HomeMy WebLinkAboutMINUTES - 05021989 - 1.2 TO: BOARD OF SUPERVISORS
FROM: J. MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: May 2, 1989
SUBJECT: Approving Addendum for Kirker Pass Road Overlay
Project, Project No. 0662-6R4138-87
Specific Request(s) or Recommendation(s) & Background &
Justification
I. RECOMMENDED ACTION:
Approve prior issuance of Addendum by Public Works Director for
the increase in quantities of Base Failure Excavation and Asphalt
Concrete (failed areas) on the Notice and Proposal for the Kirker
Pass Road Overlay Project.
II. FINANCIAL IMPACT:
Informing bidders of increased quantities is expected to result
in lower unit cost bid prices.
The revised estimated contract cost of the project is $413, 600.
III. REASONS FOR RECOMMENDATION/BACKGROUND:
The original estimate was based on field measurements made in
March, 1988. Since then the failed areas have expanded beyond
what we anticipated.
Continued on attachment: yes Signature: 2 �
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other: .
Signature(s)
Action of Board on: MAY 2 1989
Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS
A TRUE AND CORRECT COPY OF AN
ACTION TAKEN AND ENTERED ON
Unanimous (Absent 17 ) THE MINUTES OF THE BOARD OF
Ayes: Noes: SUPERVISORS ON DATE SHOWN.
Absent: Abstain:
Attested MAY 2 1989
Orig. Div. : PW (Design) Phil Batchelor,
cc: County Administrator Clerk of the Board
Attn: E. Kuevor of Supervisors and
Auditor-Controller County Administrator
PW Accounting
Construction
Community Development
Attn: Gus Almquist
GS/cw By.