HomeMy WebLinkAboutMINUTES - 05081990 - 1.16 TO: BOARD OF SUPERVISORS, AS THE GOVERNING BODY OF THE CONTRA COSTA
COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: May 8, 1990
SUBJECT: APPROVING PLANS AND SPECIFICATIONS FOR THE VERDE SCHOOL PAVEMENT
RECONSTRUCTION
Project No.: 7527-6D8610-90
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) &BACKGROUND AND JUSTIFICATION
I. Recommended Action:
APPROVE the Plans and Specifications for the Project and ADVERTISE for bids to be received
on Thursday, May 31, 1990 at 2:00 p.m.
DIRECT the Clerk of the Board to publish the Notice to Contractors in accordance with Section
21191 of the Public Contract Code.
II. Financiallmpact:
The estimated contract cost of the project is$116,200, funded by Flood Control Zone #7, (25%),
State Department of Water Resources (59%), and East Bay Regional Park District (16%).
III. Reasons for Recommendations and Background:
As part of the Corps of Engineers' Wildcat Creek Project an agreement between the Flood
Control District and the Richmond Unified School District was executed June 14, 1988 providing
for the transfer by the School District of necessary rights-of-way to implement the flood control
project at Verde School and requiring the Flood Control District to replace pavement,
landscaping and other appurtenances to mitigate project impacts. This project will fulfill the
Flood Control District's responsibilities under the terms of the agreement.
Continued on Attachment: X SIGNATURE:__
_ RECOMMENDATION OF COUNTY ADMINISTRATOR
_ RECOMMENDATION OF BOARD COMMITTEE
APPROVE OTHER
SIGNATURE(S):
ACTION OF BOARD ON MAY APPROVED AS RECOMMENDED OTHER
VOTE OF SUPERVISORS
āiā UNANIMOUS (ABSENT )
AYES: NOES:
ABSENT: ABSTAIN: I hereby certify that this is a+true and correct copy of
HF:drg an action taken and entered on the minutes of the
BO:8.t5 Board of Supervisors on the date shown.
ATTESTED: MAY g 1990
Orig. Div: Public Works (DESIGN DIVISION) PHIL BATCHELOR,Clerk of the Board
cc: County Administrator of Supervisors and County Administrator
Attn: E. Kuevor
Auditor-Controller
PW Accounting of (Deputy
Construction
Community Development
Attn: Gus Almquist
APPROVING PLANS AND SPECIFICATIONS FOR THE VERDE SCHOOL PAVEMENT
RECONSTRUCTION
May 8, 1990
Page Two
III. Reasons for Recommendations and Background Cont'd.:
The Board reviewed and considered the information contained in the final Environmental Impact
Report (EIR) for the Wildcat and San Pablo Creeks Project on May 18, 1982, and certified that
the EIR had been completed in compliance with the California Environmental Quality Act and
adopted the findings and mitigating measures expressed in Planning Commission Resolution
No. 10-1982.
The Chief Engineer has filed with the Board of Supervisors the Plans and Specifications for the
project.
The general prevailing rates of wages, which shall be the minimum rates paid on this project,
have been filed with the Clerk of the Board and copies will be made available to any interested
parry upon request.
IV. Consequences of Negative Action:
If the project is not approved for advertising, it will not be constructed as agreed.