HomeMy WebLinkAboutMINUTES - 06041991 - 1.12 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: June 4, 1991
SUBJECT: Approve Contract Change Order No. 6 for the Appian Way Widening Project
Project No. 0662-6134288-84
Specific uest s or Recommendation(s)&Bac grow n
t. Recommended Action:
APPROVE Contract Change Order No. 6 in the approximate amount of$900.00 and AUTHORIZE
the Public Works Director to execute it in order to compensate the contractor, Gallagher & Burk,
Inc., to place slurried concrete around a RCP storm line.
II. Financial Impact:
The project contingency funds are sufficient to cover this change order cost. It is funded by
Federal Highway Administration Funds, (FAU 86%) and Local Road Funds (14%).
III. Reasons for Recommendations and Background:
The location of this pipe required added protection and strength. Also this change order plus
change orders 1 thru 5 exceed $25,000.00 thereby requiring Board approval.
IV. Consequences of Negative Action:
Lack of APPROVAL would preclude payment to the contractor for work required.
Continued on attachment: _yes SIGNATURE: Chu
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: JUN 4 1991 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
X _ UNANIMOUS (ABSENT 11, :d
AYES: NOES:
ABSENT: ABSTAIN:
Orig. Div.: PW(Constr)
cc: County Administrator
Auditor-Controller
Public Works
- Design
- Accounting, R. Gilchrist
- R. Bruno I hereby certify that this Is a true and correct copy of
Contractor an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: JUN 4 1991
PHIL BATCHELOR,Clerk of the Board
of Supervisors andunty Administrator
GB\tt
c:BO\AP2-4.t6 By UaAL Deputy