HomeMy WebLinkAboutMINUTES - 06261990 - 1.76 File: 250-9010/B. 4 .4
THE BOARD OF SUPERVISORS
CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Order on June 26, 1990, by the following vote:
AYES: Supervisors Powers, Schroder, McPeak, Torlakson and Fanden
NOES: None
ABSENT: None
SUBJECT: Award of Contract for First Floor Remodeling at A. F.
Bray Building, 1020 Ward Street, Martinez for Superior
Court Administrator.
Budget Line Item No. 0122-4109
Authorization No. 0925-WH109H
(Formerly WPE731)
Bidder Total Amount Bond Amounts
Atkinson-Hebert $13, 100 . 00, Labor & Mats . $6 ,550 . 00
Construction, Inc. , Base bid Faithful Performance
1430 Willow Pass Rd. only $13, 100 . 00
Suite 140
Concord, CA 94520
Elmer Lundgren
Concord, California
Edward A. Sparacino,
General Contractor
Martinez, California
Tyler Construction
Antioch, California
S .J. Construction
Benicia, California
Younger-Wunar, Inc.
E1 Cerrito, California
Three J' s Development, Inc .
Pittsburg, California
The above-captioned project and the specifications therefor
being approved, Addendum No. 1 being issued and bids being duly
invited and received by the Director of General Services; and
The Director of General Services recommending that the bid
listed first above is the lowest responsible bid and this Board
concurring and so finding;
IT IS BY THE BOARD ORDERED that the contract for the furnishing
of labor and materials for said work is awarded to said first
listed bidder at the listed amount and at the prices submitted in
said bid; and that said contractor shall present two good and
sufficient surety bonds as indicated above; and that the General
Services Department shall prepare the contract therefor; and
IT IS FURTHER ORDERED that after the contractor has signed the
contract and returned it, together with bonds as noted above and
any required certificates of insurance or other required documents,
and the Director of General Services has reviewed and found them to
be sufficient, the Director of General Services is authorized to
sign the contract for this board; and
0
Page 1 of 2
r
.%'. Z'
AWARD OF CONTRACT FOR FIRST FLOOR 250-9010/B. 4 . 4
REMODELING AT A.F. BRAY BUILDING, June 26, 1990
1020 WARD STREET, MARTINEZ FOR
SUPERIOR COURT ADMINISTRATOR
IT IS FURTHER ORDERED that in accordance with the project
specifications and/or upon signature of the contract by the
Director of General Services, . any bid bonds posted by the bidders
are to be exonerated and any checks or cash submitted for security
shall be returned; and
IT IS FURTHER ORDERED that the Director of General Services is
authorized to sign any escrow agreements prepared for this project
to permit the substitution of securities for moneys withheld by the
County to ensure performance under the contract, pursuant to
Section 22300 of the Public Contract Code; and
IT IS FURTHER ORDERED that the Director of General Services is
authorized to consent to the substitution of another person as a
subcontractor, in any of the situations listed and after the
written notice specified in Public Contract Code Section 4107 ,
provided written objections to such substitution are not submitted
by the listed subcontractor in accordance with Section 4107 .
I hereby certify that this Is a crus and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: JUN 2 6 1990
PHIL BATCHELOR,Clerk of the Board
Of Supervisors and County Administrator
J.
Orig. Dept.- General Services Dept. - Architectural Division
cc : General Services Department
Architectural Division
G.S. Accounting
Auditor-Controller
Contractor (Via Arch. Div. )
Superior Court Administrator (Via Arch. Div. )
25010B06 . 13A
GB: ls
Page 2 of 2