HomeMy WebLinkAboutMINUTES - 05021989 - 1.6 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: May 2, 1989
SUBJECT: APPROVE Contract Change Order No. 3 for the Cummings
Skyway Slide Repair. Project No. 0671-6R6670-86, in
the Crockett area.
Specific Request(s) or Recommendation(s) & Background &
Justification
RECOMMENDED ACTION:
APPROVE Contract Change Order No. 3 and AUTHORIZE the Public Works
Director to execute Contract Change Order No. 3 in the approximate
amount of $2 , 300. 00 to compensate the contractor, Holman D.
Pettibone, Inc. for increases in contract quantities.
FINANCIAL IMPACT:
The project is 100% funded by the Federal Highway Administration
Emergency Repair fund.
REASONS FOR RECOMMENDATION/BACKGROUND:
During construction the need for fencing became apparent. Fencing
was required for safety and liability reduction purposes. In
addition the amount of compensation for items that overran
required adjustment.
This contract change order provides for the additional work. The
aggregate amount of change orders exceeds $25, 000. 00, requiring
Board approval.
CONSEQUENCES OF NEGATIVE ACTION:
The lack of approval would preclude payment for work required to
complete theārepair of the slide.
Continued on attachment: yes Signature-
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature(s) :
Action of Board on: MAY 2 1989
Approved as Recommended T:5C Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
_X_Unanimous(Absent 1Y ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: BOARD OF SUPERVISORS . ON DATE SHOWN.
Absent: Abstain:
Attested MAYS 1989
Orig. Div. : PW(Constr) Phil Batchelor
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Public Works-Design Administrator
Accounting
R. Bruno
Contractor
LT/s a By 7 , DEPUTY
bo:2 .t5