SUBJECT: PROGRESS REPORT # 27 FROM O'BRIEN-KREITZBERG ON WORK ON THE
COUNTY'S DETENTION FACILITIES
SPECIFIC REQUEST(S)OR RECOMMENDATION(S)&BACKGROUND AND JUSTIFICATION
RECOMMENDATION-
Acknowledge receipt of Progress Report # 27 from
O"Brien-Kreitzberg & Associates, Inc. on work on the County' s
detention facilities for the months of January, . February and
March, 1991 .
BACKGROUND:
Each month the County' s Construction Manager for the West County
Justice Center, Marsh Creek Detention Center and Martinez
Detention Facility, O'Brien-Kreitzberg & Associates, Inc. , files
a progress report with the County on the work they are
supervising on the construction of the West County Justice
Center, Marsh Creek Detention Center and the Main Detention
Facility in Martinez.
,Progress Report # 27 which covers the months of January, February
and March, 1991 notes, in regard to the West County Justice
Center, that the petitioner in the lawsuit has filed a motion for
attorney' s fees. Subsequently, the petitioner and the County
negotiated a settlement for $65,000 which has since been paid by
the County. Due to code required changes not contained in the
base contract documents, corrections to the perimeter security
system and changes requested by the Sheriff' s Department,
occupancy is now estimated for June 1, 1991. Construction is
reported to be 99.90 complete. The remaining financial
contingency is $458,648.
CONTINUED OIN ATTACHMENWeS YES SIGNATURE:
RECOMMENDATION OF COUNTY ADMINISTRATOR RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON May 21, 1991 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A TRUE
UNANIMOUS(ABSENT ) AND CORRECT COPY OF AN ACTION TAKEN
AYES:- NOES: AND ENTERED ON THE MINUTES OF THE BOARD
ABSENT: ABSTAIN: OF SUPERVISORS ON THE DATE SHOWN.
CC: ATTESTED MAY 21 1991
PHIL BATCHELOR,CLERK OF THE BOARD OF
County Administrator SUPERVISORS AND COUNTY ADMINISTRATOR
Sheriff-Coroner
� ��
M382 (10/88) BYDEPUTY
In regard to the Marsh Creek Detention Facility, the Progress
Report notes that the County' s waterproofing consultant produced
a report detailing their investigation of the shower area leaks.
County Counsel has provided the contractor a copy of this report
and has scheduled a meeting to discuss correction of the leaks
with the contractor. In investigating the causes of the leaks,
it- was determined that the tile was glued down over gypsum board
arid' plywood, rather than being set in a cement base.
Construction is reported to be 99% complete. The project is
Within budget.
In regard to the Main Detention Facility in Martinez, the
Progress Report notes that construction began on M Module on
January 22, 1991. Currently the project is 83 days behind
schedule. Completion is expected in late April, 1991. The
project is over budget. Construction is currently 86% completed.
Overall, the three projects are estimated .to end up $920,000 over
original estimates.