HomeMy WebLinkAboutMINUTES - 06211994 - 1.11 TO: BOARD OF SUPERVISORS,AS THE GOVERNING BOARD OF CONTRA COSTA COUNTY
AND CONTRA COSTA COUNTY FLOOD CONTROL AND WATER CONSERVATION
DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: JUNE 21, 1994
SUBJECT: APPROVE AND AUTHORIZE THE CHAIR TO EXECUTE A REIMBURSEMENT AGREEMENT WITH EAST
BAY MUNICIPAL. UTILITY DISTRICT FOR UTILITY RELOCATIONS, SAN RAMON CREEK BYPASS
PROJECT, WALNUT CREEK AREA. PROJECT NO.: 7520-68$637
SPECIFIC REQUEST($)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
1. Recommended Action:
APPROVE and AUTHORIZE the Chair to execute a reimbursement agreement with East Bay
Municipal Utility District(EBM UD)for the relocation of several water mains for the San Ramon Creek
Bypass Project, Walnut Creek area.
11. Financial Impact
Total relocation cost is equal to$712,971.64,which is 100% reimbursable. Funding sources are the
Central Contra Costa Sanitary District(28%)and California Department of Water Resources(72%).
III. Reasons for Recommendations and Backaround:
By agreement with the United States Corps of Engineers (Corps), the Flood Control District was
required to relocate utility facilities necessary for construction of the San Ramon Creek Bypass
Project. The required relocations included several facilities owned by EBMUD: approximately 2300
feet of 24-inch diameter water main along the former Southern Pacific Railroad right-of-way adjacent
to the bypass channel between Newell Avenue and Murwood Drive,and several smaller water mains
at Newell Avenue, Murwood Drive, and Mount Diablo Boulevard.
Continued on Attachment: x SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JUN 2 11994 APPROVED AS RECOMMENDED V OTHER
1 hereby certify Viet this b a true end correct 0 of
an action taken end entered on the wdnuw of the
Board of SumvisorsS
t48
ATTESM Iiild
dupe visor a=.Do*
°fthe�Nor
VOT F SUPERVISORS B, /; rat,
UNANIMOUS(ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
PHIJJ:pe
g:ktdcti\fcbolEBMUD 2116
Orig. Div: Public Works (FCE)
Contact: P. Harrington, 313-2271
cc: W. Quever, PW Accounting
County Administrator
Auditor-Controller
REIMBURSEMENT AGREEMENT WITH EAST BAY MUNICIPAL UTILITY DISTRICT FOR UTILITY RELOCATIONS,
SAN RAMON CREEK BYPASS PROJECT
June 21. 1994 �
Page Two
Ill. Reasons for Recommendations and Background: (Continued)
In conjunction with the flood control project, the Corps installed a sewer trunk line for CCCSD,
adjacent to the bypass channel. This capital sewer project required more of the 24-inch water line
to be relocated than would have been required for the channel alone. By a Joint Exercise of Powers
Agreement between CCCSD and the District, CCCSD agreed to reimburse the District for 37% of
the relocation cost for the 24-inch main—the percentage of the relocation attributable to their sewer
trunk line.
IV. Consequences of Negative Action:
The water lines have already been relocated. If the agreement is not approved,we cannot fulfill our
obligation to reimburse EBMUD for the work.
�a�y
RESOLUTION NO. 32857-94
AUTHORIZING EXECUTION OF UTILITIES AGREEMENTS BY THE DIRECTOR OF
ENGINEERING AND CONSTRUCTION
Introduced by Director coleman ; Seconded by Director Gioia
WHEREAS pursuant to Resolution No. 19140, the Board had previously authorized the Chief Engineer
of the District to execute Utilities Agreements on behalf of the District for the relocation of District
facilities necessitated by state highway construction; and
WHEREAS on June 23, 1992 pursuant to Resolution No. 32637, the Board eliminated the position of
Chief Engineer and retitled the position of Assistant Chief Engineer of Design and Construction to
Director of Engineering and Construction; and
WHEREAS the Director of Engineering and Construction has assumed the duties and responsibilities
previously held by the Chief Engineer;
NOW, THEREFORE, BE IT RESOLVED that the Director of Engineering and Construction, as the
successor to the position of Chief Engineer, is hereby authorized and directed for and on behalf of the
District to execute Utilities Agreements with the State of California, the Counties and Cities of the State
of California,and other Districts or Special Districts and governmental agencies in the State of California,
in a form approved by the General Counsel for the relocation of District facilities necessitated by
construction, development, or improvement projects of such agencies;.
BE IT FURTHER RESOLVED that any other resolution which is in conflict with the provisions herein
is hereby revoked.
ADOPTED this 24th day of May, 1994 by the following vote:
AYES: Directors Coleman, Gioia, McKenney, Nadel and President Flashman
NOES: None
ABSENT: Directors Cohen and Simmons
ABSTAIN: None
President
ATTEST:
Interim Secretary
APPROVED AS TO FORM AND PROCEDURE:
General Counsel
AGREEMENT RELATING TO THE RELOCATION
OF 8-INCH, 12-INCH, 16-INCH AND 24-INCH
WATER PIPELINES
ADJACENT TO THE SAN RAMON CREEK BYPASS
THIS AGREEMENT, entered into this day of 1994, by and
between the East Bay Municipal Utility District, a public corporation of the State of California,
hereinafter called "the Utility District," and the Contra Costa County Flood Control and Water
Conservation District, a political subdivision of the State of California, hereinafter called "the
Flood Control District."
WITNESSETH
WHEREAS,the Flood Control District,in conjunction with the United States Corps of Engineers,
hereinafter called "Corps," intends to construct a flood control channel within and aligned
longitudinally along a portion of the abandoned Southern Pacific Railroad right of way in the
location shown on the map attached hereto as Exhibit "A"; and,
WHEREAS, the Utility District presently maintains an 8-inch underground water pipeline at
Murwood Drive, a 12-inch underground water pipeline in Mount Diablo Boulevard, a 16-inch
underground water pipeline in Newell Avenue, and a 24-inch underground water pipeline which
intrudes upon the alignment of the Flood Control District's intended construction from Corps'
Station 633 to Corps' Station 656; and,
WHEREAS,said existing Utility District facilities in said area are in conflict with the intended
construction, reconstruction, maintenance or use of the proposed flood control channel of the
Flood Control District; and,
NOW, THEREFORE, the Utility District and the Flood Control District hereby mutually agree
as follows:
1. The location of said existing Utility District facilities presently in conflict with the
intended construction shall be changed to accommodate the Flood Control District's flood
control channel project as that project has been defined and presented to the Utility
District as of the date of the execution of this Agreement.
2. The Flood Control District shall request the Utility District to provide for the relocation
of the water pipelines and their appurtenances. The Flood Control District shall furnish
a complete set of reproducible "as-built" plans to the Utility District a reasonable time
after the completion of the Corps' project.
3. The Utility District shall have sole responsibility for construction, and primary
responsibility for inspection and materials testing, of the relocation work, except as noted
on the plans. The Utility District, and its representatives, shall obtain verbal approval from
the Flood Control District prior to entering the channel construction right of way. The
Utility District and its representatives shall in no way direct the Corps' contractor's
operations. Any communication concerning the relocation work between the Utility
District and the Corps' contractor shall be conducted through the Flood Control District.
It is the Flood Control District's responsibility to keep the Utility District informed of the
Corps' contractor's activities that may affect the operation and relocation of water
facilities. The Flood Control District shall represent the Utility District's interests to the
Corps and the Corps' contractor(s) to the extent that such representation is needed. In the
event of deficiencies in the relocation work, the Flood Control District shall not be
responsible for discovering or correcting such deficiencies. The Utility District
acknowledges that entry into the easement area during construction comes with it a certain
risk and agrees to release the Flood Control District, its boards, officers, agents and
employees from any liability for death of,or injury to,the Utility District's representatives
while present in the easement area during construction, except for liability resulting from
the sole negligence or willful misconduct of the Flood Control District.
4. The Flood Control District shall have the Corps include in its contract documents
provisions requiring the successful bidder to name the Utility District as an additional
named insured on any required insurance certificates with the same conditions as must be
provided for the Flood Control District for any work related to these relocations.
5. The Flood Control District shall have the Corps include in its contract documents
provisions requiring cooperation with the Utility District's forces during the construction
of the relocations.
6. Nothing in this Agreement is intended to affect the legal liability of either party to third
parties for the obligations imposed by this Agreement by imposing any standard of care
respecting work performed hereunder different from the standard of care imposed by law.
7. All costs associated with the relocation of said existing Utility District water facilities
shall be borne by the Flood Control District, including, but not limited to, engineering,
construction, construction management, and right of way acquisitions using the Utility
District's standard overhead rates where applicable. The Utility District shall supply a total
cost estimate to the Flood Control District within 30 days of the signing of this
Agreement which estimate shall be subject to the Flood Control District's reasonable
approval. The estimated cost shall not be exceeded by more than 10 percent without the
Flood Control District's prior,written approval. The Flood Control District shall reimburse
the Utility District for the relocation costs within 90 calendar days after receipt of an
itemized bill from the Utility District.
8. The Flood Control District shall make adequate provision of the protection of Utility
District facilities in any contracted work required under this Agreement.
The Flood Control District shall defend, hold harmless and indemnify the Utility District
from claims, costs and liabilities arising from or connected with work performed by the
Flood Control District under this Agreement, except for claims, costs or liabilities arising
from the sole negligence or willful misconduct of the Utility District.
The Utility District shall defend, hold harmless and indemnify the Flood Control District
from claims, costs and liabilities arising from or connected with work performed by the
Utility District under this Agreement, except for claims, costs or liabilities arising from
the sole negligence or willful misconduct of the Flood Control District.
9. The Flood Control District shall notify the Utility District's Operations Department of the
start of any construction operations relative to this Agreement 20 working days in advance
of the commencement of such operations, and shall advise said Utility District Department
of any rescheduling of such operations. Reciprocally, the Utility District shall advise the
Flood Control District of its need to perform construction or maintenance operations
within the project limits 20 working days in advance of the commencement of such
operations.
2
10. Acceptance by the Flood Control District of the relocation work shall also constitute
acceptance by the Utility District, provided that both the Flood Control District and the
Utility District shall make a final inspection of the relocation work prior to acceptance by
the Flood Control District. Upon acceptance by the Flood Control District of the
relocation word the Utility District shall assume complete responsibility for maintenance
of the relocated facilities.
11. This Agreement shall inure to the benefit of and be binding upon the successors and
assigns of both parries.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed in
duplicate by their respective officials thereunto duly authorized.
CONTRA COSTA COUNTY FLOOD EAST BAY MUNICIPAL UTILITY
CONTR AND WATER DISTRICT
CONSERV ON ISTRICT
�-
By: By:
Ch rperson, Board o Supervisors Director of Engineering and Construction
ATTEST: FORM APPROVED:
Phil Batchelor, Clerk of the Board of
Supervisors and County Administrator
By: a&t'4.0 By:
Deputy Clerk for General Counsel's Office
RECOMMENDED FOR APPROVAL:
J. Michael Walford, Chief Engineer
B .
FORM APP OVED:
Victor J. Westman, County Counsel
By: J 4 )
Deputy
JJ:pe
g:Uldctllw ork1EBMUD.Agm
May 31.1994
3
♦
sit,
r�
rt
♦Za
in
mom
} t r
w 1
1
� r
a
N
t
V
t
t
h <
i RR/w s
cri
Lli :e
s
It `
w
r—
w
Tw
A t�vRc\J
• Rt. l
, R
0
R J