HomeMy WebLinkAboutMINUTES - 04191994 - 1.5 (2) TO: BOARD OF SUPERVISORS, as the Governing Body of the Contra Costa County Flood
Control and Water Conservation District
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: APRIL 12, 1994
SUBJECT: SAN PABLO CREEK - RICHMOND AREA
Project No.: 7567-6138606 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
A. APPROVE Amendments to Right of Way Contracts and Agreement as listed below:
GRANTOR DOCUMENT DATE PAYEE AMOUNT
Yolanda Perry Amendment 4/12/94 Yolanda Perry $ 250.00
Charles Perry to Right of Way Charles Perry
Carmen Valdivia Contract Carmen Valdivia
Mary K. Curran Amendment 4/12/94 Mary K. Curran $6,000.00
Katherine Marie Curran to Right of Way Katherine Marie Curran
Contract 840 Parr Blvd.
Richmond, CA 94801
B. AUTHORIZE Chief Engineer to execute said Amendments to Right of Way Contracts on
behalf of the District.
C. APPROVE payment as listed above for said property rights and AUTHORIZE the Auditor-
Controller to issue checks in said amounts payable to the listed payees, to be forwarded
to the Real Property Division for delivery.
Continued on Attachment: SIGNATURE: `,�� �!
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON (,i'p" /y� /5 sy APPROVED AS RECOMMENDED OTHER _
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hpy Cc"""that this is a trueand coneeteopyof
an action taken and entered on the minutes of the
GK:glo Board of Supervi on t date shown.
c:BO1412.t4 ATTESTED:_.�-9. /9 y51
PHIL BATCHELOR,Clerk of the Board
Orig. Div: Public Works (R/P) of Supervisors and County Administrator
Contact: Gus Kramer (313-2225)
cc: County Administrator 81r_._..b _,Deputy
Auditor-Controller (via R/P)
P. W. Accounting
II.' Financial Impact: f
Payment totalling $6,250.00 from State Department of Water Resources (70%) and Drainage
Area 73 (30%) funds.
111. Reasons for Recommendations:
These property rights are required for the San Pablo Creek project in accordance with approved
plans and specifications.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow construction in accordance with the
approved plans and specifications.