HomeMy WebLinkAboutMINUTES - 03071995 - 1.5 TO: BOARD OF SUPERVISORS, as the Governing Body of the Contra Costa County Flood
Control and Water Conservation District
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: MARCH 7, 1995
SUBJECT: SAN PABLO CREEK PROJECT, CONTRACT 3A - N. RICHMOND AREA
Project No.: 7567-6D8606 Task: ACQ Account: 3540
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
I. Recommended Action:
1. APPROVE Amendment to Right of Way Agreement with Southern Pacific Transportation
Company.
2. AUTHORIZE the Chief Engineer to sign said Amendment on behalf of the District.
3. AUTHORIZE the Auditor-Controller to issue a check for $1,000.00 payable to: Southern
Pacific Transportation Company, One MarketPlaz Suite 912, San Francisco, CA.,
94105, to be forwarded to the Real Property Divis* or delivery.
Continued on Attachment: X SIGNATURE: AJ/
RECOMMENDATION OF COUNTY ADMINISTRATOR
_RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON `M 7_) 1 R9S APPROVED AS RECOMMENDED OTHER_
VOTE OF SUPERVISORS
�/ UNANIMOUS (ABSENT = )
AYES: NOES:
ABSENT: ABSTAIN:
RF:glo
g:\realprop\temp\BOc7.t3
Orig. Div: Public Works(R/P)
Contact: Roger Frost(313-2223)
cc: County Administrator I hereby certify that this Is a true and correct copy of
Auditor-Controller(via R/P) an action taken and entered on the minutes of the
P.W.Accounting Board of Supervisors on the date shown.
ATTESTED: -::W,8,pd_'_�1 9%C;'
PHIL BATCHELOR,Cle of the Board
Of Supervisors and County Administrator
BY 0. 0. ,Deputy
II. Financial Impact:
$1,000 (70% State Department of Water Resources, 30% Drainage Area 73)
III. Reasons for Recommendations and Background:
Payment is for a six months extension of a Temporary Construction Permit required for the San
Pablo Creek Project.
IV. Consequences of Negative Action:
There will be insufficient property rights to complete the project.