HomeMy WebLinkAboutMINUTES - 03141989 - 1.16 TO: BOARD OF SUPERVISORS, as the Governing Body of the
Contra Costa County Flood Control and Water Conservation
District
FROM: J. MICHAEL WALFORD, CHIEF ENGINEER
DATE: March 14, 1989
SUBJECT: San Ramon Creek Bypass
Project No. : 7520-6B8636 Task: ACQ Account: 3540
SPECIFIC REQUEST(S) OR RECOMMENDATIONS) & BACKGROUND AND
JUSTIFICATION
I. Recommended Action:
APPROVE Right of Way Contract and ACCEPT Temporary
Construction Easement dated February 23, 1989 from Lori Lee
Talbot, et al.
AUTHORIZE Chief Engineer to execute said Right of Way
Contract on behalf of the District. Said Right of Way
contract includes payment for an additional temporary
construction easement to the Central Contra Costa Sanitary
District for sewer relocation work required as a result of
the County Flood Control project.
APPROVE payment of $4,000. 00 for said property rights and
AUTHORIZE the, Auditor-Controller to issue a check in said
amount payable to Lori Lee Talbot, James E. Aigeltinger,
Joanne M. Aigeltinger, Mariano Jimenez, Serina E. Jimenez,
Lori L. Takahashi, Joseph H. Mattare Jr. , Mark W. Moffett,
and Patricia R. Stewart to be forwarded to the Real Property
Division for delivery.
4
Cont'd on Attachment: X yes Signature
Recommendation of County Administrator
Recommendation of Board Committee
Approve Other
Signature(s)
1
Action of Board on MAR 14 1989
Approved as recommended X Other
I
Vote of Supervisors
_ Unanimous (Absent -137- ) I HEREBY CERTIFY THAT THIS
Ayes: Noes: IS A TRUE AND CORRECT COPY
Absent: Abstain: OF AN ACTION TAKEN AND
ENTERED ON THE MINUTES OF
THE BOARD OF SUPERVISORS ON
DATE SHOWN.
ATTESTED MAR 14 1989
PHIL BATCHELOR, Clerk of
the Board of Supervisors
and County -Administrator
BY
DEPUTY
Orig. Div: Public Works (R/P)
cc: County Administrator
Auditor-Controller (via R/P)
P. W. Accounting
Recorder (via R/P)
II. Financial Impact:
Payment of $4,000 from project funds which are 100%
reimbursable by the Department of Water Resources.
III. Reasons for Recommendations:
These property rights are required for the San Ramon Creek
project in accordance with approved plans and
specifications.
IV. Consequences of Negative Action:
The project will not have sufficient land rights to allow
construction in accordance with the approved plans and
specifications.
RB:cw
BO: 12 .sanramon.t2