HomeMy WebLinkAboutMINUTES - 04161991 - 1.69 1-009
-J Contra
Costa
i Y
County
TO: Board of Supervisors
FROM: Phil Batchelor, County Administrator
DATE: April 16, 1991
SUBJECT: West County Justice Center, Project B
Change Order (PC B119)
Specific Request(s) or Recommendation(s) & Background & Justification
RECOMMENDATION ACTION
AUTHORIZE the Director, Justice System Programs to execute a change order for
work at the West County Justice Center, Project B.
FINANCIAL IMPACT
There is no financial impact beyond that already forecast and budgeted as
part of the projects' construction change order allowance. The estimate for
this work totals $30,341.
REASONS FOR RECONNECATION/BACKGROUND
The Director, Justice System Programs has been given the authority to sign
individual change orders up to a limit of $25,000 each. Change Orders
exceeding $25,000 require Board Authorization.
During construction, the Sheriff's Department had the Architect redesign the food
distribution system to use food carts. As a result of this change, the pantry area
of each housing module (9) was modified to receive and store these new food carts.
These changes included the relocation of plumbing, moM'ato wingcounters,
and addition of corner guards and cart bumpers.
CONTINUED ON ATTACHMENT: YES Signature:
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s)
Action of Board on: 4-16-91 Approved as Recommended X Other
Vote of Supervisors: I HEREBY CERTIFY THAT THIS IS A TRUE
AND' CORRECT COPY OF AN ACTION TAKEN
X Unanimous (Absent ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes:_ BOARD OF SUPERVISORS ON DATE SHOWN
Absent Abstain
cc: CAO, Justice System Programs Attested: April 16, 1991
County Counsel Phil Batchelor, Clerk of
GSD Accounting the Board of Supervisors
Auditor-Controller(Accounts Payable) and County Admin'strator
By:
BDORD7 DEPUTY