HomeMy WebLinkAboutMINUTES - 05071991 - 2.8 TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: MAY 7, 1991
SUBJECT: REPORT FROM CHIEF ENGINEER ON WILDCAT - SAN PABLO CREEKS CORPS OF
ENGINEERS PROJECT. PROJECT NO. 7567-TX8604-90, NORTH RICHMOND AREA.
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
ACCEPT1his report on financial status of the Wildcat- San Pablo Creeks Project with attached
financial sheets for Zone 7 and Drainage Area 73.
APPROVE recommendation that$300,000 of Special District Augmentation Funds be allocated
to the Wildcat - San Pablo Creeks Project to cover a portion of the funding shortfall.
AUTHORIZE the Chief Engineer to indicate to the Corps of Engineers that the District is
confident that the necessary local funding will be available for 1992 construction of the San
Pablo Creek improvements between the railroad tracks and for 1992 construction on Wildcat
Creek between the railroad tracks if the State includes sufficient Federal Flood Control
Subvention Program Funds in its Fiscal Year 1991-92 Budget.
AUTHORIZE the chair to send letters to the County's State legislators soliciting their support
for funding the State's Federal Flood Control Subvention Program in Fiscal Year 1991-92.
APPROVE the recommendation of the Design Team and Chief Engineer that the Corps of
Engineers originally planned concrete lined channel should be installed as the improvement
on San Pablo Creek between the railroad tracks and that said improvements are to be
mitigated by extensive landscaping along the south bank of the channel.
DIRECT staff to insure that said mitigation landscaping is included in the project.
Continued on Attachment: X SIGNATURE: Z�x
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON May 7, 1991 APPROVED AS RECOMMENDED X' OTHER_
VOTE OF SUPERVISORS
X UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this Is a hue'and correct copy of
an action taken and entered on the minutes of the
MFK:Iv Board of Supervisors on the date shown.
a:BO\7.t5 ATTESTED: May 7, 1991
PHIL BATCHELOR,Clerk of the Board
Orig. Div: Public Works (Design Div) of Supervisors and Cou ty Administrator
cc: County Administrator
County Counsel
Director Community Development By - °Deputy
Public Works Director
PW Accounting
WILDCAT-SAN PABLO
May 7, 1991
Page Two
II. Financial Impact:
The construction of a concrete lining with mitigation planting in lieu of a gabion lined channel
will result in a significant decrease in non-federal project costs and will reduce the Districts
future maintenance costs. The Public Works Department will make a portion of the North
Richmond Corporation Yard available to the Corps contractor to further reduce the non-federal
project right-of-way costs.
The attached financial status reports for Flood Control Zone 7 and Drainage Area 73 show a
shortfall in local funding of $950,000. To date staff has identified the following potential
sources of funds:
Special District Argumentation Funds $300,000
Reduce R/W Costs Through Donations 90,000
Future Drainage Area 73 Fees 250,000
Sale of Remnant Properties 50,000
$690,000
The cost of the remaining improvements to be constructed is approximately $6,700,000. Our
local costs share is approximately $700,000.
III. Reasons for Recommendations and Background:
On February 12, 1991, staff reported to the Board on the shortfall in funding for the Wildcat -
° San Pablo Creeks Corps of Engineers Project. Since then we have met with the Flood
Control Zone 7 Advisory Board and contacted both San Pablo and Richmond indicating our
funding problem and soliciting their assistance. On April 15, 1991 staff met with the City
Council of San Pablo. We are also working with the City of Richmond to seek dedication of
some of the needed rights-of-way along Wildcat Creek. These development dedications could
reduce the local cost share by $90,000.
The State Department of Water Resources is expected to owe $1,900,000 to Zone 7 and
Drainage Area 73 by June 30, 1991. If the State does not fund the subvention program in
Fiscal Year 1991-92 the district will have insufficient capital to fund both Wildcat and San Pablo
Creeks construction in 1992. Under this scenario we propose that the San Pablo Creek
improvements be funded and the Wildcat Creek improvements be deferred until 1993. There
is no legal requirement that the State provide funding to the Department of Water Resources
Federal Flood Control Subvention Program.
The original draft State budget proposes $43 million for the subvention program in FY 1991-
92. The Assembly Way and Means Subcommittee recommends that the amount be reduced
to $30 million, and it is very unsure that any funding will be provided in FY 1991-92. The
Districts' primary collateral that the State claims will ultimately be paid is our possession of the
Pine Creek Detention basin surplus property which can be sold to cover the State's
subvention obligation on both the Wildcat-San Pablo Creeks project and the Walnut Creek
project.
On March 21, 1989, the Board of Supervisors considered the final report from the Wildcat and
San Pablo Creeks Project Design Team (Design Team) which recommended a gabion-walled
channel alternative on San Pablo Creek between the railroad tracks, the report from the Chief
Engineer recommending implementation of the Corps approved plan alternative of a concrete
channel lining, and letters stating preferences regarding channel lining type.
The Board directed the Chief Engineer to solicit input from the Corps regarding timing, costs
and flooding potential impacts due to implementation of each alternative.
The Corps responded by letter indicating they had not programmed into their budget for 1990
sufficient funds to construct the channel improvements on San Pablo Creek between the
railroad tracks. Consequently, the earliest this reach of channel could be improved is 1991.
WILDCAT-SAN PABLO
May 7, 1991
Page Three
In response the Board on April 25, 1989 requested the Corps to consider the feasibility of a
gabion-walled channel in this reach as a part of their hydraulic model study of Reach II (San
Pablo Creek upstream of AT&SF.)
On September 19, 1990 the Corps presented the results of their cost benefit analysis to the
Design Team. Their analysis has concluded that a 100 year flood design for Reach II is not
economically feasible and therefore a hydraulic model study is not warranted at this time. The
Corps did perform a mathematical study and concluded that a gabion-walled channel between
the tracks is hydraulically feasible for a portion of the portion of the reach between the tracks.
After the Corps presented both the concrete-lined rectangular and gabion-walled channel
alternatives, with their associated impacts, the Design Team accepted the concrete-lined
rectangular channel. However, the acceptance was conditioned upon (1) the installation of
an acceptable landscape mitigation corridor along the south bank of this reach and (2) the
elimination of maintenance access from the top of bank and provision of access to the channel
bottom at a location just downstream of the SPRR tracks.
IV. Consequences of Negative Action:
Completion of the two remaining segments of the Corps of Engineers improvements will not
occur and $5,800,000 in State and Federal Government infrastructure funding will be lost.
FINANCIAL STATUS
WILDCAT CREEK - FLOOD CONTROL ZONE 7
Status as of January 1, 1991
Summary of Available Fundin0:
Cash on Hand <$162,000>
FY 1990-91 Tax Revenue $60,000
State Dept. of Water Resources Subventions
Past Due FY 1989-90 $208,000
Amount Due 07/01/90 thru 12/31/90 93,000
Total Due from State (SDWR) 301,000
Corp of Engineers Reimbursement for Mitigation Planting:
Amount Due thru 12131/90 $157,000
Estimate Future amount due 95,000
Total Corps of Engineers Reimbursement 252,000
Estimate SDWR Reimbursement for Contract 3 Costs 983,000
Estimate Tax Revenue FY 1991-92 and FY 1992-93 80,000
Estimate Credit from Drainage Area 73 640,000
Total Revenue: 2,316,000
Estimated Total Funding: $2,154,000
Summary of Estimated Costs:
Annual Maintenance Costs
Remaining FY 1990-91 $10,000
FY 1991-92 30,000
FY 1992-93 35,000
Total Maintenance Costs thru 06/30/93 $75,000
Estimate Remaining Control 3 Costs
Utility/Bridge Relocations $794,000
Rights of Way Acquisitions 445,000
5% Cash Contribution to Corp 166,000
Local Coordination Cost 50,000
Total Contract #3 Costs 1,455,000
Remaining Mitigation Planting Costs 100,000
Channel Improvements Upstream of RR Tracks 250,000
Zone 7 Revolving Fund Loan Payoff 780.000
Estimated Total Costs 2,660,000
ESTIMATED FUNDING SHORT FALL: $506,000
MFK:Iv
c:zone7.fin
(April 24, 1991)
FINANCIAL STATUS
SAN PABLO CREEK - DRAINAGE AREA 73
Status as of January 1, 1991
Summary of Available Fundina:
Cash on Hand <$386,000>
Estm. Drainage Fees 01/01/91 thru 06/30/92 $60,000
State Dept. of Water Resources Subventions
Past Due FY 1989-90 $578,000
Due in FY 1990-91 553,000
Estm. Contract #3A Claims 612,000
Estm. CE Contract #1 & 2 Extra Deposits 140,000
Total Due from State (SDWR) 1,883,000
Corp of Engineers Reimbursement for Mitigation Planting:
Amount Due thru 12/31/90 $157,000
Estimate Future Amount Due 95,000
Total Corps of Engineers Reimbursement 252,000 -
Total Revenue: 2,195,000
Estimated Total Funding: $1,809,000
Summary of Estimated Costs:
Estm. Remaining Contract #1/#2 Costs:
Corp. Deposit 223,000
Utility Costs 160,000
R/W Costs 300,000
Total Contract #1/#2 Costs $683,000
Estimate Remaining Contract #3A Costs:
Utility/Bridge Relocations $435,000
Rights of Way Acquisitions 183,000
5% Cash Contribution to Corp 170,000
Local Coordination Cost 50,000
Total Contract #3A Costs $838,000
Remaining Mitigation Planting Costs 100,000
Transfer to Zone 7 for Joint Costs 640,000
Total Expenses 2,261,000
ESTIMATED FUNDING SHORT FALL: $452,000
MFK:ly
c:DA73.fln
(April 24, 1991)