HomeMy WebLinkAboutMINUTES - 07141992 - 1.6 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July 14, 1992
SUBJECT: Approving Plans and Specifications and Advertise for bids for the San Pablo
Avenue/Willow Avenue and Willow Avenue/Hawthorne Drive Intersection Improvements
Project.
Project No. 0662-6R4272-89, CDD-CP Nos. 91-40 and 89-72.
Specific Request(s) or Recommendations) & Background & Justification
I. RECOMMENDED ACTION:
APPROVE the Plans and Specifications for the Project and
ADVERTISE for bids to be received on Thursday, August 6, 1992, at 2:00 p.m.
DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with Section
20392 of the Public Contract Code.
II. FINANCIAL IMPACT:
The estimated contract cost of the project is $712,000, funded by Traffic Systems Management
(100%)
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The project is needed to improve traffic operations and safety on Willow Avenue and at the San
Pablo Avenue/Willow Avenue and Willow Avenue/Hawthorne Drive intersections.
The Public Works Director has filed with the Board of Supervisors the Plans and Specifications
for the project.
Continued on Attachment: X SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JUL 14 1992 APPROVED AS RECOMMENDED OTHER_
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT X )
AYES: NOES:
ABSENT: ABSTAIN:
JRB:jlg
c\BO:bol4.t7 I hereby certify that this Is a true and correct copy Y
an action taken and entered on the minutes of the
Orig. Div: Public Works (Design Division) Board of Supervisors on the data shown.
cc: CountyAdministrator i-MESTED: .��._
PHIL BATCHELOR,Clerk the Board
Attn: E. Kuevor of Supervisors and untyAdministrator
Auditor-Controller
PW Accounting By ,oepuw
Construction
Community Development
i
1
'r(lnup.'Y}^.r;'tr:�.t,;n.�f.w�•;
/49
Approving Plans and Specifications and Advertise for bids for the San Pablo Avenue/Willow Avenue
and Willow Avenue/Hawthorne Drive Intersection Improvements Project
July 14, 1992
Page 2
The general prevailing rates of wages, which shall be the minimum rates paid on this project, have been
filed with the Clerk of the Board and copies will be made available to any interested party upon request.
The Board reviewed and approved the project on June 11, 1991 and found, on the basis of the initial
study and all comments received, that there is no substantial evidence that the project will have a
significant effect on the environment and adopted the Negative Declaration in compliance with the
California Environmental Quality Act. A Notice of Determination was filed with the County Clerk on June
12, 1991.
IV. CONSEQUENCES OF NEGATIVE ACTION:
If the project is not approved for advertising, it will not be constructed.