HomeMy WebLinkAboutMINUTES - 04041995 - 1.58 :r - Contra
TO: REDEVELOPMENT AGENCY _ , Costa
FROM: Phil Batchelor -T `"'u' "y
c JAS J
Executive Director
DATE: April 4, 1995
SUBJECT: Oakley Redevelopment Area-Fund Installation of Landscaping on State Route 4
SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMEND TA IONS
APPROVE and AUTHORIZE the Deputy Director - Redevelopment to sign a contract between the
Redevelopment Agency and Contra Costa County for funding of the installation of landscaping, median
landscaping, landscape irrigation facilities and sidewalks on State Route 4 between Empire Avenue and
Vintage Avenue in the Oakley area.
APPROVE and AUTHORIZE the Director of Public Works to sign a contract between the
Redevelopment Agency and Contra Costa County for funding of the installation of landscaping, median
landscaping, landscape irrigation facilities and sidewalks on State Route 4 between Empire Avenue and
Vintage Avenue in the Oakley area.
FISCAL IMPACT
No General Fund monies are involved. The Agency's adopted budget for FY 94-95 for the Oakley
Redevelopment Project Area contemplates that $189,790 will be allocated towards the project.
CONTINUED ON ATTACHMENT: _YES SIGNATURE: IEN(NC
RECOMMENDATION OF EXECUTIVE DIRECTOR COMM DATION OF EY
COMMITTEE c --
APPROVE OTHER
SIGNATURE(S):
ACTION OF
AGENCY ON Apr i 1 4 , 19 9 5 APPROVED AS RECOMMENDED v--`OTHER
VOTE OF COMMISSIONERS
I HEREBY CERTIFY THAT THIS IS A
x UNANIMOUS (ABSENT ) TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE REDEVELOPMENT
AGENCY ON THE DATE SHOWN.
Contact: Jim Kennedy ATTESTED April 4 , 1995
County Counsel PHIL BATCHELOR, AGENCY SECRETARY
646-4076
County Administrator
Public Works
BY L& DEPUTY
2
BACKGROUND/REASONS FOR RECOMMENDATIONS
The Oakley Municipal Advisory Council(OMAQ has recommended the allocation of redevelopment
funds in order to enhance the appearance of State Route 4 between Empire Avenue and Vintage
Avenue in the Oakley area. This project consists of the installation of sidewalk, landscaping behind
the sidewalk, median landscaping and landscape irrigation facilities on State Route 4. Introducing
this new landscaping will not only beautify State Route 4, but confirm one's arrival in Oakley. This
and other infrastructure improvements will ensure that Oakley continues to experience commercial
and residential development. The Agency intends to review the engineering estimate f rom Public
Works for the project. Should bid estimates be higher than the Agency's allocation to the project, the
Agency and Public Works will review the scope of the project to address any potential gap.
a:\ed2\landscap.oak