HomeMy WebLinkAboutMINUTES - 03281989 - 1.79 1-079
TO: Redevelopment Agency
FROM: Phil Batchelor Contra
Executive Director Costa
DATE: March 14, 1989 County
SUBJECT: FY 88-89 Redevelopment Agency Budget
SPECIFIC REQUEST S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATIONS
Adopt the attached annual Redevelopment Agency budget for fiscal
year 1988-89, in compliance with California Community Redevelopment
Law.
FISCAL IMPACT
Refer to attached budget report details.
BACKGROUND/REASONS FOR RECOMMENDATIONS
California Community Redevelopment Law (Health & Safety Code
Section 33606) requires in part that the Redevelopment Agency adopt
an annual budget containing the following information:
- Proposed expenditures
- Proposed indebtedness to be incurred
- Anticipated revenues
- A work program for the coming year
- An examination of the previous year' s achievements
The attached report fulfills the requirements of Redevelopment Law
and establishes a framework for implementation of the Contra Costa
County Redevelopment Agency Budget for FY 1988-89. Because
revenues and expenditures, by law, must be applied to the
particular project area in which they are generated, separate
budgets, in effect, have been created for the Pleasant Hill, North
Richmond, and West Pittsburg Project Areas. The reports also
contains information of previous financial transactions of the
Agency for comparison purposes and establishes the record for past
activities of the Agency.
CONTINUED ON ATTACE14ENT: YES SIGNATURE.
RECOMMENDATION OF EXECUTIVE DIRECTOR RECO14MENDATIO AG c7 IKE
APPROVE OTHER
SIGNATURE(S) : 1989h 28,
ACTION OF AGENCY ON MarcAPPROVED AS RECOMMENDED X OTHER
I
VOTE OF COMMISSIONERS
X UNANIMOUS (ABSENT ) I HEREBY CERTIFY THAT THIS IS A
AYES: NOES: TRUE AND CORRECT COPY OF AN ACTION
ABSENT: ABSTAIN: TAKEN AND ENTERED ON THE MINUTES
OF THE REDEVELOPMENT AGENCY ON THE
DATE SHOWN.
cc: Redevelopment Agency ATTESTED March 28, 1989
All other distribution via PHIL BATCHELOR,
Redevelopment AGENCY SECRETARY
BY , DEPUTY
JK:cg
cd8/budget.bo
CONTRA COSTA COUNTY REDEVELOPMENT AGENCY
BUDGET AND WORK PROGRAM FOR
FISCAL YEAR 1988-89
INTRODUCTION
California Community Redevelopment Law (Health & Safety Code Section 33606)
requires the Redevelopment Agency to adopt an annual budget containing the
following:
- Proposed expenditures of the Agency
- Proposed indebtedness to be incurred by the Agency
- Anticipated revenues of the Agency
- A work program for the coming year, including goals
- An examination of the previous year's achievements
A) PLEASANT HILL BART
ANTICIPATED REVENUES
Revenues for FY 88-89 are expected to reach $19,090,000 million (of which
$420,000 is tax increments restricted for housing) which includes:
- $800,000 in tax increments of which $160,000 is restricted for housing
pursuant to Section 33334.2 of Health & Safety Code.
- $1,050,000 in developer fees, including 450,000 carry over.
- $13,000,000 in developer payments for real property acquisition/
relocation.
- $100,000 earnings on investment and real estate.
- $380,000 miscellaneous charges for services.
- $3,500,000 from 1987 Note Issue proceeds.
- $260,000 tax increment fund balance - carry over of restricted housing
funds pursuant to Section 3334.2 of Health & Safety Code.
PROPOSED EXPENDITURES
Proposed expenditures for FY 88-89 total approximately $18,670,000 million.
Major expenditures for FY 88-89 will include Public Works contracts of
$945,000; property acquisition of $15,000,000; retirement of long term debt in
the amount of $1,500,000; debt service on Tax Allocation notes in amount of
$450,000; and project professional services of $795,000.
INDEBTEDNESS
The Agency has incurred approximately $12.5 mill'ionin- debt as of June, 1988.
The major elements of Agency debt include:
- $7.5 million Tax Allocation notes issued in December, 1987.
- $1.9 million due to County General fund for advances to the Agency.
- $1.8 million due to County for property conveyances.
- $1.3 million due to Assessment District 1983-1 for an advance from
transit fees.
In addition the County will provide the Agency with certain administrative
services which will accrue as a debt against the Agency. These advances will
be repaid from tax increment revenues as soon as practicable.
B) NORTH RICHMOND
ANTICIPATED REVENUES
Revenues for FY 88-89 are expected to be $130,000 including:
- $20,000 in tax increments.
- $100,000 in Community Development Block Grant funds for housing
development.
- $10,000 intergovernmental transfers.
ANTICIPATED EXPENDITURES
Expenditures for FY 88-89 are expected to be:
- $100,000 in housing subsidies.
- $30,000 in professional services.
INDEBTEDNESS
The Agency has incurred approximately $100,000 in debt as of June 30, 1988.
The major elements include:
- $75,000 to the County Flood Control District.
- $25,000 to the County General fund for advances from the County.
In addition the County will provide the Agency with certain administrative
services which will accrue as a debt against the Agency. These advances will
be repaid from tax increments as soon as practicable.
I
C) WEST PITTSBURG
ANTICIPATED REVENUES
The West Pittsburg Project Area will not receive its initial tax increments
until FY 89-90. Approximately $20,000 in County advances for administrative
services are expected.
ANTICIPATED EXPENDITURES
Expenditures of approximately $20,000 are expected for professional services.
INDEBTEDNESS
The Agency has incurred approximately $68,000 in debt as of June 30, 1988, in-
cluding:
- $53,000 to the County Flood Control District.
$15,000 to the County General fund for advances from the County.
cd8/bwkprog.doc
i
i
WORK PROGRAM FOR FISCAL YEAR 1988-89
The work program of the Contra Costa Redevelopment Agency forlFiscal Year
1988-89 is directed at continuing the implementation of the Pleasant Hill BART
Station Area Redevelopment Plan and Specific Plan, the initial implementation of
recently adopted Redevelopment Plans for North Richmond and West Pittsburg, and
the evaluation of the potential for redevelopment in other areas of the County.
Specific goals, objectives and tasks of the Agency for Fiscal Year 88-89 are
outlined below:
I . Pleasant Hill BART Station Redevelopment Project Area:
Goal 1: Secure necessary financing to implement the Plan.
- A. Secure funds from developers under terms of Disposition and
Developer Agreements (DDA's) .
B. Continue property transfers as appropriate to expedite
receipt of payments.
C. Continue to collect reimbursements from developers as called
for in DDA's and from utility companies as called for in
undergrounding agreements.
Goal 2: Complete the Assemblage of Specific Plan Development Areas.
A. Finalize Disposition and Development Agreements (DDA's) for
Development Areas 3, 4 and 10A, and amend DDA for
Development Areas 7A, 7B and 8.
B. Complete the acquisition of remaining parcels within the
Project Area required to complete development areas.
C. Complete vacation and abandonment proceedings on County
rights-of-way held in fee.
D. Secure property dedications as necessary for planned road
improvements.
Goal 3: Continue access and infrastructure improvements necessary to
allow construction to begin and to serve completed buildings.
A. Continue to transfer property as necessary to facilitate
road and public improvements.
B. Secure property dedications as specified in DDA's or de-
velopment approvals.
C. Initiate condemnation action where necessary.
D. Complete negotiations and secure title to remaining
privately-held portion of Souther Pacific right-of-way,
necessary to ensure availability of right of way for major
traffic arterial . {
E. Evaluate need for new rights-of-way and, if necessary,
acquire either through dedication or condemnation.
F. Complete construction of the following improvements:
- Cherry Lane widening
- Median landscaping and related improvements
- Coggins Drive Safety Path
G. Initiate environmental documentation, design and engineering
necessary to establish a commuter bike trail along the
Southern Pacific right-of-way.
Goal 4: Continue to evaluate Specific Plan Implementation.
A. Continue to develop Transportation Systems Management
Program.
1. Coordinate with Developers Association for program
development.
2. Coordinate the implementation of TSM with the
completion and occupancy of building.
3. Explore and evaluate new TSM measures.
B. Monitor development of child care facilities and programs.
C. Assess alternative mechanisms for financing additional
traffic improvements such as the roadway in the SP right of
way, and other improvements that may be appropriate to
enhance traffic conditions on major arterials.
II . North Richmond Redevelopment Project Area:
Goal 1. Implementation of the North Richmond Redevelopment Plan.
A. Monitor and provide support for private development within
the Project Area.
B. Continue to work with the Project Area Committee in
implementing the Plan.
C. Complete seven unit infill housing project and initiate
other infill housing activities.
D. Assist in the preparation and review of a General Plan
revision for the North Richmond area.
Goal 2. Monitor related public improvements in the Project Area.
A. Continue to support the North Richmond By-pass and the work
of the Route 93 committee.
B. Monitor progress of the Wildcat and San Pablo Creeks Flood
Control Projects.
III . West Pittsburg Redevelopment Project Area:
i
Goal 1. Implementation of the West Pittsburg Redevelopment Plan.
A. Work with the Project Area Committee in formulating and
implementing the Plan.
B. Monitor and provide support for private development within
the Project Area.
C. Pursue and participate in the utilization of other funds
that will facilitate public and private activity in the
project area.
IV. Other Redevelopment Activities:
Goal 1: Hire additional staff to assist in adoption and/or
implementation of three Redevelopment Projects: Pleasant Hill
BART, North Richmond and West Pittsburg.
Goal 2: Recommend-adoption of the Oakley Redevelopment Plan by the end of
the Fiscal Year.
Goal 3: Study other potential redevelopment areas.
A. Conduct preliminary studies to evaluate the possibility of
utilizing redevelopment in the following areas:
1. Crockett
2. Tara Hills
3. Bethel Island
4. Rodeo
B. Establish survey areas in the above areas if appropriate.
Goal 4: Provide continued support to County Administration in monitoring
existing and proposed city redevelopment projects.
cd8/wkprg889.doc
EXAMINATION OF ACHIEVEMENTS FOR
FISCAL YEAR 1987-88
The Redevelopment Agency, during Fiscal Year 1987-1988, continued to implement
the Pleasant Hill BART Station Redevelopment Plan. Substantial progress was
made in infrastructure and public improvements. The Agency completed the
adoption process for Redevelopment Plans for the North Richmond and West
Pittsburg Areas, and took initial steps towards adopting a Oakley Plan.
Specifically, the Agency accomplished the following:
I . Pleasant Hill BART Redevelopment Project Area
A. Development: The Agency completed the Disposition and Development
Agreements (DDA's) for Area 10B South for a hotel . During the fiscal
year an additional 50,000 square feet of office space was completed in
development area 1B.
B. Property Acquisition: The acquisition of property necessary to create
developable areas was nearly completed this fiscal year. Presently
only one parcel remains to be acquired to complete site assemblies.
C. The Agency completed the sale of its $7.5 million Tax Allocation
notes. The Agency utilized approximately $4 million of the proceeds
to retire a debt to the Southern Pacific Transportation Company.
D. Infrastructure Improvements: During the fiscal year the Agency
substantially completed infrastructure and ci-rculation improvements.
The Treat Boulevard, Oak Road, Wayne Drive, and Las Juntas Way
improvements were completed and operational . Associated utility and
drainage improvements were completed. A Phase II-A Study, a
requirement of the Specific Plan, to investigate signal coordination,
and other traffic improvements was initiated.
E. Plan Amendment: Substantially all of the work required to amend the
Pleasant Hill BART Station Redevelopment Plan (and related General
Plan and Specific Plan amendments) to add Area 3 as ,a high density
multi-family housing site was accomplished. The amended plan will be
considered early in Fiscal Year 1988-89.
F. Plan Review: Agency staff were lead staff in conducting a review of
the Pleasant Hill BART Station Area Specific Plan. Working with the
Pleasant Hill BART Steering Committee, the Agency completed and
reviewed additional studies relative to traffic conditions,
comparative traffic mitigation measures, and the origin/destination of
traffic. Additional traffic mitigation measures were identified and
will be evaluated for technical and economic feasibility.
II . North Richmond Redevelopment Project Area
The Agency moved ahead with the adopted Redevelopment Plan to the North
Richmond Area during Fiscal Year 1987-1988. A Project Area Committee
continues to work with staff to implement the plan. The Agency initiated
its first infill housing project. The Agency has acquired the land and has
circulated a request for qualifications for a developer. A selection will
be made early in FY 88-89.
III . West Pittsburg Redevelopment Project Area.
The adoption of a West Pittsburg Redevelopment Plan occured in Fiscal Year
1987-1988. A Project Area Committee continues to work with staff in
implementing the Plan.
IV. Other Redevelopment Activities.
Staff began to evaluate the potential for redevelopment in other areas of
the County during the fiscal year. The Oakley area received the most
attention. Staff continued to support the Administrator's office in the
evaluation of city redevelopment projects.
cd8/wkprg889.doc
• • Item 1 .79
3/28/89
CONTRA COSTA COUNTY REDEVELOPMENT AGENCY
TO: Redevelopment Agenc \., DATE: March 23, 1989
,
FROM: Jim Kennedy
Deputy Director Redevelopment
SUBJECT: Budget Message
The purpose of this memorandum is to provide a short summary of activities
contemplated by the Redevelopment Agency's 1988-89 proposed budget that will be
before you on March 28th. The major activities include:
1. Public Works activities: including the completion of infrastructure
improvements started in prior fiscal years. Activities include the
widening of Cherry Lane, median landscaping, a safety path on Coggins
Lane and initial design and engineering relative to the Commuter Bike
Trail .
2. Property acquisition: This activity consists of two major elements.
First the acquisition of properties within Area 3 in order to
facilitate the development of the Park Regency project. All revenue
necessary for the acquisition of these properties will be provided by
the private developer. The second element is the acquisition of the
Hookston Station area. This represents the last privately held piece
of the Southern Pacific Right-of-Way. Acquisition is necessary in
order to provide for the Bancroft extension. Staff is currently
negotiating with the owner of this piece and would intend to reach a
negotiated settlement prior to the end of the 88-89 fiscal year.
3. Retirement of long term debt: Agency debt as of June 1988 is
approximately $12.5 million. Approximately $3.7 million is due to the
County General Fund or to the County for property conveyances. An
additional $1.3 million is due to Assessment District 83-1 for an
advance from its TSM funds. The proposed budget would contemplate
repayment of the principle amount due to Assessment District 83-1 ($1
million) and a portion of the amount due to the County for property
conveyances. The amount that the Agency will be able to repay the
County will be determined by the price of the Hookston Station
property. Under a worse case scenario, it is anticipated that the
Agency would be able to pay the County approximately $500,000. Should
our negotiations with the owners of the Hookston Station result in a
price or property configuration that reduces our cost, this amount
could increase.
4. Debt service on a tax allocation notes: In December of 1987 the Agency
issued $7.5 million in tax allocation notes. Debt service on these
notes is $450,000 per year.
5.- Project professional services: Agency staff, legal expenses,
consultants, other County departments and miscellaneous expenses all
occur as part of the professional services part of the budget.
cc: Phil Batchelor
Harvey 3ragdon
i
I
1
i
i
jk3/jb/redagcy.mem