TO: BOARD OF SUPERVISORS
FROM: J. .MICHAEL WALFORD, PUBLIC WORKS DIRECTOR
DATE: March 14 , 1989
SUBJECT: APPROVAL of Contract Change Order No. 4 for
the Pleasant Hill Road Slide Repair, Project No.
0671-6R6775-86 in the Walnut Creek area.
Specific Request(s) or Recommendation(s) & Background &
Justification
RECOMMENDED ACTION:
APPROVE Contract Change Order No. 4, and
AUTHORIZE the Public Works Director to execute Contract Change
Order No. 4 in the approximate amount of $950. 00 to compensate the
contractor, L & S General Contractors, for miscellaneous changes
in the planned work.
FINANCIAL IMPACT:
The Project Contingency Funds are sufficient to cover the change ,
order costs. Total project costs are 100% reimburseable under the
Federal Highway Administration Emergency Repair Program.
REASONS FOR RECOMMENDATION/BACKGROUND:
Modifications were required in the guardrail. This contract
change order provides for those changes.
Because this change order and previously approved change orders
collectively exceed $25, 000. 00 Board approval is required.
CONSEQUENCES OF NEGATIVE ACTION:
The lack of approval would preclude payment for work required to
complete the repair of the slide.
c
Continued oni"at'tachment: yes Signature- � / N
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other:
Signature s :
Action of Board on: MARI 41984
Approved as Recommended Other
Vote of Supervisors I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
_
Unanimous(Absent AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: ', BOARD OF SUPERVISORS ON DATE SHOWN.
Absent: Abstain:
Attested MAR 19: 19$9
Orig. Div. : PW(Constr) Phil Batchelor
cc: County Administrator Clerk of the Board of
Auditor-Controller Supervisors and County
Public Works-Design Administrator
Accounting
R. Bruno
Contractor
DG/sa Byr �l '�A DEPUTY
bo: 14 .t3