SPECIFIC REQUEST(S) OR RECOMMENDATIONS(S) & BACKGROUND AND JUSTIFICATION
RECOMMENDATION
Approve sunset date of June 30, 1989 for Bethel Island Specific
Plan Advisory Committee.
BACKGROUND
The Board requested tie Community Development Department to provide
a schedule for completion of the Bethel Island Area Specific and a
recommendation for an. appropriate sunset date for the Bethel Island
Area Specific Plan Advisory Committee. The schedule is attached
and was approved by the Board within the contractual agreement with
Sun Charter, Inc. at your February 28 , 1989 meeting. All work on
the plan is expected to be completed by the Board the week of June
27 , 1989, therefore, it is recommended that June 30, 1989 be the
appropriate sunset date for the Committee.
CONTINUED ON ATTACHMENT: YES SIGNATURE-
RECOMMENDATION OF COUNTY ADMINISTRATOR RECO I N OF1$OATWC-0MjLTTEz
APPROVE OTHER
SIGNATURE(S) :
ACTION OF BOARD ON March 14, 1989 APPROVED AS RECOMMENDED x OTHER '
VOTE OF SUPERVISORS
I HEREBY CERTIFY THAT THIS IS A
x UNANIMOUS (ABSENT zzz ) TRUE AND CORRECT COPY OF AN
AYES: NOES: ACTION TAKEN AND ENTERED ON THE
ABSENT: ABSTAIN: MINUTES OF THE BOARD OF
SUPERVI SORSON THE DATE SHOWN.
cc: Community Development (Orig. ) ATTESTED /4 f98'9
John Everts, CDD -- PHIL BATCHELOR, CLERK OF
County Administrator THE BOARD OF SUPERVISORS
AND COUNTY ADMINISTRATOR
BY b , DEPUTY
i
BETHEL ISLAND AREA SPECIFIC PLAN TIME LINE
Jan. 27 Transmit public hearing notes to Antioch Ledger
Feb. 1 Deliver DEIR to State Clearinghouse (Notice of Completion)
45 day review period begins
Feb. 13 ECRPC Study Session on BIASP
Feb. 27 ECRPC Hearing on DEIR
March 17 End of 45 day period
April 7 Receive Admin. draft of Final EIR Response Document
April 10 Arrange printing
April 13 Return comments to consultant
April 20 Receive camera-ready copy of FEIR - Transmit to printer
April 27 Receive FEIR from printer-distribute document draft findings
May 1 ECRPC-Certify EIR
Hearing on BIASP
May 8 ECRPC-Hearing on BIASP
May 15 ECRPC-Final action on plan
May 16 Schedule before Board of Supervisors
May 22 ECRPC-Adoption of findings
June 20 BOS-Hearings on BIASP
June 27 BOS-Final Action
June 28 File N.O.D.
August 1 Close of N.O.D. Challenge Period
jeanl:bitime.aga