HomeMy WebLinkAboutMINUTES - 06151993 - 1.16 BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA COUNTY
FLOOD CONTROL AND WATER CONSERVATION DISTRICT
Adopted this Order on June 15, 1993, by the following vote:
AYES: Supervisors Powers, Smith, Bishop, McPeak and Torlakson
NOES: None
ABSENT: None
ABSTAIN: None
SpecificRequest(s)or s ground&Jusiffication
SUBJECT: Rejection of all bids for the Drainage Area 48C, Line A Bypass Project, located in
the West Pittsburg area.
Project No. 7572-6D8477-92
Engineer's Estimate: $177,451.50
Bidder Bid Amounts
Palma, Inc. $258,814.00
Fairfield, CA
R & E Construction Co. $288,025.00
Walnut Creek, CA
Pfister Excavating, Inc. $295,867.50
Vallejo, CA
V & M Construction $313,566.00
Antioch, CA
The above-named project and the specifications therefor having been previously approved, and
bids having been duly invited and received by the Director of Public Works; and
The Director of Public Works having reported to the Board that all bids exceeded the engineer's
estimate. The lowest bid exceeded the engineer's estimate by $81,362.50;
NOW, THEREFORE, the Board REJECTS all bids received for the above-named project; and
The Board ORDERS that any bid bonds posted by the bidders are to be exonerated and any
checks or cash submitted for security shall be returned.
I hereby certify that this Is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supe on the date shown.
ATTESTED: 5 1491
PHIL BATCHELOR,Clerk of the Board
of Supervisors and County Administrator
By .,..&.�' h A,6
Contact: B.J. Kerekes, (510) 313-2321
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works
- Design
- Accounting, R. Gilchrist
- R. Bruno
Bidders
C:\WP51\BO\DA48C-15.16