HomeMy WebLinkAboutMINUTES - 07171990 - 1.2 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: July 17, 1990
SUBJECT: Agreements with Pacific Gas & Electric Company and Pacific Bell for work to be
performed in conjunction with the Nichols Road Overhead Project.
Project Number 0662-6114132-87
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. RECOMMENDED ACTION:
APPROVE and AUTHORIZE the Public Works Director to execute agreements with Pacific Gas and
Electric Company and Pacific Bell to relocate their facilities in conjunction with the Nichols Road
Overhead Replacement Project.
II. FINANCIAL IMPACT:
There is no impact to the County General Fund. The Nichols Road Overhead Replacement Project is
funded by the General Chemical.Corporation, Chevron U.S.A., Inc. and Allied Signal Corporation (14%)
and Federal funds (86%). The cost of the relocations to be performed by the utilities is $27,618.95 by
Pacific Gas and Electric Company and $11,293 by Pacific Bell.
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The existing Nichols Road Overhead is in poor condition and qualified as a Federal Highway Bridge
Replacement project in 1986. The project will provide a new grade separation structure spanning the
Southern Pacific Transportation .Company tracks on Nichols Road. The structure serves General
Chemical Corporation, Chevron U.S.A., Inc. and Allied Signal Corporation who have agreed to provide
the local share.
Continued on Attachment: X SIGNATURE:__1;1�.�Lan
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JUL 17 1990 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT JIM )
AYES: NOES:
ABSENT: ABSTAIN:
I hereby certify that this is a true and correct copy of
an action taken and entered on the minutes of the
JRB:drg Board of Supervisors on the date shown.
c:BO:17.t7 ATTESTED: JUL 17 1990
PHIL BATCHELOR,Clerk of the Board
Orig. Div: Public Works (Design Division) of Supervisors and county Administrator
cc: County Administrator
Auditor-Controller "��'''h�'
Road Engineering
PW Accounting
Construction
Agreements with P G & E Company and Pacific Bell for Nichols Road Overhead Project.
July 17, 1990
Page Two
III. REASONS FOR RECOMMENDATION/BACKGROUND Cont'd.:
A contract has been awarded to replace the overhead and the utilities must be relocated to construct
the project. Both utility companies have agreed to perform the work to relocate their facilities. The
County has agreed pay for the relocations because they are not presently located in the County right-
of-way.
IV. CONSEQUENCES OF NEGATIVE ACTION:
The project cannot be constructed unless the utilities are relocated. Failure to approve and authorize
execution of these agreements will delay construction indefinitely and the County will lose the funding
for this project.