TO: REDEVELOPMENT AGENCY
FROM: PHIL BATCHELOR, EXECUTIVE DIRECTOR
DATE: June 7 , 1988
SUBJECT: APPROVE Contract Change Order No. 2 for the Pleasant
Hill BART Station Area Landscaping, Project No. 7891-
6X5559-85.
Specific Request(s) or Recommendation(s) & Background &
Justification
RECOMMENDED ACTION:
APPROVE Contingency increase of $50, 000, and
AUTHORIZE the Chief Engineer to execute Contract Change Order No.
2 to Mori Hatsushi and Associates, Inc. of Concord, in the
amount of $47, 038, to provide for changes in the planned work for
Pleasant Hill BART Landscaping. Project No. 7891-6X5559-85.
FINANCIAL IMPACT:
Funds are available from the tax increment and development fees
for the Pleasant Hill BART Specific Plan area.
Continued on attachment: x yes Signature:
Cr,
Recommendation of Executive Director
Recommendation of Agency Committee
Approve Other:
Signatures)
Action of Agency on: June 7, 1988
Approved as Recommended--_X_ Other
vote of Commissioners I HEREBY CERTIFY THAT THIS IS A TRUE
AND CORRECT COPY OF AN ACTION TAKEN
X Unanimous(Absent_ ) AND ENTERED ON THE MINUTES OF THE
Ayes: Noes: REDEVELOPMENT AGENCY ON DATE SHOWN.
Absent: Abstain:
Attested June 7, 1988
Orig. Div. : Redevelopment (Const) Phil Batchelor
cc: Redevelopment Director Agency Secretary
Auditor-Controller
Chief Engineer
By 11,10
DEPUTY
LT/sa
bo: 7 .t6
REASONS FOR RECOMMENDATION/BACKGROUND:
The Agency is installing landscaping within the medians of
Pleasant Hill BART Specific Plan area. This contract change
order provides for extension of the median landscaping in Treat
Boulevard between Jones Road and Cherry Lane. This Change order
provides for compensation to the contractor for which are
required to complete the project.
Because this change order exceeds $25, 000, Agency approval is
required.
CONSEQUENCES OF NEGATIVE ACTION:
Failure to approve the change order will delay construction of
the improvments as well as impact public access to the Pleasant
Hill BART Station.
I CONTRA COSTA-COUNTY
C-3 REVS(:D(85)x-22 PUBLIC WORKS DEPARTMENT SHEET 1 OF 1
CONTRACT CHANGE ORDER NO. _2 REV.NO. SUPPL NO.
ROAD NAME W.O.NO. PROJECT NO. DATE
Pleasant Hill BART
Station Area - Landscaping 5559 7891-6X5559-85 May 19, 1988
TO: Mori Hatsu shi and Associates CONTRACTOR. Change reested by Resident Engineer
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications
on this contract.
NOTE:This change order is not effective until approved by the Deputy Public Works Director,Operations and Flood Control,
I. CHANGE IN PLANS - EXTRA WORK AT AGREED PRICE:
Install irrigation and landscaping on Treat Boulevard between Jones Road an Cherry
Lane, per David Gates plan.
Agreed Price $47,038.00
The contractor agrees to accept $47,038.00 as full compensation for all the work
described above, and no additional compensation will be allowed therefor.
By signature below, ;Clb tor indicates aooeptap a of pride staged ,hlerein as full
coMmsatioln for -ail -direct and -inc7irec costs far all work c�ribed. above ;and:as
full c�pI rig -i rn fczr any effects this charge may bave prop ' i e atirety
and/or on the-time rmpired to aouplete the project.
bla2.t5
y
Akl
),,
ESTIMATED COST:DECREASE$ INCREASE$ 47.038.00 _
BY REASON OF THIS CHANGE -0^ WORKING DAYS EXTENSION OF TIME WILL BE ALLOWED.
We,the undersigqned contractor,have given careful consideration to the change proposed and hereby agree,if this proposal is approved,that we will provide all equipment,
furnish all matenats,except as may otherwise be noted above,and perform all services necessary for the work above specified,and will accept as full payment therefor
the prices shown above.
SUBMITTED: RECOMMENDED:
RESIDENT ENGINEER ASSISTANT PUBLIC WORKS DIRECTOR,
CONSTRUCTION DIV.
ACCEPTED BY CONTRACTOR DATE APPROVED—DEP.PUBLIC WORKS DIR, DATE
OPERATIONS&FLOOD CONT.
If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered
work and filing a written protest within the time therein specified.
AUDITOR