HomeMy WebLinkAboutMINUTES - 02081994 - 1.8 TO: BOARD OF SUPERVISORS FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR DATE: February 8, 1994 SUBJECT: Approval of Contract Change Order No. 4 for the Oakley Road Improvement project, Project No. 0662-6R4235-92, Oakley area. SpecE Requests ors grow &JLISWWAdion I. Recommended Action: APPROVE Contract Change Order No. 4 in the approximate amount of $6,000.00 and AUTHORIZE the Public Works Director to execute it in order to compensate the contractor, Vintage Grading and Paving, Inc. for work performed. II. Financial Impact: The project contingency funds are sufficient to cover this change order cost. The project is funded by Developer Contribution (12%) Deferred Improvement Agreement (7%), Oakley/North Brentwood Area of Benefit (55%), State Transportation Partnership Program (15%), and Diablo Water District (11%). III. Reasons for Recommendations and Background: The cumulative total of contract change orders Nos. 1 through 4 exceeds $25,000.00, requiring Board approval. IV. Consequences of Negative Action: Without approval the contractor will not receive payment for work required. Continued on attachment: _yes SIGNATURE: FiEMMMENDATION OF COUNTY ADMINI TRA RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON: FEB 8 - 1994 APPROVED AS RECOMMENDED b/ OTHER VOT"F SUPERVISORS // UNANIMOUS (ABSENT — YES: NOES: ABSENT: ABSTAIN: Contact: B.J. Kerekes, (510) 313-2321 Orig. Div.: PW(Constr) cc: County Administrator i hereby cartK,thee this is®tw and oorreat ooay-4 Auditor-Controller an action taken and entered on the vmnuteo of tfq Public Works Board of Supendsom on the date shotnm. - Design FEB 8 _ 1994 - Accounting, R. Gilchrist ATTESTED: - R. Bruno PHIL BATCHELOR Clerk of the Board Contractor of Suorvisore and County Administrator n GB\tt By ,_,(' �•JIX rCt�!� G_ � �__.Oeputy c:BO\OER-8.t2