HomeMy WebLinkAboutMINUTES - 06111991 - 1.4 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: June 11, 1991
SUBJECT: Amend Consulting Services Agreement with Woodward Clyde Consultants
Project No.: 0358-6X4120
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
Approve and Authorize the Public Works Director to execute Amendment No. 1 with Woodward
Clyde Consultants (WCC) for the preparation of the Wetland Mitigation Plan for the State Route
4 Willow Pass Grade Project.
II. Financiallmpact:
There will be no impact to the County General Fund. The additional $9,806 will be reimbursed
by the BAATD funds allocated to the State Route 4 Willow Pass Grade project. The contract will
now totals $24,270.
III. Reasons for Recommendations and Background:
A wetland mitigation plan was developed and processed under the original contract scope of
work. As design proceeded and detention basin property acquisition commenced it was
determined that only one basin would be acquired. This would leave the other two detention
basins to be constructed by developers when the surrounding property develops.
As a result of the reduction in basin area a new wetland mitigation plan will have to be
developed and submitted to the Corps of Engineers for approval. This revised scope of work
will satisfy the wetland mitigation requirements.
i
Continued on Attachment: X SIGNATURE:
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JUN 11 1991 APPROVED AS RECOMMENDED OTHER_
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN:
RVF:kd I hereby certify that this is a true and correct copy of
an action taken and entered on the minutes of the
C:Bo11.1:6 Board of Supervisors on
11 data
th Wn.
ATTESTED: -1991
Orig. Div: Public Works (MP) PHIL BATCHELOR,Clerk of the Board
cc: J. Zimmerman, WCC of Supervisors and Cou ty Administrator
P. Maxwell, CCTA '
C. Raynolds, Accounting By - �'Depub
V. Germany, Design
a
AMEND SERVICES AGREEMENT WITH WOODWARD CLYDE CONSULTANTS
JUNE 11, 1991
Page Two
IV. Consequences of Negative Action:
Should the Board not approve this Resolution the State Route 4 Willow Pass Grade Lowering
Project construction would be delayed until a Wetland Mitigation Plan is Approved.