HomeMy WebLinkAboutMINUTES - 07171990 - 1.1 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR '
DATE: July 17, 1990
SUBJECT: Approving Plans and Specifications for Camino Tassajara Overlay-South
Project No.: 0662-6134126-89, Tassajara Area
CP#89-74.
SPECIFIC REQUEST(S) OR RECOMMENDATION(S) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
APPROVE the Plans and Specifications for the Project, and
ADVERTISE for bids to be received on Thursday, August 16, 1990, at 2:00 p.m., and
DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with Section
20392 of the Public Contract Code, and
DETERMINE that the project is exempt from "CEQA requirements as a Class 1 C Categorical
Exemption, and
DIRECT the Director of Community Development to file a Notice of Exemption with the County
Clerk.
II. Financial Impact:
The estimated contract cost of the project is $430,700, funded by CRP (86%), State matching
funds (14%).
III. Reasons for Recommendations and Background:
The project is needed to improve safety and extend the usable life of this road.
Continued on Attachment: X SIGNATURE: y9 ,
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON JUL 1Y 1990 APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
✓ UNANIMOUS (ABSENT
AYES: NOES:
ABSENT: ABSTAIN:
RT:drg -
c:BO17.t7 1 hereby certify that this is a tru6 and correct copy of
Orig. Div: Public Works (Design Division) an action taken and entered on the minutes of the
cc: County Administrator Board of Supervisors on the date shown.
ATTESTED: J,J 111 1 .7 l..l Lt_
Attn: E. Kuevor PHIL.BATCHELOR,Clerk of the Board
Auditor-Controller of Supervisors and County administrator
PW Accounting
Construction
Community Development
Attn: G. Almquist
�I
Ji
Approving Plans and Specifications for Camino Tassajara Overlay-South
July 17, 1990
Page Two
III. Reasons for Recommendations and Background Cont'd.:
The project has been determined to be in compliance with the General Plan and is exempt from
CEQA because it satisfies the requirements of Section 15301. The project consists of overlaying
an existing highway facility, no additional right-of-way is required.
The Public Works Director has filed with the Board of Supervisors the Plans and Specifications
for the project.
The general prevailing rates of wages, which shall be the minimum rates paid on this project,
have been filed with the Clerk of the Board and copies will be made available to any interested
party upon request.
IV. Consequences of Negative Action:
If the project is not approved for advertising, it will not be constructed.