HomeMy WebLinkAboutMINUTES - 05231995 - 1.2 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: May 23, 1995
SUBJECT: Approve Plans and Specifications and Advertise for bids for the San Pablo Dam Road
Slide Repair at Station 252+00 Project in the EI Sobrante Area.
Project No. 0672-6R6523-93, CDD-CP # 94-13.
Specific Request(s) or Recommendation(s) & Background & Justification
I. RECOMMENDED ACTION:
APPROVE the Plans and Specifications for the Project and
ADVERTISE for bids to be received on Thursday, June 22, 1995, at 2:00 p.m.
DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with Section
20392 of the Public Contract Code at least 21 days prior to the date bids are to be received.
II. FINANCIAL IMPACT:
The estimated contract cost of the project is $249,000, funded by Federal Aid Storm Damage
Repair Funds (65.8%) and County Road Funds (34.2%).
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The project is needed to repair slide damage in the road embankment to prevent further
deterioration and endangerment of the roadway.
The Public Works Director has filed with the Board of Supervisors the Plans and Specifications
for the project.
Continued on Attachment: X SIGNATURE:
_RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON `Mayr 2+3j 19 9 APPROVED AS RECOMMENDED_OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
DHE:SC.jlg
c\BO:bo23b.t5 f hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
Orig.Div: Public Works(Design Division) Board of Supervisors on the date shown.
Contact: Sam Choi(313-2352) _M � a� 19�
cc: County Administrator ATTESTED: �.L1.}�
Attn: E.Kuevor PMIL BATCH R.Clark of the Board
Auditor-Controller of"fHltoraafldCojigAd dnistraW
PW Accounting �-
Construction ''
Community Development Oeputi/
`Approve Plans and Specifications and Advertise for bids for the San Pablo Dam Road Slide kipair at
Station 252+00 Project
May 23, 1995
Page 2
The general prevailing rates of wages, which shall be the minimum rates paid on this project,
have been filed with the Clerk of the Board and copies will be made available to any interested
party upon request.
The Board reviewed and approved the project on April 12, 1994 and determined the project to be
exempt from the California Environmental Quality Act as a Class 1 c Categorical Exemption. A
Notice of Exemption was filed with the County Clerk on April 20, 1994.
IV. CONSEQUENCES OF NEGATIVE ACTION:
If the project is not approved for advertising, it will not be constructed.