HomeMy WebLinkAboutMINUTES - 05211991 - 1.59 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: May 21, 1991
SUBJECT: BOARD REFERRAL DATED May 21, 1991, - BAILEY ROAD, WEST PITTSBURG
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
Accept the following report, retain the existing bicycle lanes and no parking restrictions on Bailey
Road and direct the Public Works Director to send a copy of this report to William Filbeck, West
Pittsburg Municipal Advisory Council.
II. Financial Impact:
None, unless the Board of Supervisors directs the Public Works Director to remove the No
Parking signs and bicycle lane markings on Bailey Road, which would cost approximately
$3,000.
III. Reasons for Recommendations and Background:
On February 5, 1991, the Board of Supervisors referred a letter from William Filbeck, President,
West Pittsburg Municipal Advisory Council, objecting to the recent installation of bicycle lanes
and "No Parking" signs on that "portion of Bailey Road between Willow Pass Road and Canal
Road in West Pittsburg, to Public Works for investigation and report.
Recently, the Board of Supervisors authorized the Community Development Department to
develop a Countywide Bikeway Plan in conjunction with the County General Plan. This plan is
being developed in cooperation with other local agencies and bicycle groups and coalitions.
The primary goals of the new Bikeway Plan are to expand opportunities for bicycle use in the
County, to delineate a countywide master plan of bikeways and lanes, to assure long term
Continued on Attachment: x SIGNATURE: % Yf ✓2�
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON MAY 21 1991 APPROVED AS RECOMMENDED �_ OTHER
VOTE OF SUPERVISORS
UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that thb b a Crus and correct copy of
an action taken and entered on the minutes of the
LLV:cl Board of Supervisors on the date shown.
c:BOBailey.m ATTESTED: MAY 2-1 1gg1
PHIL BATCHELOR,Clerk of the Board
Orig. Div: Public Works (R/E)
of Supervisors and County Administrator
cc: W. Filbeck, West Pittsburg Municipal By . AY��� A,,; Depuq►
Advisory Council
BAILEY ROAD - WEST PITTSBURG
May 21, 1991
Page Two
Ill. Reasons for Recommendations and Background: (Cont.)
maintenance of bicycle facilities and to incorporate consideration of the needs of bicycles in the
everyday planning activities of public agencies.
The Public Works Department has been implementing the goals of the Bikeways Plan by
incorporating bicycle lanes in County road projects when appropriate. The portion_of Bailey
Road between Willow Pass Road and State Highway 4 provides access to local residential areas,
schools and local commercial areas. In addition, BARTD is planning to extend its rail line from
Concord to West Pittsburg with a station at State Route 4 at Bailey Road.
The Public Works Department has applied for outside funding to supplement local funds to
implement bicycle facilities along portions of Canal Road, Willow Pass Road, Bailey Road and
Evora Road. The Public Works Department has been successful in obtaining some outside
funding because the Department has made certain commitments to complete the construction
of bicycle lanes along the four above mentioned roads.
For all of the above reasons, and the fact that the Board of Supervisors supports bicycle lanes,
the Public Works Department included the marking of bicycle lanes on Bailey Road in
conjunction with the recent road widening project between Willow Pass Road and Canal Road.
Unfortunately, this new portion of Bailey Road is not wide enough to provide both bicycle lanes
and on-street parking. For this reason, it was necessary to prohibit all on-street parking in order
to provide safe and legal bicycle lanes. The Public Works Department is sympathetic with the
local residents loss of on-street parking, however, the existing bicycle lanes are a benefit to the
community at large and they are in keeping with the County's desire to expand bicycle facilities
within the County.
IV. Consequences of Negative Action:
If the bicycle lanes are removed, bicyclists will not have a safe dedicated portion of the
pavement for their use on Bailey Road. Also, removal of bicycle lanes from Bailey Road could
jeopardize the County's future success in obtaining outside funding to implement additional
bicycle lane projects in the West Pittsburg area.