. Issue #4: Reclaimed water routing system could be made a condition of approval on the project. Staff Response: The project is not within the Ultimate Service .Boundary of EBMUD or CCWD and the applicant has not provided a verifiable source of water for irrigating the golf course and servicing the clubhouse. In order for staff to adequately assess the environmental impacts of the project, a preliminary design for the delivery of reclaimed water is necessary to ensure a verifiable source of water exist for the project. Furthermore, hydrogeologic investigations prepared by Engeo, Inc. determined that adequate groundwater does not exist to serve the project. VI. CONCLUSION The Zoning Administrator's decision to deny the project was based on the applicant's failure to provide requested information on a timely basis, preventing staff from providing a complete and accurate assessment of the project. The applicant has not presented any new information, that was not available to the Zoning Administrator at the time of decision. DJC/AB/aa LUPXX/2017-92.DJC 3/1/95 • > f�� 1T l Community Contra Harvey E. Bragdon . Development I 1 Director of Community Developmc Department COSta County Administration Building County 651 Pine Street 4th Floor, North Wing Martinez, California 94553.0095 Phone{510) 646-2091 f April 10, 1992 New Golf Course Enterprises 3466 Mt. Diablo Blvd., C-205 Lafayette, CA 94549 Dear Applicant: The Contra Costa County Community Development Department has reviewed your application, County File No. 2017-92. Your application has been found to be incomplete. The following information will be required before we can further review your request: In order to complete your application, the following information must be provided: Project Components: cording tour application, your project involves: 18 hole golf course Clubhouse with classrooms Tennis Center Pro-shop Dining Facilities Golf Cart Storage Parking For each of these project elements, provide the following information: a. Location (if not shown on site plan). b. identify and describe all necessary improvements c. identify the hours and days of operation 2. Elevations: Provide elevation drawings showing all portions of the planned project. 3. Geology: The report submitted as part of your application entitled, "Fox Creek County Club ..Geologic Evaluation Revised February 12, 1992," Engeo Incorporated has been copyrighted. For the purposes of the Public Record Act, provide a release from copyright restrictions. Similarly, any copyright restriction on a document submitted as part of the application or as required in order to comply with the California Environmental Quality Act must be removed. This report will be submitted to the County's Geologist for review. 4. Environmental Assessment: The report submitted as part of your application entitled, "Limited Phase One Environmental Site Assessment," Engeo Incorporated, January 21 , 1992. This report is a limited study based on property owner recollection and a site visit. No testing was conducted, and regulatory agencies which might have information on potential contamination were not contacted. Provide additional information on the types and quantities of hazardous materials located on the site which were referenced in the report (e.g. location, size, contents by type and estimated quantity). Regulatory agencies should also be contacted to ascertain if they have information regarding any potential contamination. 5. Water Supply: Provide the following information: a. Identify the location of all existing and proposed on-site wells. b. Identify the location of existing and proposed off-site wells which may be used to augment irrigation supply. - C. Provide a conceptual proposal for preventing' the interconnection of the domestic and irrigation water supplies. d. Identify the location of storage area(s) for fuel, fertilizers,pool chemicals,etc. in relation to existing and proposed wells, including nearby off-site wells. e. Identify/describe the effect of the project on underlying aquifers (i.e. groundwater withdrawal vs recharge). f. Identify the location of off-site septic systems and disposal (leach) field replacement areas in relation to any existing or proposed on-site wells located within one hundred (100) feet of project boundaries. g. Provide additional information regarding the proposal to obtain treated wastewater from the Dublin/San Ramon Services District. This includes: 1 . Copies of any Board action relative to the proposal. 2. Tasks which must be completed in order to deliver the water including the responsible party and timetable for completion. This includes engineering studies, district Board approvals, other agency approvals, (e.g. annexation, change in Sphere of Influence), acquiring easements, and construction. 3. In our .verbal discussions, you stated that a services district would be formed in order to reimburse for the cost of the pipeline. Provide information detailing the proposed extent of the service district and any actions to date relative to this need. 5. Sewage Disposal: Due to the large volume of projected wastewater flows (15,000 to 50,000 gpd), a package treatment plant is indicated. Such a plant will operate under a permit from the Regional Water Quality Control Board. . Provide the following information: a. A conceptual design of the package treatment plant. b. The location of the plant. C. The location of on-site wells relative to the plant. d. If the plant is proposed within one hundred (100) feet of property lines, provide the location of nearby off-site wells. NOTE: The Regional Water Quality Control Board may have additional requirements involving the construction and operation of a package treatment plant. 6. Solid Waste: Identify/describe your proposal to handle solid waste generated by the this project, in particular waste generated by the maintenance of the golf course (e.g. on-site composting). 7. Traffic: a. Submit.a traffic study which is acceptable to the County Public Works Department. The study submitted as part of your application has been submitted to the Public Works Department for their review. For information regarding the scope of additional traffic studies, contact the Public Works Department, Road Engineering Division. b. Show the structure setback lines for all natural watercourses traversing the property. Because of the size of the land considered under this application, you may show the approximate location of this line on the topographical map. The line should be based on representative cross sections and the criteria specified in Section 914-14.012 "Structure Setback Lines for Unimproved Earth Channels," of the County Ordinance Code. 8. Regulatory Agencies: Identify any agencies which have regulatory authority over the establishment or operation of the project. If other agencies have permitting authority, identify the entitlement (s), and the status of your discussions/submittals. 9. Growth Management Standards: Provide detailed information on how this project will comply with the Growth Management Policies and the 1990 Measure C provisions of the 1991 Contra Costa County General Plan (refer to attached). Please submit the information requested above as soon as possible so that the processing of your application will not be delayed. Sincerely, Catherine Kutsuris Mat Senior Project Planner cc: Mary Fleming Eileen Doten County File No. 2017-92 John Compaglia New Golf Enterprises 3466 Mt. Diablo Blvd., C-205 Lafayette, CA 94549-3952 NEW (510)284-7100 FAX 284-7112 GOLF (�D ENTERPRISES October 12, 1992 Re: Use Permit Application, CCC File No. 2017-92 (Fox Creek Country Club, vic Tassajara) In response to the specific requests in CCC-CDD letter of 10 April: 1. Prof ect Components: a. Locations are generally depicted on the .blue-line and color renderings of the golf facility, attached, prepared by Robert Muir Graves, Ltd, Golf Course Architects. Clubhouse, classrooms, cart storage, pro shop and dining facilities are all part of one coherent structure or group of structures located where the "clubhouse" is on the renderings. Parking is also as depicted. The Tennis Center may be located immediately adjacent to the Clubhouse or on the land immediately south and east of the "corner" made by the 3rd green and 4th hole in the "North Valley 9 . " Tennis location is dependent on a detailed clubhouse site analysis to be conducted during clubhouse design. b. Improvements: whole facility is new construction. c. Hours for outdoor recreation are sunrise to sunset, or a nominal maximum of 6 am to 8:30 pm. Clubhouse dining will provide for breakfast for the sunrise starters though evening events which would not normally go later than 2 am. Parking will generally support these times with clubhouse staff arriving and departing about an hour before and after opening and closing times. Parking will also include perhaps up to 4 club owned vehicles (station wagon, sedan, small vans) parked overnight in the parking lot. 2 . Elevations: Specific elevations will be submitted for the Clubhouse design once completed. Since the design of a clubhouse is extremely expensive and integrated with the individual course design, normally that phase is not undertaken until the golf course Use Permit Request is approved. It is anticipated that review and approval of the clubhouse and associated components will be a Condition of Approval for the course. 3 . Geology: ENGEO' s copyright on its Soils Report has been rescinded. 4 . Environmental Assessment: the additional work requested has been performed and the study is attached. See also Soils and Site Assessment on the Silva Ranch to the requested standard. Regulatory agencies have been contacted and minor stains, etc. will be appropriately removed prior to course construction. 5 . Water Supply: Since the Dublin San Ramon (Water) Services District Board has approved the application for the use of reclaimed water to the site, on and off-site well water is not required for this project. It is the intention of Fox Creek to not use well water for any use. The one exception may be the clubhouse use (average of 20, 000 gallons per day) . If not permitted to use Super Still technology to provide potable water from reclaimed water for clubhouse use, Fox Creek would require the 20, 000 gallons per day from wells. Specific information requested: a/b. Location of On/Off Site Wells: See map attached. C. Interconnection of dissimilar supplies: Reclaimed and rain run-off supplies are collected and stored in lakes on the course. Potable wateris stored in tanks adjacent to clubhouse. There are no common connections to both systems. d. Storage of fuels and chemicals: in the Maintenance Area in the vicinity of the current West Ranch farmhouses and outbuildings . No closer than 250 feet from any well, nor .230 feet from any exterior property line. e. Effect on Underlying Aquifers: None, if Super Still permitted. If not, the total land could be divided into 15 - 40 plus acre parcels, as currently zoned. Clubhouse consumption of 20, 000 gallons per day would be the equivalent usage of 1, 333 GPD per zonable ranch, well below normal consumption in the vicinity. The provision of reclaimed water for irrigation has the net effect of recharging the aquifer. f . Proximity of On and Off-Site Septic and Leach Fields to Wells: None within 100 feet either side of any project exterior property line. g. Treated Wastewater (reclaimed water) : 1. Enclosed is the Resolution (DSRSD #23-92) and Contract by and through which DSRSD agrees to provide Fox Creek with reclaimed water. It should be noted that the water is Title 22 standard, Tertiary grade water, suitable for watering any plants which routinely come in contact with humans. 2 . The Process: after approval of the use permit for an outdoor golf facility, the following takes place: a. DSRSD prepares the engineering plans for the pipeline. This includes an assessment of possible additional users who currently exist (ranchers, existing ranchettes, etc) and what their requirements might be. The idea is to provide for the needs of current potential users without over-sizing to a growth inducing level . b.' Fox Creek agrees to the forecast costs of the pipeline. . C. DSRSD obtains approval from Water Quality Regional Board and California Department of Health Services for engineered project. d. DSRSD builds pipeline over existing easements and rights of way from Sanitary plant to golf course site. e. The whole process, from this point on, will take from 6 months to a year, from time of County golf course Use Permit approval . We would not commence construction of the course until the waterline project is sufficiently underway to provide reclaimed water to the course when it is ready to start irrigating turf - about 6 to 9 months from start of construction (depending upon rain delays during grading) . 3 . Reclaimed water service district: this would be run by the. DSRSD, as they provide for their other customers. No new "district, " pe se, needs to be created. -5 . Sewage Disposal: Please see package plant plan, attached. 6 . Solid Taste: a. Package plant solids are trucked away about every two months per the plan. b. Grass clippings, leaves and tree prunings are mulched, composted and recycled back onto the golf course and clubhouse landscaping. The compost pile is located in the vicinity of the maintenance area, no closer than 100 feet from any property line, streambed or well . 7. Traffic: Plan as submitted also will be coordinated with County Public Works Department. It should be noted that a 27 hole facility does not increase the traffic on Johnston Road or Camino Tassajara. Setback lines are shown on Bluelines, attached. 8 . Regulatory Agencies: a. Army Corps of Engineers -. Wetlands permit (Nationwide 26) and Water Quality Certification. b. Fish & Game: a 603 Streambed Alteration Agreement. 9 . Growth Management Standards: this project fully complies with the growth management standard of measure C and the revision to the County General Plan in that it provides an outdoor recreation facility both in and outside the Urban Limit Line without impacting traffic (LOS at serving roads remain at LOS A) . It adds to the quality of life within the county without adding any infrastructure requirements . c. DSRSD obtains approval from Water Quality Regional Board and California Department of Health Services for engineered project. d. DSRSD builds pipeline over existing easements and rights of way from Sanitary plant to golf course site. e. The whole process, from this point on, will take from 6 months to a year, from time of County golf course Use Permit approval . We would not commence construction of the course until the waterline project is sufficiently underway to provide reclaimed water to the course when it is ready to start irrigating turf - about 6 to 9 months from start of construction (depending upon rain delays during grading) . 3 . Reclaimed water service district: this would be run by the DSRSD,- as they provide for their other customers. No new "district, " pe se, needs to be created. 5 . Sewage Disposal: Please see package plant plan, attached. 6 . Solid Waste: a. Package plant solids are trucked away about every two months per the plan. b. Grass clippings, leaves and tree prunings are mulched, composted and recycled back onto the golf course and clubhouse landscaping. The compost pile is located in the vicinity of .the maintenance area, no closer than 100 feet from any property line, streambed or well . 7 . Traffic: Plan as submitted also will be coordinated with County Public Works Department. It should be noted that a 27 hole facility does not increase the traffic on Johnston Road or Camino Tassajara. Setback lines are shown on Bluelines, attached. 8 . Regulatory Agencies: a. Army Corps of Engineers = Wetlands permit (Nationwide 26) and Water Quality Certification. b. Fish & Game: a 603 Streambed Alteration Agreement. 9 . Growth Management Standards: this project fully complies with the growth management standard of measure C and the revision to the County General Plan in that it provides an outdoor recreation facility both in and outside the Urban Limit Line without impacting traffic (LOS at serving roads remain at LOS A) . It adds to the quality of life within the county without adding any infrastructure requirements . Community Contra Harvey oE.f Bragdon Director of Community Developmer Development Costa Department County Administration Building 651 Pine Street SE 4th Floor, North Wing �E•�•-- i_--_o„ Martinez, California 94553.0095 Phone: 646-2091 x� - •zJy A C"UNC February 24, 1993 John Baker, President New Golf Enterprises 3466 Mt. Diablo Boulevard; C-205 Lafayette, CA 94549-3952 Dear Mr. Baker: At our January 27, 1993 meeting with Mr. John Compaglia, we discussed the effect of the Williamson Act contracts (which are on the Silva and West properties) on the processing of an application for a golf course. I explained that neither the contract nor the A-4 zoning ordinance provided for a golf course on these properties. You explained your understanding that the County's proposal to revise the A-4 provisions of the Zoning Ordinance to include golf courses would resolve this issue. We agreed that your attorney, Mr. Sandy Skaggs, would write a letter to our department which outlines your belief as to how the County could make the findings necessary to either amend the A-4 section of the Zoning Ordinance to allow golf courses within .Williamson Act areas or to amend the contracts on these properties. On February 1 , 1993 Mr. Sandy Skaggs contacted Mr. Harvey Bragdon to discuss this issue, and stated that other jurisdictions have allowed golf courses within lands that are under Williamson Act contract. Mr. Bragdon requested that your attorney write a letter to our department detailing which other agencies have taken this action and the rationale for making the findings. I assume that information is currently being prepared. At our January 27, 1993 meeting you agreed with my recommendation that our department suspend processing the application until the issue.of whether a golf course may be allowed within a Williamson Act area is resolved. The exception to that suspension is, of course, any work necessary to resolve that issue, and the sending of various reports to the County Public Works Department, the Health Services Department, and the County Geologist. 2. I I look forward to receiving your information. If you have any further questions, please do not hesitate to call me at 646-2091 . Sincerely, CATHERINE KUTSURIS _ Senior Planner CK/aa LTRIV/2017-92.CK cc: 2017-92 ` New Golf Enterprises ` 3466 Mt. Diablo Blvd.. C-205:;!'-. ? .. Lafayette, CA 94549-3952 J T (510)284-7100 NEW (:D FAX 284-7112 f'J ";GOL UG 24 PF9 I: 48 (Z) ENTERPRISES ii:NT DEPT August 20, 1993 Catherine Kutsuris Senior Project Planner Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Use Permit Application, March 12, 1992 , County File No. 2017-92 (Golf Course: Fox Creek Country Club vic Tassajara) Dear Ms. Kutsuris: 1. Per your request this letter confirms that subject project process was suspended from the date of your letter, February 24, 1993 until determination of status under the Williamson Act was made and other zoning issues were determined. Such issues were resolved by the Director of the Community Development Department of Contra Costa County by and on July 28, 1993 . 2 . For purposes of the Permit Processing Streamlining Act, this means that the subject project was tolled from February 24 to July 28, 1993 . Sincerely, ;� q nr. 4Be President cc: Sandford Skaggs, McCutchen Doyle John Compaglia, Bryan & Murphy Harvey E. Bragdon Community Contra Director of Community Development Development Costa Department County Administration Building County- 651 unty 651 Pine Street 4th Floor, North Wing ,E.--SE:L Martinez, California 945530095 f =_ Phone: 646-2031 CSO; - ST1 COUK� August 27, 1993 John L. Baker, President New Golf Enterprises 3466 Mt. Diablo Boulevard, C-205 Lafayette, CA 94549 Dear Mr. Baker: RE: Land Use Permit Application.for the Fox Creek Country Club (County File #2017-92) Per your request, please find attached a tentative schedule for the processing of the zoning ordinance change and the land use permit for your project. You will note that the schedule provides that our department will give you a decision as to whether we think a Negative Declaration or an Environmental Impact Report is appropriate by September 10, 1993. As I explained to you in our telephone conversation earlier this week,this application is being transferred to Ms. Debbie Aime. Ms. Aime and I will be working together on the project during the next two to three weeks to ensure a smooth transfer. If you have any questions, please feel free to call either Debbie or myself at 646-2091 . Sincerely, CATHERINE OSTERMAN KUTSURIS Senior Planner COK/aa LTRXII/2017-92.CK cc: 2017-92 Sanford Skaggs John Campagilia Harvey E. Bragdon Debbie Aime I NEW GOLF ENTERPRISES APPLICATON PROCESSING SCHEDULE A. SCHEDULE FOR ZONING ORDINANCE CHANGE: Prepare Zoning Ordinance Change September 17 ,1993 * Post Negative Declaration September 17 , 1993 Negative Declaration Posting October 11, 1993 Period Ends Zoning Ordinance Change to P. C. October 19 , 1993 Zoning Ordinance 2nd hearing at PC November 2 , 1993 (if needed) Zoning Ordinance to the BOS -1st November 30, 1993 (assumes a 4 wk scheduling. delay for the BOS) Zoning Ordinance to the BOS - 2nd December 14 , 1993 Ordinance Effective Date January 13 , 1994 * Assumes a Negative Declaration is appropriate; If 'an Exemption is appropriate, the Ordinance could be heard by the Planning Commission at their October 5, 1993 hearing. B. SCHEDULE FOR PROJECT.: ASSUMING NEGATIVE DECLARATION "Internal" Initial Study September 10, 1993 All additional information/studies to October 11, 1993 be submitted by applicant and found to be sufficient for preparing a Negative Declaration Negative Declaration Posting October 15 - Nov 8 , 1993 Zoning Administrator's hearing January 25, 1994 C. SCHEDULE ASSUMING ENVIRONMENTAL IMPACT REPORT "Internal" Initial Study September 10, 1993 All additional information supplied September 30, .1993 by applicant and found to be sufficient Notice of Preparation Issued October 8 - Nov 7 EIR Contract Approved by the Board November 30, 1993 Draft EIR Issued February 18, 1994 Draft 45 Day Review Closes April 4, 1994 Final EIR Prepared May 2 , 1994 Project LUP to Hearing May 9th or May 23 , 1994 ck1: 2017 . sch Harvey E. Bragdon Community Contra Director of Community Devefopmen; Development Costa Department COUry r G County Administration Building 651 Pine Street AT1 & a4T. 4th Floor, North Wing E•—; - Martinez, California 94553-0095 Phone: (510) 646-2031 as September 28 , 1993 Mr. John Baker , New Golf Enterprises 3466 Mt. Diablo Blvd. C-205 Lafayette, Ca 94549 Dear Mr. Baker: RE: LUP 2017-92 The Community Development Departm-ent is completing the environmental review for the above referenced project. Please provide the following information before our final assessment. 1. Please indicate how reclaimed water is provided to the project site from DSRSD. If the water is unable to be piped in, please provide the number of trucks and trips per day which are required to provide adequate water supply to the site. 2 . The County General Plan requires "no net loss" of wetlands. It is unclear from the information provided how you will be mitigating for the loss of wetlands. 3 . The amount of csf of runoff the project will generate. 4 . A copy of the "Hydrogeologic Evaluation for Ground-Water availability" prepared by Engeo. In addition, please provide the location of all existing and proposed wells. 5. A site plan showing all the improvements proposed for the project site and building elevations of each structure. 6. The geotechnical report does not examine a clubhouse location and design and location of additional uses such as. tennis courts, swimming pools, etc. Please provide a preliminary geologic assessment of the clubhouse and acessory uses. Please provide all the information as soon as possible oo avoid delays in processing your application. Should you have any questions, please do not hesitate to call . Sincerely, Debbie Aime Senior Planner cc: Sandy Skaggs w Agenda Item # Community Development Contra Costa County CONTRA COSTA COUNTY PLANNING COMMISSION TUESDAY, JANUARY 4, 1994 - 7:30 P.M. I. INTRODUCTION ORDINANCE TEXT AMENDMENT 3-93: PROPOSED REVISIONS TO CHAPTER 84-80: SECTION 84-80.404, OF THE COUNTY ORDINANCE CODE (A-20) This is a public hearing to consider a proposed revision to Section 84-42.404 and Section 84-80.404 of the County Ordinance Code pertaining to the application of the A-4 and A-20 ordinance. The proposed revision would expand the "Uses - requiring land use permits" to include "Commercial recreational facilities when the principal use is not in a building". The modification would affect all lands Countywide with a zoning designation of A-20, A-40 and A-80. Il. RECOMMENDATION Recommend to the Board of Supervisors that they approve the proposed text amendment as recommended by staff. III. DISCUSSION The Open Space Element of the 1991 General Plan identifies goals and policies that are directed at preserving open space lands for recreation uses. The goals and policies are as follows: A. Open Space Goals: 9-A. To preserve and protect the ecological, scenic and cultural/historic, and recreational resource lands of the County. 9-C. To achieve a balance of open space and urban areas to meet the social, environmental and economic needs of the County now and for the future. B. Open Space Policies: 9-7. Open space shall be utilized for public safety, resource conservation and appropriate recreation activities for all segments of the community. C. Recreational Goals: 9-H. To develop a sufficient amount of conveniently located, properly designed park and recreational facilities to serve the needs of all residents. 9-J. To promote active and passive recreational enjoyment of the County's physical amenities for the continued health, safety and welfare of the citizens of the County. The proposed amendment would allow consideration of proposals for uses such as golf course, baseball/soccer fields, marinas, campgrounds, outdoor sports and athletic complexes, duck and hunting clubs. Uses would be limited to those low- to medium- intensity establishments that do not rely on urban levels of service or infrastructure, i.e., a public water or sewer system, and in the case of flood-prone area will not draw large concentrations of people. The wording for the proposed amendment would be as follows: "Commercial recreational facilities of low to medium-intensity, which do not rely on urban levels of surface, when the principal use is not in a building." DJA/aa SPVIII/Golf.DJA 12/15/93 I COUNTY PLANNING COMMISSION 4 January 1994 - Tuesday 7:30 P.M., Board Room (Transcript of Item #2) ORDINANCE TEXT AMENDMENT: PUBLIC HEARING: ORDINANCE TEXT AMENDMENT #3-93, PROPOSED.REVISIONS TO CHAPTER 84- 80: SECTION 84-80.404, OF THE COUNTY ORDINANCE CODE (A-201: This is a public hearing to consider a proposed revision to Section 84-42.404 and Section 84-80.404 of the County Ordinance Code pertaining to the application of the A-4 and A-20 Ordinance. The proposed revision would expand the "Uses - requiring land use permits" to include "Commercial recreational facilities when the principal use is not in a building". The modification would affect all lands Countywide with a zoning designation of A-20, A-40 and A-80. DJA CHAIRMAN CLARK: Staff, are there any changes suggested to the agenda? MRS. KUTSURIS: Staff recommends that Item #2 be handled as .a consent item. Item #2 is Ordinance Text Amendment #3-93. This would consider a proposed revision to Section 84-42.404 and Section 84-80.404 of the County Ordinance Code pertaining to the application of the A-4 and A-20 Ordinance. The proposed revision would expand the uses which require land use permits to include commercial recreational facilities when the principle use is not a building. The modification would affect all lands countywide with the zoning designation of A-20, A-40 and A-80. CHAIRMAN CLARK: Does anyone wish to make a motion on the suggestion by staff that we place item #2 on the consent calendar and approve it as outlined in the staff report of today's date? COMMISSIONER GADDIS: Did anyone submit--- CHAIRMAN CLARK: No. We have no speakers cards on it. COMMISSIONER TERRELL: So move on your recommendation, Mr. Chairman. COMMISSIONER ACCORNERO: Second. CHAIRMAN CLARK: It's been moved and seconded. All those in favor say "Aye". AYES: Commissioners -Terrell, Accornero, Wong, Woo, Gaddis, Straus, Clark. NOES: Commissioners - None. ABSENT: Commissioners - None. ABSTAIN: Commissioners - None. CHAIRMAN CLARK: It's unanimous. Present the next item, please. Agenda Item # Community Development Contra Costa County COUNTY ZONING ADMINISTRATOR MONDAY, AUGUST 8, 1994 - 1 :30 P.M. I. INTRODUCTION NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SiLVA (Owners), County File #2017-92: The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800 feet on the north side of Johnson Road approximately 11350 feet east of Camino Tassajara, in the Danville area. (A-8, A-40, A-2) (ZA: U-20, V-20, V-21) (CT 3551.03) (Parcel #204-050-021 , #204-100-012, #204-160-001 , #206-200-003, #204-080-007, #204-110-003, #204-180-005). II. RECOMMENDATION Staff recommends this application be denied without prejudice for excessive delays on the part of the applicant in processing this application. III. DISCUSSION This application was filed with the Community Development Department on March 12, 1992 and was subsequently deemed incomplete on April 10, 1992. The applicant submitted a portion of the requested information on October 11, 1992 and the project was deemed complete by default on November 11, 1992. The application was suspended from processing from February 24, 1993 to July 28, 1993 at the request of the applicant to determine if an ordinance text amendment was necessary. The applicant was notified on September 28, 1993 of the required information necessary to complete an initial study of environmental significance. A portion of the requested information was received on April 6, 1994 with the remainder to be submitted within the week. No further information was received. The applicant telephoned staff in early May and indicated the information would be submitted within the week. No information was provided. The applicant has filed to provide staff with the requested information numerous times on a timely manner. Staff, therefore, recommends this application be denied. DJC/aa LUPXXXXI/2017-92.DJC 5/31/94 7/26/94 New Golf Enterprises 3466 Mt. Dtablo Blvd., C-205 - O IER V I Lafayette, CA 94549-3952 I V (510) 284-7100 NEW � FAX 284-7112 AUG 8 1994 T GOLF Cf NTRA COSTA COUNTY (::D ENTERPRISES ZONING ADMINISTRATOR MEETING August 08, 1994 Debbie Chamberlain Senior Project Planner Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club vic Tassajara) Dear Ms . Chamberlain: 1. Attached please find the additional information requested by your letter dated September 28, 1993 . Sincerely, John B ker President cc: Sandford Skaggs, McCutchen Doyle, Walnut Creek New Goif Enterprises 3466 Mt. Dtablo Blvd., C-205 Lafayette, CA 94549-3952 NEW (:Z) FAX84�112 GOLF (�D ENTERPRISES August 08, 1994 Re: Use Permit Application, CCC File No. 2017-92 (Fox Creek Country Club, vic Tassajara) In response to specific. requests in CCC-CDD letter of 28 September: 1. RECLAIMED WATER: a. Route: Overland pipe, buried in existing utility rights of way, are utilized to bring reclaimed water to the site. The route from the DSRSD treatment site (southeast of the intersections of I-680 and I-580 at Johnson Drive in Pleasanton) is overland north, then east along the utility right of way (URW) of I-580 to Camino Tassajara, then north along the URW of Camino Tassajara to Johnston Road, then east along the URW of Johnston Road to a terminus in the southwest corner of Parcel 204-160-100-7 (the "West Ranch, " which comprises the northeastern portion golf course) . b. Requirement: The size of the pipe is about 12 inches in diameter to supply approximately 500 acre feet (ACFT) per year of reclaimed water to the site. The .pipe diameter is sized to meet the peak summer requirements of the golf course (4 . 5 ACFT per day for days on which temperatures meet or exceed 100 degrees Fahrenheit - about 14 days on an average summer at this location) . That requirement is buffered somewhat by the 45 ACFT of storage afforded in onsite lakes or ponds integrated into the golf course design. The grade of reclaimed water is Title 22 , Tertiary (non potable, yet better than what 800 of the country drinks ! ) . C. Engineering: Final design of the pipeline will be initiated by DSRSD once the golf course use has been approved. Detailed engineering and installation of the pipeline takes about. six months in the dry season, seven months when more two months or more of the November-March "rainy season" are involved. This is good fit for a golf project because it takes , 6 to 9 months of coarse and fine grading, irrigation and drain system installation, etc. , before the course is ready for grass irrigation. Due to the approximate rise of 600 feet in elevation from about 100 feet Mean Sea Level (MSL) at the source to 700 feet MSL. at golf course entry., the pipeline requires about three pumps along its 8 mile length. One pump will be located at the DSRSD source site and two along Camino Tassajara in the URW. Pumps are electrically driven, inconspicuous, and look like a. 4 X 5 foot utility box. d. Trucking: No trucking of water is required for irrigation of the golf course . Turf growing will not commence on the golf project until the reclaimed water pipeline is in place and 1 providing irrigation (the cost of trucking in water for course irrigation would be prohibitive: 150 to 200 tank truckloads per day! ) . Since this course is not designed to use any on-site existing or developed water (ie. wells) for course irrigation or clubhouse use, any construction water requirements (dust reduction) will be trucked in until the reclaimed water is available at the site. Worst case (hot day, summer) dust reduction for this site is about four - 4, 000 gallon water truckloads per day. Normal day dust reduction requirements are about l 1/2 to 2 truckloads (6, 000 to 8, 000 GPD) . 2 . WETLANDS: No wetlands are lost through the construction of this golf course project. Indeed, there is a net gain of about 13 acres of lakes. internal to the golf course site. a. Lakes: The two existing stock ponds .are kept and improved, as ponds or lakes on the course. Other, new, additional lakes are created on the course and will be used to store rain runoff internal to the course/clubhouse and reclaimed water pumped to the project from off-site. b. Creeks: No existing streambeds are effected by the course. The main creek "internal" to the course (unnamed) proceeds along Johnston Road and is not altered by golf course construction. and associated drainage. Indeed, the Johnston Road creek is not part of the course, is left in its natural state, and is not in play or accessible to golfers. Due to the relative flatness of the topography along this creek through the golf course site, no drainage currently occurs from the site into the creek, nor will any drainage occur as a result of construction. R C. Drainage: In the northwest sector of the project along the little valley which continues southwest of the existing stockpond, there is some nuisance drainage which currently occurs in severe rains onto the two adjacent properties immediately to the west. This drainage does not reach Tassajara Creek. This nuisance drainage onto the adjacent properties will be eliminated through course construction and internal drainage back into course ponds . 3 . RUNOFF: No runoff generated internal to the course and clubhouse effects adjacent properties or creeks . All runoff generated is collected in course lakes and then utilized later for course irrigation. The overall effect of course construction is to reduce runoff: hills tend to be leveled, permitting more rain to soak into the soil . Additionally, the soil medium is improved from the existing clay-silt, providing better water retention in the soil and eliminating soil erosion. a. Impervious Surfaces: The project creates 11.93 Acres of impervious services per Table 1, below. This in turn would generate 11 . 88 CFS in a 1 inch per hour worst case rain. That is the equivalent of 42, 771 CFH / .98 ACFT per hour for the 50 year occurrence one inch per hour rain: For 3 inches per day (100 year occurring day) , 128 , 313 CFD / 2 .94 ACFT per day is produced, or 1 . 49 CFS average over the 24 hour period. That is well within the capacity of the approximately 242 ACFT of storage provided by on 2 site lakes . Over a nominal normal 20 inch rainfall year, impervious surfaces "collect" 19 . 7 ACFT, which are deposited in course lakes through the stormwater drain system. TABLE 1 IMPERVIOUS SURFACES Created by Fox Creek Project I14PERVIOUS SURFACES ITEM SOFT ACRES CLUBHOUSE FACILITY 166, 666 3 .78 (33, 152 SQFT Total All Floors) Roofline and Decks 24, 586 .54 Patios 10,400 .24 Parking (300 Cars) 130, 680 3 .00 TENNIS/SWIM/EXERCISE FACILITY 250, 061 5.74 (14, 541 SQFT All Floors) Roofline 14, 036 .32 Patios & Pools 18,225 .42 Parking (150 Cars) 65,340 1.50 Outdoor Tennis Courts (13) 152,460 3 .50 ACCESS ROADS (New, Hard Surfaced) 106, 848 2 .45 . (2, 500 X 421 ) TOTAL 523, 575 SQFT 11.97 Acres b. Normal Surfaces: Whereas, the golf course does not produce more GPS than grazing pasture (it actually causes less to be generated) , the course design easily accommodates runoff, even. at worst case rain rates . If ground saturation is assumed (thereby- permitting therebypermitting 1000-. runoff over the nominal 400 acres of watershed which underlies and feeds the course) , a one inch per hour rain generates 33 .9 ACFT in one hour, or 102 ACFT in 3 hours. Again, this is well within the capacity of the internal lake system to handle. In the winter rainy season the Course Superintendent tries to utilize as much natural rain/runoff as possible. He, therefore, keeps the water level in the lower lakes on dry days at about one third of capacity. Since the lower lakes have a capacity of about 162 ACFT, the course can routinely handle any worst case day without checking a weather report (2/3rds of 162 ACFT of lower lake storage capacity = 108 ACFT = immediate capacity to handle the 102. 3 ACFT created on a saturated 3 inch rain worst case day, plus the 2 .94 ACFT generated by impervious surfaces, per para 3 .a. , above) . 4 . HYDROGEOLOGIC EVALUATION: The ENGEO report requested is attached. The three wells not previously depicted were the three on the Silva Ranch, to the south. One well on the northwest section of the Silva property serves the western-most four acre property north of Johnston Road about 250 yards north of the well . The other two wells serve the Silva farmhouse and are both within 100 feet northeast of the farmhouse, as shown. It should be pointed out that none of these wells, or any other shown on any of. the properties used for the golf course, will be used either for course irrigation or the clubhouse (cooking, drinking, etc. ) . All of the water requirements for the complete facility will be met though the use of reclaimed water. The potable water requirements (clubhouse, swimming pool) will be met though Super-Still treat- ment on site of reclaimed water and site runoff collected. 5. BUILDINGS: A site plan showing the Clubhouse, Tennis/Swimming/ Exercise Center, associated parking and access roads is attached. The 27 hole golf course has the following buildings associated: a. Clubhouse Facility: Wood Frame/Stucco construction on concrete piers and concrete retaining walls on uphill (northwest and northeast) sides . Essentially a 2 1/2 story structure which does not exceed 35 feet in height when viewed from the down hill southeast and southwest, it mostly looks like a 1 12/2 story building from the uphill northwest and northeast. The indoor finished clubhouse encompasses 38, 452 square feet (SQFT) : 23 , 891 SQFT on the first floor and 14, 561 SQFT on the second floor. This facility contains a golf pro shop, locker rooms, a major food i t service operation serving several dinning rooms, lounges, and administrative offices . An unfinished concrete basement like structure of 10, 215 SQFT is located below grade under the southwest portion of the first floor and is utilized for golf cart, golf bag and furniture storage. Approximately 6, 630 SQFT of deck accessible from the 2nd floor is planned on top of the first floor mostly to the southeast and southwest. On grade patio of about 10 , 400 SQFT is planned off the first floor to the southeast and southwest . Nominal interior dimensions in feet are: first floor 266 X 96 ; second floor 248 X 76; cart and bag storage 160 X 64 . b. Tennis/Swimming/Exercise Facility: Square shaped 2 1/2 story building of about 14, 541 SQFT, of which 12, 321 SQFT are on the first floor. Located approximately 200 yards east of the Main Clubhouse in the western part of the area bordered by holes 3 , 4 and 5 of the North Valley Nine. Wood Frame/Stucco construction which does not exceed 35 feet in height . Each side of square is 111 feet. The building contains 3 indoor handball/ racquetball courts (20 X 40' each) , exercise and exercise equipment rooms, locker rooms including shower and toilet facilities, spas, saunas, pro shop, administrative offices for the tennis, exercise and swimming professionals and their assistants . The lighted outdoor tennis courts are of standard size and composite material are built over appropriately keyed, filled and compacted underlayment materi- al . A 13th "Stadium Court" includes seating for 300 observers . 4 c. Maintenance Facility: A Butler building type structure of about 4, 200. SQFT and 1 1/2 stories is located in the Maintenance area (vicinity of the two houses at the old West Ranch) . It houses mowers and other course maintenance equipment and provides maintenance shops for the equipment, offices and lounge for the Greens Superintendent and his staff of - about 7 people. 6. GEOLOGIC ASSESSMENT: The Clubhouse, Exercise/Tennis/Swimming Facility and Maintenance Barn are located on the standard clay-silt soils prevalent throughout the site. None are located on or adjacent to slide areas or surface seismic faults. The soils are . stable and adequately support pier, retaining wall and grade beam foundation construction. Grading involved is minimal : soils will be keyed and compacted in accordance with code and established engineering practices. No streams, wetlands or springs exist in the areas of building construction. All building- designs include supporting storm drain systems which drain to course lakes on site. 5 .. ��i-tl ►3 iT�� Community Contra Harvey oE.f Bragdon Director of Community pevelopn Development Costa Department COUnty County Administration Building 651 Pine Street 4th Floor, North Wing Martinez, California 94553-0095 Phone: 646-2031 - `= fT�.cOkiK{` August 25, 1994 John Baker New Golf Enterprises 3466 Mt. Diablo Boulevard, C-205 Lafayette, CA 94549-3952 Dear Mr. Baker: RE: 2017-92 I have reviewed the material submitted at the August 8, 1994 Zoning Administrator hearing, as requested by my letter dated September 28, 1993. The following information was not provided: 1 . A site plan .showing the improvements to the site and building elevations of each structure. Your letter dated August 8, 1994 describes additional structures that were not shown on the original submittal. 2. Additional structures identified in your August 8, 1994 letter were not described in the Preliminary Geologic Assessment prepared by Engeo, Inc. This additional assessment was required in my September 28, 1993 letter. 3. The "Hydrogeologic Elevation", prepared by Engeo, Inc., was not provided which was required in my September.28, 1993 letter. Furthermore, your August 8, 1994 letter mentions "The potable water requirements will be met through super-still treatment on site of reclaimed water and site run-off collected." There is no conceptual plan in the file which describes this facility. This information will be required to further process your application. Since the following information was not provided as requested by the Zoning Administrator on August 8, 1994 and my letter of September 28, 1993, staff will be recommending denial of your application. Sincerely, DEBBIE CHAMBERLAIN Senior Planner DJC/aa - LTRXVII/2017-92.DJC cc: 2017-92 a • Agenda Item #� Community Development Contra Costa County COUNTY ZONING ADMINISTRATOR MONDAY, SEPTEMBER 12, 1994 - 1 :30 P.M. I. INTRODUCTION NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SILVA (Owners), County File #2017-92: The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800 feet on the north side of Johnson Road approximately 1 ,350 feet east of Camino Tassajara, in the Danville area. (A-8, A-40, A-2) (ZA: U-20, V-20, V-21) (CT 3551.03) (Parcel #204-050-021 , #204-100-012, #204-160-001 , #206-200-003, #204-080-007, #204-110-003, #204-180-005). IL RECOMMENDATION Staff recommends this application be denied without prejudice for excessive delays on the part of the applicant in processing this application. III. DISCUSSION This application was filed with the Community Development Department on March 12, 1992 and was subsequently deemed incomplete on April 10, 1992. The applicant submitted a portion of the requested information on October 11 , 1992 and the project was deemed complete by default on November 1 1 , 1992. The application was suspended from processing from February 24, 1993 to July 28, 1993 at the request of the applicant to determine if an ordinance text amendment was necessary. The applicant was notified on September 28, 1993 of the required information necessary to complete an initial study of environmental significance. A portion of the requested information was received on April 6, 1994 with the remainder to be submitted within the week. No further information was received. The applicant telephoned staff in early May and indicated the information would be submitted within the week. No information was provided. At the August 8, 1994 Zoning Administrator hearing, the applicant provided some of the information requested in staff's September 28, 1993 letter. However, the applicant has not provided all the required information. The applicant was notified by letter on August 25, 1994 of staff's requirements. The applicant has failed to provide staff with the requested information numerous times on a timely manner. Staff, therefore, recommends this application be denied. DJC/aa LUPXXXXI/2017-92.DJC 5/31/94 7/26/94 8/25/94 n l t t t5\T \C)E New Golf Enterprises PO Box 381 Lafayette, CA 94549MKXr-D-3.81 NEW �./ (510)284-7100 FAX 284-7112 er ! ; S 1 ' 3 . (2--) ENTERPRISES September 09, 1994 Debbie Chamberlain Senior Project Planner Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club vic Tassajara) Dear Ms . Chamberlain: Attached please find the additional information requested by your letter dated August 25, 1994 (paragraph numbers keyed to yours) . 1. A site plan which includes the Tennis/Swim/Exercise Center and the associated pool/patio, tennis courts (one stadium court seating 300 and 12 regular tennis courts) , and parking (for 150 vehicles) . 2 . The Preliminary Geologic Assessment prepared by ENGEO (Revised February 12 , 1992) addresses the general area for course and club- house development. It shows known slide areas and notes soil types and distribution. The Tennis/Swim/Exercise Center was located, as a detached part of the Clubhouse Facility, in the same soil type clear of any slides with the concurrence of ENGEO: both the main clubhouse and TSEC/pool/courts are suitable for both sites geolog- ically. Of course ENGEO also recommends further site specific soils studies when the final clubhouse design is conducted, which would most certainly be completed prior to engineering/structure design of the buildings, pool and courts . 3 . The Hydrogeologic Evaluation is attached. Our extra copies were misplaced when we. recently moved our offices . Attached also find a description of the Reverse Osmosis System which will be used for the potable water requirement for the clubhouse (drinking, cooking, showers, etc. ) . The Aqua Design model S-050 meets the needs of the Clubhouse and TSE Center in that it provides significantly more of a reserve capacity than a similarly priced "super still" system. The ROS also is considerably more energy efficient, somewhat more reliable, and generally well understood by most municipalities (the technology has been available for a number of years) . .. gyp. . The concept is to use reclaimed water as the exclusive source or "feed supply" to the ROS, since there is virtually no residue generated by tertiary water. The average daily . "clubhouse requirement" is 20, 000 gallons of potable water per day; it would be prudent to have a surge capacity of 35, 000 to 40, 000 GPD for special events (member tournaments for instance) . The model 5-050 provides a maximum of 50, 000 GPD when operated continuously. .Note thatthe plant size is 15 X 5 X 7 feet . It is housed in a small building of that size adjacent to the kitchen/back of the house area of the main clubhouse. Potable water is stored in a 30, 000 gallon tank located adjacent to the ROS shed (dimensions of tank: 25 foot diameter, 8 foot height) . The storage tank is masked by landscaping foliage. Please note the new address of New Golf Enterprises : PO Box 381, Lafayette, CA 94549-0381. Your letter of August 25, postmarked August 30 was received by us on September 8, 1994 . Hopefully the information provided herein is sufficient for consideration of this application. Sincerely, ohn 4Baer President cc: Sandford Skaggs, McCutchen Doyle, Walnut Creek Agenda Item # 2, Community Development Contra Costa County COUNTY ZONING ADMINISTRATOR. MONDAY, OCTOBER 10, 1994 - 1 :30 P.M. I. INTRODUCTION NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SILVA (Owners), County File #2017-92: The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800 feet on the north side of Johnson Road approximately 1 ,350 feet east of Camino Tassajara, in the Danville area. (A-8, A-40, A-2) (ZA: U-20, V-20, V-21) (CT 3551.03). (Parcel #204-050-021 , #204-100-012, #204-160-001 , #206-200-003, #204-080-007, #204-110-003, #204-180-005). II. RECOMMENDATION Continue indefinitely to allow staff time to coordinate with Dublin-San Ramon Services District on the issue of reclaimed water, and process the appropriate environmental document. Ill. DISCUSSION The applicant has provided staff with the information that has been requested for the past two years. The project has been modified to include a potable water treatment plant, which will require approval of the County Health Services Department. Furthermore, a verifiable source of water has not been determined for the project. The applicant has received authorization from the Dublin-San Ramon Services District to participate in a planning study. This authorization does not guarantee the applicant will receive water. The applicant is required to pay Dublin-San Ramon Sanitary District appropriate fee to .review the potential for providing water. The applicant is also responsible for contracting through the Dublin-San Ramon Services District for .a consultant to complete the environmental review. The County will be the lead agency in processing the environmental documents, with the Dublin-San Ramon Services District as a responsible agency. Since this project is relying solely on recycled water for water service to the property, all the impacts associated with providing reclaimed water to the site need to be examined. DJC/aa LUPXXXXI/2017-92.DJC 5/31/94 7/26/94 8/25/94 9/27/94 b,XH Ir 7 . .� New Golf Enterprises 3466 Mt. Diablo Blvd., C-205 Lafayette, CA 94549-3952 NEW (510)284-7100 FAX284-7112 ��I I GOLF ;r . Q, P 3. 24 <:ZD ENTERPRISES LL April 06, 1994 _Debbie Aime Senior Project Planner Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club vic Tassajara) Dear Ms. Aimee: 1. . Attached please find the text of the additional information requested by your letter dated September 28, 1993 (also included) . The site plan, building elevations and copy of ENGEO' s Hydrogeo- logic Evaluation will be forwarded within the week. Sincerely, John L.4Baer President cc: Sandford Skaggs, McCutchen Doyle, Walnut Creek �(ca h no+ prDYi d.Ld New Golf Enterprises i 3466 Mt.Diablo Blvd., C-205 Lafayette, CA 94549-3952 N E (510)284-7100 FAX 284-7112 GOLF (Z) ENTERPRISES April 06, 1994 Re: Use Permit Application, CCC File No. 2017-92 (Fox Creek Country Club, vic Tassajara) In response to specific requests in CCC-CDD letter of 28 September: 1. RECLAIMED WATER: a. Route: Overland pipe, buried in existing utility rights of way, are utilized to bring reclaimed water to the site. The route from the DSRSD treatment site (southeast of the intersections of I-680 and I-580 at Johnson Drive in Pleasanton) is overland north, then east along the utility right of way (URW) of I-580 to .Camino Tassajara, then north along the URW of Camino Tassajara to Johnston Road, then east along the URW of Johnston Road to a terminus in the southwest corner of Parcel 204-160-100-7 (the "West Ranch, " which comprises the northeastern portion golf course) . b. Requirement: The size of the pipe is about 12 inches in diameter to supply approximately 500 acre feet (ACFT) per year of . reclaimed water to the site. The pipe diameter is sized to meet the peak summer requirements of the golf course" (4 .5 ACFT per day for days on which temperatures meet or exceed 100 degrees Fahrenheit - about 14 days on an average summer at this location) . That requirement is buffered somewhat by the 45 ACFT of. storage afforded in onsite lakes or ponds integrated into the golf course design. The grade of reclaimed water is Title 22, Tertiary (non- potable, yet better than what 800 of the country drinks ! ) . C. Engineering: Final design of the pipeline will _ be initiated by DSRSD once the golf course use has been approved. Detailed engineering and installatioh of the pipeline takes about six months in the dry season, seven months when more two months or more of the November-March "rainy season" are involved. This is good fit for a golf project because it takes 6 to 9 months -of coarse and fine grading, irrigation and drain system installation, etc. , before the course is ready for grass irrigation. Due to the approximate rise of 600 feet in elevation from about 100 feet Mean Sea Level (MSL) at the source to 700 feet MSL at golf course entry, the pipeline requires about three pumps along its 8 mile length. One pump will be located at -the DSRSD source site and two along Camino Tassajara in the URW. Pumps are electrically driven, inconspicuous, and look like a 4 X 5 foot utility box. d. Trucking: . No trucking of water is required for irrigation of the golf course . Turf growing will not commence on the golf project until the reclaimed water pipeline is in place and 1 providing irrigation (the cost of trucking in water for course irrigation would be prohibitive: 150 to 200 tank truckloads per day! ) . Since this course is not designed to use any on-site existing or developed water (ie. wells) for course irrigation or clubhouse use, any construction water requirements (dust reduction) will be trucked in until the reclaimed water -is available at the site. Worst case (hot day, summer) dust reduction for this site is about four 4, 000 gallon water truckloads per day. Normal day dust reduction requirements are about 1 1/2 to 2 truckloads (6, 000 to 8, 000 GPD) . 2 . WETLANDS: No wetlands are lost through the construction of this golf course project. Indeed, there is a net gain of about 13 acres of lakes internal to the golf course site. a. Lakes: The two existing stock ponds are kept and improved, as ponds or lakes on the course. Other, new, additional lakes are created on the course and will be used to store rain runoff internal to the course/clubhouse and reclaimed water pumped to the project from off-site. b. Creeks: No existing streambeds are effected by the course. The main creek "internal" to the course (unnamed) proceeds along Johnston Road and is not altered by golf course construction and associated drainage. Indeed, the Johnston Road creek is not part of the course, is left in its natural state, and is not in play -or accessible to golfers. Due to the relative flatness of .the topography along this creek through the golf course site, no drainage currently occurs from the site into the creek, nor will any drainage occur as a result of construction. c. Drainage: In the northwest sector of the project along the little valley which continues southwest of the existing stockpond, there is some nuisance drainage which currently occurs in severe rains onto the two adjacent properties immediately to the west. This drainage does not reach Tassajara Creek. This nuisance drainage onto the adjacent properties will be eliminated through course construction and internal drainage back into course ponds . 3 . RUNOFF: No runoff generated internal to the course and clubhouse effects adjacent properties or creeks. All runoff generated is collected in course lakes and then utilized later for course irrigation. The overall effect of course construction is to reduce runoff : hills tend to be leveled, permitting more rain to soak into the soil . Additionally, the soil medium is improved from the existing clay-silt, providing better water retention in the soil and eliminating soil erosion. a. Impervious Surfaces: The project creates 11 . 93 Acres of impervious services per Table 1, below. This in turn would generate 11 . 88 CFS in a 1 inch. per hour worst case rain. That is the equivalent of 42 , 771 CFH / .98 ACFT per hour for the 50 year occurrence one inch per hour rain. For 3 inches per day (100 year occurring day) , 128, 313 CFD / 2 . 94 . ACFT per day is produced, or 1 .49 CFS average over the 24 hour period. That is well within the capacity of the approximately 242 ACFT of storage provided by on 2 site lakes . Over a nominal normal 20 inch rainfall year, impervious surfaces "collect" 19 .7 ACFT, which are deposited in course lakes through the stormwater drain system. TABLE 1 IMPERVIOUS SURFACES Created by Fox Creek Project IMPERVIOUS SURFACES ITEM SOFT ACRES CLUBHOUSE FACILITY 162, 666 3 .74 (33, 152 SQFT Total All Floors) Roofline and Decks 21, 586 .50 Patios 10,400 .24 Parking (300 Cars) 130, 680 3 .00 TENNIS/SWIM/EXERCISE FACILITY 250, 061 5.74 (14, 541 SQFT All Floors) Roofline 14, 036 .32 Patios & Pools 18,225 .42 Parking (150 Cars) 65,340 1.50 Outdoor Tennis Courts (13) 152,460 3 .50 . ACCESS ROADS (New, Hard Surfaced) 106, 848 2 .45 (2, 500 X 421 ) TOTAL 519,575 SQFT 11.93 Acres b. Normal Surfaces: Whereas, the golf course does not produce more GPS than grazing pasture (it actually causes less to be generated) , the course design easily accommodates runoff, even at worst case rain rates. If ground saturation is assumed (thereby permitting 1000-. runoff over the nominal 400 acres of watershed which underlies and feeds the course) , a one inch per hour rain generates 33 . 9 ACFT in one hour, or 102 ACFT in ,3 hours . Again, this is well within the capacity of the internal lake system to handle . In the winter rainy season the Course Superintendent tries to utilize as much natural rain/runoff as possible. He, therefore, keeps the water level in the lower lakes on dry days at about one third of capacity. Since the lower lakes have a capacity of about 162 ACFT, the course can routinely handle any worst case day without checking a weather report (2/3rds of 162 ACFT of lower lake storage capacity = 108 ACFT = immediate capacity to handle the 102 3 ACFT created on a saturated 3 inch rain worst` case day, plus the 2 . 94 ACFT generated by impervious surfaces, per para 3 .a. , above) . 4. HYDROGEOLOGIC EVALUATION: The ENGEO report requested is attached. The three wells not previously depicted were the three on the Silva Ranch, to the south. One well on the northwest section of the Silva property serves the western-most four acre property north of Johnston Road about 250 yards north of the well . The other two wells serve the Silva farmhouse and are both within 1.00 feet northeast of the farmhouse, as shown. It should be pointed out that none of these wells, or any other shown on any of . the properties used for the golf course, will be used either for course irrigation or the clubhouse (cooking, drinking, etc. ) . All of the water requirements for the complete facility will be met though the use of reclaimed water. The potable water requirements (clubhouse, swimming pool) will be met though Super-Still treat- ment on site of reclaimed water and site runoff . collected. 5. BUILDINGS: A site plan showing the Clubhouse, Tennis/Swimming/ Exercise Center, associated parking , and access roads is attached. The 27 hole golf course has the following buildings associated: a. Clubhouse Facility: Wood Frame/Stucco construction on concrete piers and concrete retaining walls on uphill (northwest and northeast) sides. Essentially a 2 1/2 story structure which does not exceed 35 feet in height when viewed from the down hill southeast and southwest, it mostly looks like a 1 12/2 story building from the uphill northwest and northeast. . The indoor finished clubhouse : encompasses 33, 152 square feet (SQFT) : 19 , 891 SQFT on the first floor and 13, 261 SQFT on the second floor. This facility contains a golf pro shop, locker rooms, a major food. service operation serving several dinning rooms, lounges, and administrative offices . An unfinished concrete basement like structure of 10, 215 SQFT is located below grade under the southwest portion of the first floor and is utilized for golf cart, golf bag and furniture storage. Approximately 6, 630 SQFT of deck accessible from the 2nd floor is planned on- top of the first floor mostly to the southeast and southwest. On grade patio of about 10,400 SQFT is planned off the first floor to the southeast and southwest . Nominal interior dimensions in feet are: first floor 311 X 64; second floor 288 X 46; cart and bag storage 160 X 64 . b. Tennis/Swimming/Exercise Facility: Square shaped 2 1/2 story building of about 14, 541 SQFT, of which 12 , 321 SQFT are on the first floor. Located approximately 200 yards east of the* Main Clubhouse in the western part of the area bordered by holes 3 , 4 and 5 of the North Valley Nine. Wood Frame/Stucco construction which does not exceed 35 feet in height. Each side of square is 111 feet. The building contains 3 indoor handball/ racquetball courts (20 X 401 each) , exercise and exercise equipment rooms, locker rooms including shower and toilet facilities, spas, saunas, pro shop, administrative offices for the tennis, exercise and swimming professionals and their assistants . The lighted outdoor tennis courts are of standard size and composite material are built over appropriately keyed, filled and compacted underlayment materi- al . A 13th "Stadium Court" includes seating for 300 observers . 4 , r c. Maintenance Facility: A Butler building type structure of about 4, 200 SQFT and 1 1/2 stories is located in the Maintenance area (vicinity of the two houses at the old West Ranch) . It houses mowers and other course maintenance equipment and provides maintenance shops for the equipment, offices and lounge for the Greens Superintendent and his staff of about 7 people. 6. GEOLOGIC ASSESSMENT: The Clubhouse, Exercise/Tennis/Swimming Facility and Maintenance Barn are located on the standard clay-silt soils prevalent throughout the site. None are located on or adjacent to slide areas or surface seismic faults. The soils are stable and adequately support pier, retaining wall and grade beam foundation construction. Grading involved is minimal : soils will be keyed and compacted in accordance with code and established engineering practices . No streams, wetlands or springs exist in the areas of building construction. All building designs include supporting storm drain systems which drain to course lakes on site. 5 2 Based on the above information, staff recommends the application be denied with .prejudice for excessive delays by the applicant. If the Zoning Administrator determines there is merit in denying the application without prejudice, allowing the applicant the opportunity to refile the application immediately, the following information is required to process the application: A. Preliminary engineering studies to determine the approximately location of the pipeline and pumping facilities. B. Detailed information on the proposed Reverse Osmosis Water Demineralization System or other system to provide potable water to the site that is acceptable; to the County Health Services Department, Environmental Health Division, and the State Department of Health Services. DJC/aa LUPXXXXI/2017-92.DJC 5/31/94 7/26/94 8/25/94 9/27/94 1/3/95 CONTRA COSTA COUNTY ZONING ADMINISTRATOR 10 OCTOBER 1994 - 1 :30 P.M. Item #2 on the Agenda. LAND USE PERMIT: CONTINUED PUBLIC HEARING: NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SILVA (Owners) - #2017- 92 The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800-ft., on the north side of Johnston Road, approximately 1,350-ft., east of Camino Tassajara, in the Danville area.(A-80, A-40, A-2) (ZA: U-20)- (CT3551 .03) (Parcel #204-050- 021, #204-100-012, #204-160-001, #206-200-003, #204-080-007, #204-110-003, #204-180-005), (Continued from 9-12-94) - DT (RHD) ROSE MARIE PIETRAS: Staff is recommending continuing this indefinitely to allow staff time to coordinate with Dublin-San Ramon Services District on the issue of reclaimed water and to process the appropriate environmental documents. MR. BARRY: Thank you. Is the applicant present? MR. JOHN BAKER: I'm with New Golf Enterprises. What we're requesting is a continuance to a date certain to determine what the process will be for approving and obtaining reclaimed water. We think that's the logical next step and if we can do it in a finite period of time, I think we can determine what the process is and that would be a big help to us. MR. BARRY: Is there anything else you would like to add? MR. BAKER: Well, in the staff report, there is a discussion---a minor discussion about the potable water. We're totally flexible on how the potable water is done, whether it's through the reverse osmosis system, a super still or pumping water in the ground and coming back up through wells, whatever works---that's for the clubhouse requirement. MR. BARRY: Sir, how much time do you think you'd need? You asked for a date certain. How much time would you like for pulling together the various information that the staff is looking into? MR. BAKER: Well, what we're looking for is a determination of what the process is; what---really, it's a function of how quickly the staff and staff from the Dublin-San Ramon Water Services District can meet and agree and I would think that---we would hope that within a month that meeting could happen and we could determine what the required steps would be. MR. BARRY: Well, I'm reluctant to continue this for a month without knowing that we're going to have a staff report. Certainly, the environmental documentation will have to be done; whether that is in the form of an environmental impact report or a mitigated declaration, or what-have-you, it seems to me that given the processing requirements for any of those documents, that a month is not going to be sufficient time. It may be sufficient time to pull together the technical information upon which to perfect the request and the proposal; but, to analyze it and to document it for CEOA purposes is probably insufficient. I'm going to suggest to you that three (3) months continuance would be appropriate. MR. BAKER: That's fine. MR. BARRY: Okay. Is there anything else that you'd like to add to your testimony? MR. BAKER: No. Thank you. MR. BARRY: Thank you very much. I have a speaker's.card from Jim Blickenstaff, 2410 Talavera Drive, San Ramon, California, who indicates that he requests postpone- ment; he opposes the project; he has given us a written request which among other things asks that additional notification be provided to the Preserve Area Ridgelands Committee, Save Mt. Diablo, Mt. Diablo Audobond, Sierra Club and Save our Hills. t: . In continuing this today I would not be asking for additional noticing since it would be a continued public hearing; but, I would ask that the staff take this in submission and so notify the organizations as to the continuance date should one be granted. Is there anyone else who would like to speak on this item? I have a speakers card for a Mr. Steve Williams. 'Would you like to speak, Mr. Williams? Mr. Williams spoke from the audience section of the Board Room. He is not audible to the transcriber. MR. BARRY: Mr. Williams has indicated that he would like to be notified as well and would ask staff to please do so along with the other organizations. MR. TONY TEXIERA, 6615 Johnston Road, Danville, California. I didn't plan on speaking today. I wanted to hear what was going to be said; but, what I don't understand is they applied for this in 1992 and now they're just figuring out they are going to have to get together with the County about water. I don't quite understand that. It's kind of frustrating for me because I have to take off work to be here and this is going to go on and on. It started, I believe, in August and now it will be another three months down the road when, in fact, I thought they applied for this originally two years ago. And., I'm not really saying I'm against the project. All I'm -2_ saying is that I want to know what's going on because it seems like it's just going to go on forever. That's really all I have to say. It's kind of frustrating though. MR. BARRY: And, I understand your frustration and I'm sure that the applicant does too, In terms of the time limit that you alluded to, there is a stipulation in the California Environmental Quality Act that a delay on the part of the applicant in providing information necessary for the environmental review will result in extension of the time limits in it; so, that means if we don't have the information to do the environmental document,that sometimes these things do get continued an reasonable amount of time from the perspective of someone like yourself who has to take time off to come down and I do apologize for the process in that respect. We try to make sure that everyones' constitutional rights are protected. MR. BAKER: Right. I understand. 1 was going to add that with what they've submitted so far---because I.don't know what they have submitted---I take it that the County is happy with that, because I don't they haven't submitted anything for I guess two years and I think at the last hearing I was at they said that they were waiting for some more information from this group. Now, are we saying that we've accepted that portion of the information that they've supplied and now we're going under something else or what are we saying? MR. BARRY: The County has deemed the application submittal complete for the purposes of proceeding with the process. Now, what that means is that the next step is to go into the environmental review. Additional information is needed to complete that environmental review and that's what we're trying to complete at this point. So, if you are interested in reviewing the project files, it's all a matter of public record and the project planner is Debbie Chamberlain and you can call her, make an appointment and come in and take a look at the file at any time that is mutually convenient for you and staff. MR. BAKER: Okay. Thank you. MR. BARRY: So,' if there is no one else to speak on this item---I'm looking now at the schedule---we don't seem to have the 1995 meeting schedule. At the risk of unduly delaying the people who are waiting for their hearing, I'm going to ask staff to call upstairs for a calendar of 1995 so they can give me a date that's essentially three months from today in order to continue this hearing to a date certain and we'll go ahead with the next item on the agenda. This matter will be continued to the meeting of January 9, 1995. _3_ CONTRA COSTA COUNTY ZONING ADMINISTRATOR 9 JANUARY 1995 -1:30 P.M. Item #3 on the agenda,- Decision only. LAND USE PERMIT - CONTINUED PUBLIC HEARING: NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SILVA (Owners) - #2017- 92 The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800-ft., on the north side of Johnston Road, approx., 1,350-ft., east of Camino Tassajara, in the Danville area. (A-80, A-40, A-2) (ZA:U-20) (CT-3551 .03) (Parcel #204-050-021, #204-100-012, . #204-160-001, #206-200-003, #204-080-007, #204-110-003, #204-180-005) - (Continued from 10/10/94) (DC) - (RHD) (The following dialogue picks up with the Zoning Administrator talking after the applicant gives his rebuttal) MR. DRAKE: I have two concerns with this project. One is that the applicant apparently realized early on.that in order to establish this project there would have to be major provision for extension of water to the site and is only now beginning to engage a potential water district about providing that water and I think these things. ought to be identified early on in the process rather than after the application is filed with the County. My other concern is that the sheer scope of extending a water Fine eight (8) miles to the site, costing $2,000,000. with the sole purpose of serving this site is---I'm not sure that it's realistic given today's planning considerations in terms of annexations and decisions that would have to involve other properties and may raise a number of planning issues beyond the scope of this project. I'm also concerned that there hasn't, until the day of the hearing that we seem to get any response from the applicant from the previous identification on the necessary information that we need to pursue this thing and I don't want to trouble the neighbors further on this matter. That's not to say that ultimately down the line it may be possible to demonstrate the feasibility of establishing a golf course on this site and we would be Willing to consider that; but, based on the existing circumstances for that area, I'm not prepared today to come to the conclusion that there is a reasonable possibility that the County is likely to be able to approve this project. So, based on those matters, I am going to go along with the staff recommendation and deny the application. At the same time, I would ask staff to advise the applicant of his appeal rights if he chooses to appeal this decision to the next higher body. _1_ MRS. CHAMBERLAIN: To clarify your decision, briefly, that is denial with prejudice? MR. DRAKE: Yes. Basically, what that means is that we would not accept an application within a year's time frame unless it addresses the issues that have been raised to date in terms of level of information. We would have to have a substantially changed application. It would have to address the water provision issues, the reclaimed water issues to the site---you would need to demonstrate to us that there is a feasible program from a planning, engineering and financial perspective to provide for reclaimed water from D.S.R.S.D., or some other water source to the site. In the absence of that within a one-year time frame, we would not accept an application, unless you file an appeal within ten days. MRS. CHAMBERLAIN: The appeal must be filed within a ten-day period which expires on January 19, 1995 at 5:00 P.M. The appeal must state the grounds for the appeal and be accompanied by the appropriate fee and noticing envelopes. An appeal instruction hand-out is on the railing. This item, if appealed, would then be heard by the San Ramon Valley Regional Planning Commission at a date to be specified later and notification would be mailed to anyone who testified at the numerous hearings that have been held or is within 300-ft., of the subject property. MR. DRAKE: And, to anyone who submitted green sign-in slips. There was no further discussion on this item. -2- j Agenda Item # Community Development Contra Costa County COUNTY ZONING ADMINISTRATOR MONDAY, JANUARY 9, 1995 - 1 :30 P.M. 1. INTRODUCTION NEW GOLF ENTERPRISES (Applicant) - WEST%FLANAGAN/SILVA (Owners), County File #2017-92: The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800 feet on .the north side of Johnson Road approximately 1,350 feet east of Camino Tassajara, in the Danville area. (A-8, A-40, A-2) (ZA: U-20, V-20, V-21) (CT 3551 .03) (Parcel #204-050-021 , #204-100-012, #204-160-001 , #206-200-003, #204-080-007, #204-110-003, #204-180-005). This item was continued by the Zoning Administrator on October 10, 1994 to allow the applicant the opportunity to meet with Dublin-San Ramon Service District to resolve the issues of providing reclaimed water and potable water to the project site. II. RECOMMENDATION Staff recommends this application be denied with prejudice for excessive delays by the applicant in processing the application. III. DISCUSSION Staff,the applicant and representatives of Dublin-San Ramon Service District (DSRSD) met on October 27, 1994 to discuss the issue of providing reclaimed water to the project site. The applicant initiated a planning study with DSRSD in 1992, but no further work has been completed to assess the viability of providing reclaimed water to the project site. DSRSD has preliminarily suggested, if all the appropriate studies are completed and infrastructure and planning cost are covered, they are not opposed to servicing the site. Staff and DSRSD indicated to the applicant, preliminary engineering studies would be required before completing the environmental review for the project. The meeting with DSRSD further focused the applicant's proposal to install a Reverse Osmosis Water Demineralization System to provide potable water. Staff requested the applicant meet with the County Health Services Department, Environmental Health Division, and the State Health Services Department to discuss the proposed system. To staff's knowledge, no meetings have occurred and the applicant has not provided any new information to staff on the issue. �nEt t �T New Golf Enterprises Y&XY&P_EhHB11Xvd3.81"x J Lafayette, CA 94549-3952 L—Vo cG --? (510)284-7100 NEWC FAX 284-7112 GOLF (�D ENTERPRISES January 09 , 1994 Debbie Chamberlain, Senior Project Planner Community Development Department, Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club vic Tassajara) ; Project Process Status Dear Ms . Chamberlain: 1. This letter informs you and staff about the status of project. 2 . At a meeting attended by yourself and representattives of the Dublin San Ramon Services District (DSRSD) on October 27, 1994, it was agreed that there were essentially 3 steps remaining prior to project approval, all of which deal with water issues: a. Resolving with the County and Health Services Departments how the potable water for clubhouse use would be accomplished. The likely solution would utilize reclaimed water as a source, turning it into potable water though either an injection/well, reverse osmosis or still type system. b. Conducting a "Routing" and Engineering Study under the auspices of DSRSD. Such a study would determine the appropriate route, size and probable cost of a pipeline from the DSRSD' s Pleasanton facility to the proposed Fox Creek/ Johnston Road site. c. Once the routing study is completed, an environmental review on the pipeline would be conducted under the leadership of the county. 3 . In preparation for the potable water conversion determination, para 2 .a. , above, New Golf Enterprises has obtained the services of an engineering firm which speL4alizes in this type of work and which is familiar with the general location. It has been forwarded the hydrogeologic and geotecnical studies conducted for this application in preparation for discussions with the state and county Health Services Departments . We expect that part of the process to be completed and resolved within another month. 4 . Concerning the routing study with/by DRSRD, we expect funding shortly to be able to start that process within 2 to 3 weeks. DSRSD has indi- cated a window of about 2 1/2 to 4 months to complete that study. The subsequent environmental review timing would be study results dependent . 5 . Therefore, request a continuation of our application in order to permit the completion of the process discussed in this letter. Sincerely , John L. B er �X1 t l 6 IT 1�L CONTRA COSTA COUNTY ZONING ADMINISTRATOR 9 JANUARY 1995 - 1:30 P.M. Item #3 on the agenda - Decision' only. LAND USE PERMIT - CONTINUED PUBLIC HEARING: NEW GOLF ENTERPRISES (Applicant) - WEST/FLANAGAN/SILVA (Owners) - #2017- 92 The applicant requests approval to establish a golf course and related facilities. The subject properties are approximately 616 acres fronting approximately 3,800-ft., on the north side of Johnston Road, approx., 1,350-ft., east of Camino Tassajara, in the Danville area. (A-80, A-40, A-2) (ZA:U-20) (CT-3551 .03) (Parcel #204-050-021, #204-100-012, #204-160-001, #206-200-003, #204-080-007, #204-110-003, #204-180-005) - (Continued from 10/10/94) (DC) - (RHD) (The following dialogue picks up with the Zoning Administrator talking after the applicant gives his rebuttal) MR. DRAKE: I have two concerns with this project. One is that the applicant apparently realized early on that in order to establish this project there would have to be major provision for extension of water to the site and is only now beginning to engage a potential water district about providing that water and I think these things ought to be identified early on in the process rather than after the application is filed with the County. My other concern is that the sheer scope of extending a water line eight (8) miles to the site, costing $2,000,000. with the sole purpose of serving this site is---I'm not sure that it's realistic given today's planning considerations in terms of annexations and decisions that would have to involve other properties and may raise a number of planning issues beyond the scope of this project. I'm also concerned that there hasn't, until the day of the hearing that we seem to get any response from the applicant from the previous identification on the necessary information that we need to pursue this thing and I don't want to trouble the neighbors further on this matter. That's not to say that ultimately down the line it may be possible to demonstrate the feasibility of establishing a golf course on this site and we would be willing to consider that; but, based on the existing circumstances for that area, I'm not prepared today to come to the conclusion that there is a reasonable possibility that the County.is likely to be able to approve this project. So, based on those matters, I am going to go along with the staff recommendation and deny the application. At the same time, I would ask staff to advise the applicant of his appeal rights if he chooses to appeal this decision to the next higher body. -1- MRS. CHAMBERLAIN: To clarify your decision, briefly, that is denial with prejudice? MR. DRAKE: Yes. Basically, what that means is that we would not accept an application within a year's time frame unless it addresses the issues that have been raised to date in terms of level of information. We would have to have a substantially changed application. It would have to address the water provision issues, the reclaimed water issues to the site---you would need to demonstrate to us that there is a feasible program from a planning, engineering and financial perspective to provide for reclaimed water from D.S.R.S.D., or some other water source to the site. In the absence of that within a one-year time frame, we would not accept an application, unless you file an appeal within ten days. MRS. CHAMBERLAIN: The appeal must be filed within a ten-day period which expires on January 19, 1995 at 5:00 P.M. The appeal must state the grounds for the appeal and .be accompanied by the appropriate fee and noticing envelopes. An appeal instruction hand-out is on the railing. This item, if appealed, would then be heard by the San Ramon Valley Regional Planning Commission at a date to be specified later and notification would be mailed to anyone who testified at the numerous hearings that have been held or is within 300-ft., of the subject property. MR. DRAKE: And, to anyone who submitted green sign-in slips. There was no further discussion on this item. _2_ C Community Contra Harvey E.of Commuommu ragdon Director of nity Development Development Costa Department County County Administration Building 651 Pine Street 4th Floor, North Wing Martinez, California 945530095 z Phone: 646-2031 January 30, 1995 a court John L. Baker New Golf Enterprises P.O. Box 381 Lafayette, CA 94549 Dear Mr. Baker: This letter acknowledges receipt of your letter of appeal dated January 19, 1995 for application #2017-92, which was denied by the Zoning Administrator, on January 9, 1995. Your appeal will be heard by the San Ramon Valley Regional Planning Commission Board of Appeals. This office will notify you, by letter, when the appeal has been scheduled for hearing before the San Ramon Valley Regional Planning Commission. You should be aware that you or your representative should be present at the hearing. Also, please note that in order to proceed promptly with the scheduling of this appeal, you should submit 9 full sized maps for the Board of Appeals, a list of names and addresses for all properties within 300 feet of your property along with stamped (NOT METERED), self-addressed envelopes to each individual property owner, but do not include a return address, no later than Monday, February 5, 1995. Please direct the maps, envelopes and list to: Community Development Department, Attention: Debbie Chamberlain, 651 Pine Street, North Wing - 4th Floor, Martinez, CA 94553-0095. If you.have any questions regarding this matter, please call Debbie Chamberlain at 646-2031. Sincerely yours, 01, Robert Drake Senior Planner RD/df L3:2017-92.apl cc: File/aa West/Flanagan Public Works Attn: Mitch Avalon New Golf Enterprises �v-"` "; 1 PO Box 381 CONTRA COSTA Lafayette, CA 94549 NEW CZ) FAX 284-7100 FAX 284 7112 95 JAN 19 PM 5: 08 GOLF CZ) ENTERPR I SEScK4 Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Appeal ICO Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club, in the vicinity of Tassajara) 1. This letter appeals the January 9, 1995 decision of the Zoning Administrator to deny referenced application with prejudice. 2 . The reasons for denial stated by the hearing officer: a. The scope of a project to pipe reclaimed water to the project site from a Dublin San Ramon Services District treatment plant, approx- imately 8 miles at a cost of about $2 , 000, 000 "seemed unrealistic. ,, b. Nobody at the hearing made statements for the project. c. Since staff had not received a letter from applicant advising staff of water route study and clubhouse potable water matters until the day of the hearing, staff had recommended denial by reason of the applicant taking too long to complete the requested work. 3 . The reason for appeal: (From the "Appeal Instructions" sheet made available by the Community Development Department, Item 3 . , under Land Use Permits, et al, "Specified findings of the planning division appealed from are not supported by the evidence before it. " ) a. The scope of the pipeline is realistic. The applicant notes that this reason given by the hearing officer is a new issue, with which. the county does not normally interest itself: economics of this project has not been a concern in the past. However, this is _what an 8 mile long pipeline, estimated to cost about $2, 000, 000, enables : 1. ) The construction of a course and clubhouse; the reclaimed water pipeline costs about one tenth of the total project. 2 . ) Once constructed, and on a per annum basis, the golf course facility will generate about 35 full time jobs with a payroll of slightly over $1, 000, 000 , it will add real estate taxes' of about $750, 000, sales taxes of over $250, 000 and improve surrounding property values, which would greatly improve real estate tax returns to the county over time. When it is mature, the club facility will generate in excess of a 20% return, which it must do to attract the investment capital necessary. Most of the jobs and material used in construction of the course and clubhouse will .come from within the county, adding even more jobs, income and taxes . 3 . ) It does this at no "cost" to the county. Because there is no housing associated with this project, there is no impact on 2 traffic, schools or other public services . The golf course. is able to stand on its own economically precisely because of where it is located: if it were in an area where sewer, potable and reclaimed water were already available, the land would be too expensive, requiring some housing as part of the project. The project is completely self- contained, requiring no outside source of potable water or sewer. 4 . ) Because the course is not limited by residential considerations, it is a "golfers course, " by design. This will make it one of the better golf facilities in the state, adding to the stature of the county and area. At baseline the project provides recreation for 400 families . Economics, mostly land costs, dictate that the facility must be private. Very few public courses are being built in California these days unless on publicly owned land. And few munici- palities are willing to risk their credit ratings to get one built. 5 . ) It is an environmentally sensitive project: due to the natural suitability of the site for a golf course, it requires sub- stantially less grading than what is typical in the West. It also does. not effect wetlands, fish or wildlife, or endangered species of any kind, nor is there drainage off of the project onto adjacent prop- erties . . Indeed, the use of Title 22 Tertiary reclaimed water for course irrigation will recharge the surrounding aquifer over time, improving the well capacities of adjacent properties. Essentially, the project continues to do what the land is currently doing: grow grass. b. No one appeared at the hearing to speak for the project. 1. ) Staff indicated to applicant that the hearing was basically for the purpose of obtaining- a continuance in order to complete the reclaimed water routing study. Therefore, the applicant 1 instructed the many interested neighbors and other parties to save time (their' s and staff) by testifying at a future hearing, when the water studies were complete. 2 . ) The relatively late notice to the applicant by staff of the actual meeting date: notice of the meeting (a copy of - the staff report) was mailed on Wednesday, January 4, and received on Friday, January 6, the workday before the Monday hearing date, January 9 , 1995 . i C. Staff had not received a letter or other communication from applicant advising staff on progress of water routing study and club- house potable water matters by the time she generated her staff report for the hearing schedule; therefore, staff had recommended denial by reason of the applicant not proceeding with the requested work: 1. ) At the meeting with county staff and DSRSD on October 27, 1994, a "process" was agreed to for "ensuring the project has a verifiable source of reclaimed water. " This "process" included approximate times for each "step. " Staff clearly understood that these steps would most likely take more than the 2 working months remaining to complete before either January hearing date. When asked by applicant at the conclusion of. that meeting whether she required, or would like, a letter about the "process, " she indicated to applicant that would not be necessary - to proceed with the work and indicate how it was progressing for the January continuation hearing, whenever that was, - would suffice . It should be noted that once in receipt of our progress letter on January 9 , staff recommended continuance. . „ 3 2 . ) The late receipt of notification of the meeting date (Friday before a Monday meeting) and staff busy schedule prevented a status letter from being relayed to staff prior to the meeting. Staff was told by applicant in a phone conversation on Friday, 1/6/95, that the work was proceeding: an engineering firm had been hired to study and negotiate the conversion of reclaimed to potable water issue with state and county health services departments; funding of the routing study was to be forthcoming in January.. Staff was communicated with prior to the hearing, but not before she wrote her staff report recommending denial due lack of progress. 3 . ) The applicant was never notified, technically, of the date of the hearing until the receipt of the staff report, on Friday, 1/6/95.. At the Zoning Administrator hearing on October 10, staff had recommended a continuation of one year to resolve the reclaimed water routing and potable water conversion matters. The applicant requested continuation, instead, to a date certain about three months hence: a joint meeting between county staff and DSRSD. personnel would indicate a much more specific process which should take three to six months . The hearing officer granted a three month continuation to a date certain in January. The date, itself was not available in the meeting room (nobody had a calendar) , but the applicant was told by the hearing officer and staff that it would be one of the two Zoning Administrator meeting dates in January (second or fourth Monday) ; that he would be informed of which date in a timely fashion. That did not really happen. 4. On the subject of processing delays, this project and application have not been particularly well served by the process. Initial inquiries with the county and the appropriate suitability studies were commenced in the early fall of 1991 and the application was made in March 1992 . Issues which were not deemed significant by the county by the fall of 1992 were then brought forward by the planning division one at time, each requiring another study or further action by the county. Some of these issues: a determination of status under the Williamson Act (project "tolled" for months) , amendment to the zoning code to permit recreational use of some types of agricultural lands (it was left out of the previous revision of the County General Plan, and determined to be an oversight - took months to staff), reassignment of staff due to other large project staffing requirements (project waited months for new staff) , Clubhouse design (a time consuming process) , and now reclaimed water routing. Over two years, now, have been consumed by these additional studies or events, not only at major expense to the applicant for the work required, but also for ongoing land option pay- ments and processing administration costs to keep the project alive. S. Regarding the specific issue/study around_ which this project is currently denied, the reclaimed water routing study could easily be determined by the Zoning Administrator to be a condition of approval. a. As a practical matter of great economic impact to the project, construction of a course could not commence until the availability of water was assured. As soon as the grading is complete (about 6 months into a typical construction cycle) , the irrigation source must be in place to start turf growth and minimize dust and soil erosion. Early turf development requires higher rates of irrigation. Therefore, the project is absolutely reclaimed water dependent from the start - the underlying aquifer is inadequate to support the adjacent homes and ranches in the area, much less a golf course . • -4 ,4 , b. One of the reasons mentioned by staff for the pre-approval requirement for the reclaimed water routing study was a recent court case in which it was determined that counties must have verifiable sources of potable water for planned unit developments. Underlying that decision was a judgement that sources of potable water may be scarce in California and that there might be a need to consciously determine specific priorities for potentially competing potable water uses. In this specific application, the issue is not potable water, it is reclaimed water. It is a resource in abundant supply in Northern California. Most citizens think it should be utilized more for irrigation, instead of pumping it into the Bay or Ocean at ratepayer and taxpayer expense. What this project is requesting is to utilize that resource in a most positive way at private expense. Also it would use the appropriate utility which is already in the reclaimed water delivery business over existing utility rights. of way and easements . 6. The baseline question which this application asks: is this project bad for the. county? On every level considered, a golf course at this location is most positive - for the county, its coffers, the welfare of its citizens and the general and specific environment: a. The facility is needed: Contra Costa County is included in an area which is eighth off the bottom among some 300 U.S. geographical population centers. Studies by the National Golf Foundation and others indicate that we live in one of theworst areas in the country in terms of courses/golf holes available per unit of the population and known golfers in the area. Due to lack of facilities, the county is exporting its golfers and their recreation money. b. This project will be completed at minimal infrastructure costs , to the public: new schools and roads . simply are not needed because it does not generate additional residential properties to foot the bill . c. It has the added benefit of assisting with the recharge of the aquifer of surrounding homes and ranches: their well water situation will be greatly improved shortly after irrigation is commenced. This project has no toxic impact on the surrounding properties. There is no runoff of pesticides or fungicides to adjacent properties, the level and- types of chemical used are greatly restricted by county, state and federal regulation, and none would make it into the ground water for the depth of adjacent wells/aquifer and soil types 'in the project area. d. Indeed, most adjacent residents who are familiar with the project think it will be good for them. Most think it will help retain many of their views and is very compatible with the general spacious layout of properties in the area. They also tend to like the provision of local recreation and the probable improvement in property values. 7 . Therefore, the applicant requests that this golf course application be approved, as is, with a condition of approval specifying utilization of reclaimed water, or at least continued to another Zoning Admini- strator Hearing to a time when the water studies would be complete. i Mn er SAM 0 DUBLIN 4 7' 7051 Dublin Boulevard SAN RAMON • Dublin,Califomia 94568 SERVICES C�Ap, G FAX:510 829 1180 DISTRICT `?�,ES DI5�4~ 510 828 0515 May 21, 1992 Fox Creek Country Club, Inc. c/o New Golf Enterprises Attn: Mr. John Baker 3466 Mt. Diablo Blvd., C-205 Lafayette, CA 94549 Dear Mr. Baker: Enclosed is the letter agreement between Fox Creek Country Club and the Dublin San Ramon Services District regarding utility planning services for recycled water. A certified copy of Resolution 23-92, adopted by the Board of Directors on May 19, 1992 is enclosed for your records. . Please sign and return a copy of this letter agreement to my.attention at your earliest convenience. Thank you. Sincerely, NANCY GAMBLE District Secretary Enclosures cc: Bob Beebe Bert Michalczyk n,.Inmlu, DES:df- t 5/15/92 (008/31-J. ' 5/18/92R R E S O L- U ,T I O N N O. 23-92 RESOLUTION APPROVING AND . AUTHORIZING EXECUTION OF LETTER AGREEMENT RELATING TO RECYCLED WATER USE PLANNING SERVICES (FOX CREEK COUNTRY CLUB) BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE DUBLIN SAN RAMON SERVICES DISTRICT, A PUBLIC AGENCY IN THE COUNTIES OF ALAMEDA AND CONTRA COSTA, CALIFORNIA, AS FOLLOWS: That certain letter agreement by and between the Dublin San Ramon. Services District, a public agency in the Counties of Alameda and Contra Costa, California, and Fox Creek Country Club, Inc. , pursuant to which this District shall perform certain recycled water use planning services relating to a proposed project of Fox Creek Country. Club, Inc. , in the form of Exhibit "A" hereof, attached hereto, and by this reference incorporated herein, is hereby approved, and the General Manager is hereby authorized and directed to execute said letter agreement for and on behalf of the District. Adopted by the Board of Directors of the Dublin San. Ramon Services District at a regular meeting held on the 19th of May, 1992 , and passed by the following vote Ayes - 5 Directors Donald M. Schinnerer, G.T. (Tom) McCormick, Noes Q Georgean M. Vonheed r, Joseph Covello, Jeffrey G. Hansen - Absent - Q / Jeffry/G. Hansen,] President Attest: rERTIFIED'AS A TRUE AND CORRECT COPY OF THE ORIGINAL ON FILE IN THE OFFICE OF. Nancy Gamble , Secretary DUBLIN SAN RAMON SERv�ES DISTRICT Secretary I IA y 2 1 1992 v ^ . 1 SAN_,t,� DUBLIN 4 x 7051 Dublin Boulevard .SAN RAMON N Dublin,California 94568 SERVICESG FAX: 510 829 1180 DISTRICT �CE 15�¢~ 510 828 0515 SD May 21, 1992 Fox Creek Country Club, Inc. c/o New Golf Enterprises Attn: Mr. John Baker 3466 Mt. Diablo Blvd., C-205 Lafayette, CA 94549 Subject: Fox Creek Country Club Recycled Water Dear Mr. Baker: This letter will serve as the agreement between the Dublin San Ramon Services District ("DSRSD") and Fox Creek Country Club for utility planning services to be provided by DSRSD relating to the provision of recycled water by DSRSD to the Fox Creek Country Club. The project is generally described in the letters of February 12, 1992 and March 24, 1992 from New Golf Enterprises (attached). This agreement is entered into pursuant to Resolution No. 23-92, adopted by DSRSD's Board of Directors on May 19, 1992. Fox Creek has requested that DSRSD conduct, or cause to be conducted, activities and studies to determine the feasibility and requirements for providing recycled water services and facilities to the project. Such studies and activities will generally include, but are not limited to, attending meetings and conferring with engineers and other experts, representatives of Contra Costa and Alameda Counties and other governmental agencies which do or may have approval.authority over the project, and other persons or agencies serving as sources of information or providing other services regarding the proposed project; contracting or subcontracting the performance of professional services (including, but not limited to, engineering consulting services) necessary or appropriate to ascertain the above-mentioned services; collecting information, data, and conducting any other planning activities as may be necessary or appropriate in pursuance of the proposed project. Fox Creek shall furnish DSRSD current factual information regarding the project necessary for utilities planning purposes, including without limitation recycled water demands, project location and other information as requested. At the time that DSRSD requests the remittance of any but the first installment amounts described below, a scope of work describing the anticipated activities to be funded from the installment shall be agreed to by DSRSD and Fox Creek. In accordance with the foregoing, upon signing a copy of this letter in the place provided hereinbelow, New Golf Enterprises shall deposit with DSRSD the sum of $1,000 as the first n, n„ne:: Mr. Baker May 21, 1992 Page 2 installment. These funds shall be credited to the project and retained by DSRSD to be used for services rendered under future scopes of work or for reimbursement of costs to be incurred by DSRSD, including costs and expenses of staff time, and contracted or subcontracted work. As scopes of work are agreed to DSRSD shall bill Fox Creek Country Club for additional deposits, likewise in installments as required by timing of work performed for said purposes; provided, further, that the sum on deposit with DSRSD at any given time shall not exceed an amount sufficient to cover all such scopes of work. - All funds, if any, remaining on deposit upon completion of furnishing services by or for DSRSD hereunder shall be returned to Fox Creek. Kindly acknowledge your agreement with the foregoing by signing the copy of this letter in the space provided below and returning the signed copy. For purposes of administering this agreement, kindly contact Mr. Bert Michalczyk, Technical Services Manager, DSRSD. Meanwhile if you have any questions, please do not hesitate to call. Very truly yours, ROBERT D. BEEBE General Manager ACCEPTANCE The undersigned, for and on behalf of fer�•Q�c�m��aY hereby accepts and a s to the above terms and conditions. DATED: BY: • New Golf Enterprises 3466 Mt. Diablo Blvd.. C-205 Lafayette. CA 94549-3952 - J NEW (510) 284-7100 r FAX 284-7112 C GOLF _ __ "_ . •._ .; :_. .. (�D ENTERPRISES May 26, 1993 Catherine Kutsuris Senior Project Planner Community Development Department Contra Costa County 651 Pine Street, 4th Floor, North Wing Martinez, CA 94553-0095 Re: Use Permit Application, County File No. 2017-92 (Golf Course: Fox Creek Country Club vic Tassajara). Dear Ms . Kutsuris: 1. Attached please find the additional information requested in our February meeting: Map of the Silva ranch with neighbor names and mailing labels . - Map of proposed golf course showing golf boundaries. 2 . I've also included a copy of the letter from our attorney to Harvey Bragdon on the subject Golf Courses in Agricultural Zones (also Williamson Act considerations) , for your information. It is our understanding that the Assistant County Counsel is in the process of reviewing it. You may recall that the approval process is awaiting a decision on the issues therein discussed. 3 . Also, for your information it is our understanding that there are no renters living within 300 feet of the Silva, West, or Flanagan ranches (all properties subject to our request) . Sincerely, ohn er President