HomeMy WebLinkAboutMINUTES - 06161992 - 1.7 (2) TO: BOARD OF SUPERVISORS
s.... Contra
FROM: PHIL BATCHELOR
County Administrator Costa
DATE: June 1992C�'•• .• • : '`� ounty
SUBJECT: COUNTY JUSTICE CONSTRUCTION PROGRAM
Specific Request(s) or Recommendation(s) & Background & Justification
RECOMMENDATION:
APPROVE and AUTHORIZE Chair to execute amendment to County' s Standard
Agreement (Contract *008-90). with the Board of Corrections modifying the
programmed use for portions of the Martinez Detention Facility.
FINANCIAL IMPACT:
None
REASONS FOR RECOMMENDATION/BACKGROUND:
The State Board of Corrections provided funding to remodel the F- and M-
Modules of the Martinez Detention Facility as part of the Jail Capital Grants
program (Proposition 52) . This construction project was completed consistent
with the State . grant and approved design. Following construction of this
project and the opening of the. West County Detention Facility, the Sheriff ' s
Department changed elements of inmate housing assignments. A separate
portion of F-Module was changed from a medical use to isolation and
administrative segregation. In addition, inmate exams were relocated from
the clinic to exam rooms situated in each module. Since these operational
changes change the approved program and the facilities rated capacity, the
grant agreement calls for the change to be documented and approved.
Continued on Attachment: YES Signature
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s) :
Action of Board on: G 19 Approved as Recommended —Other
Vote of Supervisors: �-, I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN. ACTION TAKEN
—X Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: ) BOARD OF SUPE ISORS ON DATE SHOWN.
Attested: A/5, z2Zk
cc: CAO, Justice System Programs 4il Batchelor, Clerk of
County. Counsel the Board of Supervisors
Sheriff-Coroner and Cou ty Administrator
GSD-Accounting (Terry Mann)
By: , DEPUTY