HomeMy WebLinkAboutMINUTES - 05011990 - 1.10 THE BOARD OF SUPERVISORS OF CONTRA COSTA COUNTY, CALIFORNIA
Adopted this Resolution on May 1, 1990 by the following vote:
AYES: Supervisors Schroder, McPeak, Torlakson and Fanden
NOES: None
ABSENT: Supervisor Powers
ABSTAIN: None RESOLUTION NO.90/261
SUBJECT: Approval of the Final Map and Subdivision Agreement for
Warranty Period and Deficiency Deposit for Subdivision
7129, Byron Area.
The Public Works Director having notified this Board that
the improvements for 7129, being developed by Bar-C Properties
have been completed except for minor deficiencies and that such
improvements have been constructed without the need for a
Subdivision Agreement;
The following documents were presented for Board approval
this date:
The Final Map of Subdivision 7129, property located in the
Byron area, said map having been certified by the proper
officials.
A Subdivision Agreement for warranty period with Bar-C
Properties , subdivider, whereby said subdivider agrees to
satisfy any valid claims of liens of labor and materials as to
the said improvements and subdivision appearing hereafter upon
demand by the county as required in said Subdivision Agreement
for Improvement Warranty within six months from the date of said
agreement.
Said documents were accompanied by:
I.' Security to guarantee the completion of minor road and
drainage deficiencies as required by Title 9 of the
County Ordinance Code, as follows:
A. Cash deposit (Auditor's Deposit Permit No. 172080,
dated April 18, 1990) in the amount of $1, 100 made
by Bar-C Properties.
B. Additional security in the form of a cash deposit
(Auditor's Deposit Permit No. 172080, dated April
18, 1990) in the amount of $16,995 made by Bar-C
Properties.
II. Security for labor and materials for the six month lien
guarantee period as required by Title 9 of the County
Ordinance Code, in the form of a cash deposit
(Auditor' s Deposit Permit No. 172080, dated April 18,
1990) in the amount of $57,200 for labor and materials
made by Bar-C Properties.
III. Letter from the County Tax Collector stating that there
are no unpaid County taxes heretofore levied on the
property included in said map and that the 1989-90 tax
lien has been paid in full and the 1990-91 tax lien,
which became a lien on the first day of March, 1990, is
estimated to be $10,700.
IV. Security to guarantee the payment of taxes as required
by Title 9 of the County Ordinance Code, in the form of
a cash deposit (Auditor's Deposit Permit No. 172022
dated April 17, 1990) made by Bar-C Properties in the
amount of $12, 000 guaranteeing the payment of the
estimated tax;
RESOLUTION NO. 90/261
Approve Final Map and Subdivision Agreement for Subdivision 7129
May 1, 1990
Page 2 of 2
NOW THEREFORE BE IT RESOLVED that said subdivision, together
with the provisions for its design and improvement, is DETERMINED
to be consistent with the County's general and specific plans.
BE IT FURTHER RESOLVED that said Final Map is APPROVED and
this Board does not accept or reject on behalf of the public any
of the streets, paths, or easements shown thereon as dedicated to
public use.
BE IT FURTHER RESOLVED that said Subdivision Agreement is
also APPROVED.
BE IT FURTHER RESOLVED that the improvements have been
completed except for minor deficiencies as of April 19, 1990
thereby establishing the six-month terminal period for the filing
of liens in case of action under said Subdivision Agreement for
Improvement Warranty.
BE IT FURTHER RESOLVED that the $57,200 cash security for
labor and materials (Auditor's Deposit Permit No. 172080, dated
April 18, 1990) deposited by Bar-C Properties be RETAINED for the
six-month lien guarantee period until October 15, 1990, at which
time the Public Works Director is AUTHORIZED to refund the cash
security less the amount of any claims on file.
I hereby certify that this is a true and correct copy of
an action taken and entered on the minutes of the
Board of Supervisors on the date shown.
ATTESTED: - MAY _? igq(l
PHIL BATCHELOR,Clerk of the Board
of Supervisors and County Administrator
.De
--- puffâ–ş
Originator: Public Works (ES)
cc: Director of Community Dev.
Public Works - Construction
Bar-C Properties,
A California Gen Partnership
P.O. Box 102
Antioch, CA 94509
MM:mg
BO: l.t5
RESOLUTION NO. 90/261