TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: April 23, 1991
SUBJECT: Approval of Contract Change Orders No. 5 and 6, for the Highway 4 Widening Project
in the Discovery Bay Area.
Project No.: 4660-6X4122-88
Specific Request(s)or Recommenda m(s)&Background&Justification
I. Recommended Action:
Authorize the Public Works Director to execute Contract Change Orders 5 and 6, in the
approximate amounts of $15,000.00 and $8,000.00 to compensate the contractor, Teichert
Construction, for installing storm drains, salvaging base rock and placing fill in an abandoned
culvert.
II. Financial Impact:
The project contingency funds are sufficient to cover the change order costs. The source of
funds is the Discovery Bay Area of benefit.
III. Reasons for Recommendations and Background:
The cumulative total of Contract Change Orders No. 1 through No. 6 exceeds $25,000.00,
requiring approval. Design changes which required additional work were made to improve
drainage, reuse base rock and fill an abandoned culvert.
IV. Consequences of Negative Action:
The lack of APPROVAL would preclude payment for work required.
Continued on attachment: —yes SIGNATURE• a4 6,,ru
c-4
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON: April 23, 1991 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
X UNANIMOUS(ABSENT__L_j
ABSENT: ABSTAIN:
Orig. Div.: PW(Constr) I hereby certiy that this Is a true and correct copy of
cc: County Administrator an action taken and entered on the minutes of the
Auditor-Controller A�rd�o8ipe" J T`11 ""
Public Works - Design PHIL BATCHELOR,Clerk of the Board
- Accounting, R. Gilchrist ofsupervismand counlyAdmin+atrstor
- R. Bruno
ContractorBy l a' - -- .Do"
DG\tt
c:BO\H4WD-23.t4