HomeMy WebLinkAboutMINUTES - 07111989 - 1.86 l ..
100086
TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATES JULY 11, 1989
SUBJECT: AMENDMENT NO. 2 AND CHANGE ORDERS NO. 2 AND NO. 3 TO
FEDERAL AVIATION ADMINISTRATION (FAA) GRANT AGREEMENT FOR
BUCHANAN FIELD AIRPORT IMPROVEMENTS (AIP #3-06-0050-05 )
Specific Request(s) or Recommendation(s) & Background &
Justification
I . RECOMMENDATION
APPROVE and AUTHORIZE the Chairman of the Board of Supervisors
to sign Amendment No. 2 to said Grant Agreement on behalf of
Contra Costa County; and
AUTHORIZE AND DIRECT the Clerk of the Board to attest the
signature of the Chairman and to impress the official seal of
Contra Costa County on the aforesaid Amendment; and
AUTHORIZE AND DIRECT County Counsel to sign a Certificate of
Sponsor's Attorney (after Chairman' s signature) which
certifies that the acceptance complies with all applicable
laws and constitutes a legal and binding obligation.
APPROVE Contract Change Orders No. 2 and No. 3; and
AUTHORIZE the Public Works Director or his designee to sign
said Change Orders on behalf of Contra Costa County.
II . FINANCIAL IMPACT - No changes to the project cost.
III . REASONS FOR RECOMMENDATION/BACKGROUND
See Page 2 .
Cont'd on attachment: B yes Signature: j �-
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Sicmature(s) :
Action of Board on: JUL 11 1989
Approved as Recommended_ Other
Vote of Supervisors: I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY
Unanimous (Absent ) OF AN ACTION TAKEN AND
Ayes Noes ENTERED ON THE MINUTES OF
Absent Abstain THE BOARD OF SUPERVISORS ON
DATE SHOWN.
Attested JUL 11 1989
Orig. Div. : Airports Phil Batchelor, Clerk
cc: County Administrator of the Board of Supervisors
County Counsel and County Administrator
Auditor-Controller
P.W. Accounting
FAA (via BFA)
By�►-„�, i
HEW:dg
amend205 .bo Deputy Clerk
AIP #3-06-0050-05
Amend No. 2
Change Order Nos. 2 & 3
July 11, 1989
Page 2
III . REASONS FOR RECOMMENDATION/BACKGROUND
Amendment No. 2 (which is also Change Order No. 2) changes the
project description. The FAA has required blast pads on the
ends of all the runways . Also, an additional connector taxiway
needs rehabilitation and reconstruction. Other portions of the
project can be reduced in an equivalent dollar amount.
Change Order No. 3 specifies changes within the scope of the
existing contract. These changes include a change in sub-base
..construction materials, reworking of a temporary taxiway,
installation of additional drainage improvements, and a change
.in some of the electrical work. Increases and decreases, plus
contingencies account for all of the costs of these changes .