HomeMy WebLinkAboutMINUTES - 07181989 - 1.1 WHEN RECORDED, RETURN RECORDED AT REQUEST OF OWNER
TO CLERK, BOARD OF at o'clock M.
SUPERVISORS Contra Costa County Records
STEPHEN L. WEIR, County Recorder
Fee $ Official
BOARD OF SUPERVISORS, CONTRA COSTA COUNTY, CALIFORNIA
In the Matter of Accepting and Giving) RESOLUTION OF ACCEPTANCE
Notice of Completion of Contract for ) and NOTICE OF COMPLETION
Hidden Pond Road Assessment ) (C.C. §3086, 3093)
District 1986-1, W.O. No. 5454 in )
the Pleasant Hill/Lafayette Area ) RESOLUTION NO. 89/ 485
The Board of Supervisors of Contra Costa County RESOLVES that:
The County of Contra Costa on July 28, 1988 contracted with North
Bay Construction, Inc. , for underground utilities , road
construction of Hidden Pond Road, and landscaping, with The
American Insurance Company as surety, for work to be performed on
the grounds of the County; and
The Public Works Director reports . that said work has been
inspected and complies with the approved plans, special provisions
and standard specifications and recommends its acceptance as
complete as of June 28, 1989 .
Therefore, said work is ACCEPTED as completed on said date, and
the Clerk shall file with the County Recorder a copy of this
Resolution and Notice as a Notice of Completion for said contract.
PASSED BY THE BOARD on July 18, 1989 by the following vote:
AYES: Supervisors Powers , Fanden, Schroder, McPeak & Torlakson
NOES: None
ABSENT: None
CERTIFICATION AND VERIFICATION
I certify that the foregoing is a true and correct copy of a
resolution and acceptance duly adopted and entered on the minutes
of this Board's meeting on the above date. I declare under
penalty of perjury that the foregoing is true and correct.
Dated: July 18 , 1989 PHIL BATCHELOR, Clerk of the Board
at Martinez, California of Supervisors and County
Administrator
By
Deputy Clerk
Orig.Dept. : Public Works (Construction)
cc: Record and return
Auditor
Public Works-Accounting
R. Bruno
Contractor
DG:pg
bo: 18 .t7
RESOLUTION NO. 89/485