HomeMy WebLinkAboutMINUTES - 03281995 - 1.3 TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: March 28, 1995 SUBJECT: Approval of Contract Change Order #6 for the Ygnacio Valley Rd. Overlay Project, Project No. 0662-6R4221-92, Concord area. Specific Requests or Recommendation(s)&Background&Justification I. Recommended Action: Approve Contract Change Order No. 6 in the approximate amount of$1,200.00 and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, Oliver de Silva, Inc., for work performed. II. Financial Impact: The project contingency funds are sufficient to cover the change order cost. The project is funded by Measure "C" Funds (95%) and the City of Concord (5%). III. Reasons for Recommendations and Background: The cumulative total of Contract Change Orders Nos. 1 through 6 exceeds $25,000.00, requiring Board approval. IV. Consequences of Negative Action: Without approval the contractor will not receive payment for the work required. Continued on attachment: _yes SIGNATURE: UJ RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON: 2 $ APPROVED AS RECOMMENDED OTHER VOT F SUPERVISORS UNANIMOUS (ABSENT S: NOES: ABSENT: ABSTAIN: Contact: Joseph P. Murphy, (510) 313-2321 Orig. Div.: PW(Constr) cc: County Administrator Auditor-Controller Public Works - Design,V. Germany - Accounting, R. Gilchrist - R. Bruno Contractor DG\tt g:\const\BO\YVC-28.t3 1 hereby certify that this is a true and correct copy of an action taken and entered on the minutes of the Board of Supervis rsAA mon the ppdate sho R wn. ATTESTED: �/i2 ® 1QQs PHIL BATCHELOR,Clerk i f the Board of Supervisors and County Administrator By Deputv