HomeMy WebLinkAboutMINUTES - 04231991 - 1.25 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: April 23, 1991
SUBJECT: Get Date for Public Hearing to Revise the Richmond/EI Sobrante Area of Benefit.
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
Fix May 14, 1991 at 11:00 AM for a public hearing to revise and update the Richmond/EI
Sobrante Area of Benefit fee schedule and project list; and direct the Public Works Director to
give notice of the hearing and to file a copy of the revised Development Program Report for the
Richmond/El Sobrante Area of Benefit with the Clerk of the Board in accordance with
Government Code Sections 65091, 65962, and 66484.
II. Financial Impact:
Revising the Richmond/EI Sobrante Area of Benefit will update the fees to reflect current
construction costs and will decrease the future financial demand on the County for the
infrastructure needed to serve this area.
III. Reasons for Recommendations and Background:
The Richmond/EI Sobrante Area of Benefit is being revised to update the fees to reflect current
construction costs, revise growth projections for the project area and to update the project list
to reflect current needs in the circulation element for the Richmond/EI Sobrante area.
The Richmond/EI Sobrante Area of Benefit was established in 1985 and encompasses the EI
Sobrante Valley. In,1988 the EI Sobrante Traffic Advisory Committee began the task of updating
the Area of -Benefit. The updating process is now completed. The County Public Works
Department has met extensively with the EI Sobrante Traffic Advisory Committee and the City
Continued on Attachment: X SIGNATURE: � �
RECOMMENDATION OF COUNTY ADMINISTRATOR
RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON April 23, 1991 APPROVED AS RECOMMENDED X OTHER
VOTE OF SUPERVISORS
_ X UNANIMOUS (ABSENT I )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this Is a true and correct copy of
an action taken and entered on the minuteo of the
HB:MC:eh Board of Supero 3 date
ow&
c:BO 12.t3 ATTESTED:
PHIL BATCHELOR,Clark of the Board
of and County Adminiatraatar
Orig. Div: Public Works (Road Engineering)
cc: See page 2 By �- --._ • � - ®�pu�►
I
Get Date for Public Hearing to Revise the Richmond/EI Sobrante Area of Benefit
April 23, 1991
Page 2
IIII. Reasons for Recommendation and Background: (Cont.)
of Richmond. The cost estimates and growth projections were done in great detail and were
reviewed by the City of Richmond, the County and Traffic Advisory Committee. The Traffic
Advisory Committee approved the Revised Development Report for the Richmond/EI Sobrante
Area of Benefit on January 17, 1991.
The Revised Development Report for the Richmond/EI Sobrante Area of Benefit is on file with
the Public Works Director and the Clerk of the Board.
IAV. Consequences of Negative Action.
Failure to fix a hearing date will prevent the Richmond/EI Sobrante Area of Benefit from being
revised. Development will continue to occur without updating the fees or the project list. As a
result, there will not be an adequate funding mechanism in place to construct all of the needed
roadwork.