Loading...
HomeMy WebLinkAboutMINUTES - 07131993 - 1.28 TO: BOARD OF SUPERVISORS, AS THE GOVERNING BOARD OF CONTRA COSTA COUNTY AND CONTRA COSTA COUNTY FLOOD CONTROL AND WATER CONSERVA- TION DISTRICT FROM: J. MICHAEL WALFORD, CHIEF ENGINEER DATE: July 13, 1993 SUBJECT: Rescind the Approval of the Plans and Specifications and Rescind the Advertising for bids for the 1993 Walnut Creek Desilting Project. Project No. 7520-669316-93 CP #92-21. Specific Request(s) or Recommendation(s) & Background & Justification I. RECOMMENDED ACTION: RESCIND the approval of the plans and specifications for the project and RESCIND the advertising for bids that are to be received on Tuesday, July 20, 1993, at 2:00 pm. II. FINANCIAL IMPACT: None. III. REASONS FOR RECOMMENDATION/BACKGROUND: In order to desilt the channel, it is necessary that the District obtain a permit from the United States Army Corps of Engineers. On March 26, 1993, staff submitted an application for the Corps of Engineers Permit. The Corps has just informed the District that a permit will not be issued in time to complete the project during the 1993 construction season. Therefore, the project needs to be cancelled. IV. CONSEQUENCES OF NEGATIVE ACTION: If the project is not rescinded, bids can be submitted. Continued on Attachment:_ SIGNATURE: &24ti , _ RECOMMENDATION OF COUNTY ADMINISTRATOR _ RECOMMENDATION OF BOARD COMMITTEE APPROVE OTHER SIGNATURE(S): ACTION OF BOARD ON JUL 13 1993 APPROVED AS RECOMMENDED OTHER VOTE OF SUPERVISORS _1// UNANIMOUS (ABSENT ) AYES: NOES: ABSENT: ABSTAIN: HF:kd c\BO:BO13.t7 I hereby certify that this Is a true and correct copy of an action taken and entered on the minutes of the Orig. Div: Public Works (FC) Board of Supervisors on the date shown. Contact: Melissa Morton, 313-2285 ATTESTED: Jul 1 1 1993 cc: County Administrator PHIL BATCHELOR,clerk of the Board Attn: E. Kuevor of Supervisors and County Administrator County Counsel GMEDA �� e Auditor-Controller By . (C>(�'� -1 p rf ,Deputy PW Depart.Accounting Flood Control